MaintainX Asset Hub logo
EnterprisePricing
Miura

Miura Steam Boiler LX-200

Need answers fast?
Explore the manual using AI.

Miura Steam Boiler LX-200
Miura Steam Boiler LX-200

Turn manuals into instant answers
with your AI-powered assistant
Turn manuals into instant answers
with your AI-powered assistant

PDF MANUAL

Manual for Miura Steam Boiler LX-200

MAINTENANCE RESOURCES

Complete asset maintenance, one click away

Get instant access to all the maintenance information you need. Empower technicians to perform preventive maintenance with asset packages, ready to use right out of the box.

Documents

Documents & Manuals

Find all the essential guides in one place.

  • CheckTensioning Guide

  • CheckBelt-diagram

  • CheckC-120 pulleys

  • + 13 more

Work Orders

Work Order Templates

Pre-built workflows to keep your asset running smoothly.

  • CheckDaily Electrical System Inspection

  • CheckReplace Roller and Pulley

  • CheckInstall Engine B-120

  • + 29 more

Procedures

Procedures

Integrate maintenance plans directly into your work orders.

  • CheckMotion Industries

  • CheckApplied Industrial Technologies

  • CheckElectrical Brothers

  • + 5 more

Parts

Parts

Access the parts list for your equipment in MaintainX.

  • CheckDrive Motor

  • CheckB2 Rollers

  • CheckTensioning System

  • + 40 more

Miura Steam Boiler LX-200

Miura Steam Boiler LX-200

Create an account to install this asset package.

Maintenance Plans for Miura Steam Boiler Model LX-200

Integrate maintenance plans directly into your work orders in MaintainX.

1 Daily Chemical Feed Check

Check mark

Warning: No work other than that clearly indicated below is to be carried out on the boiler. Failure to observe this precaution may result in injury.

Check mark

Checking the Chemical Feeder

Check mark

Confirm that the chemical feed is as required.

Check mark

Confirm that sufficient liquid is present to properly dissolve chemicals.

Check mark

Confirm that there is no air in the chemical feed pump or feed line.

Check mark

Warning: Protective glasses and rubber gloves must be worn when adding chemical compounds. These compounds may cause sight loss, burns, and other injuries when they contact with skin or eyes.

Check mark

If boiler chemical comes into direct contact with skin, immediately wash away using cold water.

Check mark

If this chemical enters an eye, immediately wash away with cold water and seek medical attention.

Check mark

Always follow the instructions of your water treatment personnel in terms of chemical dosage.

Run this procedureArrow right

1 Daily Gas Pressure Check

Check mark

Warning: No work other than that clearly indicated below is to be carried out on the boiler. Failure to observe this precaution may result in injury.

Check mark

Open the main gas valve

Check mark

Using the boiler’s gas pressure gauge, confirm whether the gas is pressurized to the required range (i.e., 3 to 5 PSI)

Check mark

If the reading on the gas pressure gauge is not within the required range, immediately shutdown the boiler

Check mark

If the reading on the gas pressure gauge is not within the required range, contact a MIURA sales office or your local dealer for further instruction.

Check mark

Sign off on the daily gas pressure check

Run this procedureArrow right

1 Daily Low Water Level Interlock Test

Check mark

Warning: No work other than that clearly indicated below is to be carried out on the boiler. Failure to observe this precaution may result in injury.

Check mark

Low Water Level Interlock Test

Check mark

If the water volume, for any reason, falls below the pre-determined water volume, combustion will immediately be stopped and if it is not recovered after 15 sec after combustion shutoff, a warning alarm will be activated. The display will read, “WATER ALARM 1”.

Check mark

Open the ball valve at the bottom of the LVC and allow time for the steam pressure to force the water out of the LVC.

Check mark

When the low water cut-off probe loses contact with the water for more than 15 seconds, the boiler will shift to stand-by mode first and shut down 15 seconds, the alarm will sound and the BL11 Microcomputer will display “WATER ALARM 1”.

Check mark

Sign off on the Low Water Level Interlock Test

Run this procedureArrow right

1 Daily Steam Boiler Maintenance

Check mark

Warning!

Check mark

No work other than that clearly indicated below is to be carried out on the boiler. Failure to observe this precaution may result in injury.

Check mark

To keep your MIURA boilers running in optimum condition, be sure to check the following daily:

Check mark

a) CHEMICAL FEED PUMP

Check mark

i. Proper chemical feed.

Check mark

ii. No air in the chemical feed pump or lines.

Check mark

b) WATER SOFTENER

Check mark

i. Boiler Make-up water is completely soft (use a test kit sensitive to less than 1.0 PPM).

Check mark

ii. Make sure the water softener timer or softener flow meter is working every day.

Run this procedureArrow right

1 Daily Steam Pressure Check

Check mark

Warning: No work other than that clearly indicated below is to be carried out on the boiler. Failure to observe this precaution may result in injury.

Check mark

Startup the boiler as described in Section 8.1: Boiler Startup.

Check mark

Confirm that the reading on the steam pressure gauge is in the normal range, and that the gauge pointer is not swinging wildly.

Check mark

Warning: If the steam pressure is not within the normal range, immediately shutdown the boiler and contact a MIURA sales office or your local dealer for further instruction. Continued use of the boiler with abnormal steam pressure levels may result in boiler damage, which in turn could lead to injury.

Check mark

Sign off on the daily steam pressure check

Run this procedureArrow right

Unlock efficiency
with MaintainX CoPilot

MaintainX CoPilot is your expert colleague, on call 24/7, helping your team find the answers they need to keep equipment running.

Time Lapse Icon

Reduce Unplanned Downtime

Ensure your team follows consistent procedures to minimize equipment failures and costly delays.

Wrench Clock Icon

Maximize Asset Availability

Keep your assets running longer and more reliably, with standardized maintenance workflows from OEM manuals.

Dollar Coin Icon

Lower Maintenance Costs

Turn any technician into an expert to streamline operations, maintain more assets, and reduce overall costs.

Thousands of companies manage their assets with MaintainX

DuracellAB InBevErgonTitan AmericaMeritUnivar SolutionsRivianCadrexMagnaMaasPresriteSoutheast PowerInterrollDuracellAB InBevErgonTitan AmericaMeritUnivar SolutionsRivianCadrexMagnaMaasPresriteSoutheast PowerInterroll

More from Miura

Explore Other Assets