Tensioning Guide
Belt-diagram
C-120 pulleys
+ 13 more
Pre-built workflows to keep your asset running smoothly.
Daily Electrical System Inspection
Replace Roller and Pulley
Install Engine B-120
+ 29 more
Integrate maintenance plans directly into your work orders.
Motion Industries
Applied Industrial Technologies
Electrical Brothers
+ 5 more
Access the parts list for your equipment in MaintainX.
Drive Motor
B2 Rollers
Tensioning System
+ 40 more

Triangle Tube Gas Condensing Boiler Prestige Solo 175
Create an account to install this asset package.
Integrate maintenance plans directly into your work orders in MaintainX.
Boiler System Check
Verify all system components are correctly installed and operating properly
Pressure Checks
Enter the cold fill pressure for the system
Is the system pressure within the normal range (not exceeding 25 psig)?
Air Vent and Separator Inspection
Inspect air vent and air separators for leaks
Replace any leaking vents
Boiler Fluid and Chemical Analysis
Verify boiler fluid pH level
Ignition Cable / Ground Wiring Check
Inspection of Ignition Cable and Ground Wiring
Inspect the following components for good condition and secure connection
Ground Continuity Check
Check ground continuity using a continuity meter
Is the ground continuity satisfactory?
Replace ground wire if ground continuity is not satisfactory
Burner Area Inspection
Preparation
Remove the boiler front jacket panel and venturi inlet elbow
Cleaning
Vacuum any dirt or debris from the burner/blower components
Inspection
Check the burner plate mounting nuts for tightness
Check burner plate gasket for discoloration or damage
Check for flue gas leakage at the condensate pan and internal vent pipe
Reassembly
Boiler Replacement
Pre-Installation Checks
Check and correct the following items before installation
Burner Flame Check
Flame Inspection
Inspect the flame pattern through the observation port of the heat exchanger.
Is the flame pattern fully blue and covering the entire burner surface during high fire?
Shutdown and Disassembly
Shut the unit down and allow it to cool thoroughly before disassembly.
Close the external manual gas valve on the gas supply line.
Disconnect the gas piping and gas valve wire harness connector.
Disconnect the wiring harness connectors from the blower.
Remove the blower clamp and blower from the unit.
Access the parts list for your equipment in MaintainX.
Front Jacket Panel (With Insulation)
PAJKT01
Left Side Jacket Panel (With Insulation)
PAJKT03
Right Side Jacket Panel (With Insulation)
PAJKT21
Top Panel
PAJKT12
Wall Mounting Bracket With Hardware
PSRKIT21
Front Jacket Panel (With Insulation)
PAJKT01
Left Side Jacket Panel (With Insulation)
PAJKT03
Right Side Jacket Panel (With Insulation)
PAJKT21
Top Panel
PAJKT12
Wall Mounting Bracket With Hardware
PSRKIT21
Front Jacket Panel (With Insulation)
PAJKT01
Left Side Jacket Panel (With Insulation)
PAJKT03
Right Side Jacket Panel (With Insulation)
PAJKT21
Top Panel
PAJKT12
Wall Mounting Bracket With Hardware
PSRKIT21
MaintainX CoPilot is your expert colleague, on call 24/7, helping your team find the answers they need to keep equipment running.
Reduce Unplanned Downtime
Ensure your team follows consistent procedures to minimize equipment failures and costly delays.
Maximize Asset Availability
Keep your assets running longer and more reliably, with standardized maintenance workflows from OEM manuals.
Lower Maintenance Costs
Turn any technician into an expert to streamline operations, maintain more assets, and reduce overall costs.
Thousands of companies manage their assets with MaintainX