MaintainX Asset Hub logo
EnterprisePricing
CDR Pompe

CDR Pompe Pump UCL 125-80-200 50 Hz

Need answers fast?
Explore the manual using AI.

CDR Pompe Pump UCL 125-80-200 50 Hz
CDR Pompe Pump UCL 125-80-200 50 Hz

Turn manuals into instant answers
with your AI-powered assistant
Turn manuals into instant answers
with your AI-powered assistant

PDF MANUAL

Manual for CDR Pompe Pump UCL 125-80-200 50 Hz

MAINTENANCE RESOURCES

Complete asset maintenance, one click away

Get instant access to all the maintenance information you need. Empower technicians to perform preventive maintenance with asset packages, ready to use right out of the box.

Documents

Documents & Manuals

Find all the essential guides in one place.

  • CheckTensioning Guide

  • CheckBelt-diagram

  • CheckC-120 pulleys

  • + 13 more

Work Orders

Work Order Templates

Pre-built workflows to keep your asset running smoothly.

  • CheckDaily Electrical System Inspection

  • CheckReplace Roller and Pulley

  • CheckInstall Engine B-120

  • + 29 more

Procedures

Procedures

Integrate maintenance plans directly into your work orders.

  • CheckMotion Industries

  • CheckApplied Industrial Technologies

  • CheckElectrical Brothers

  • + 5 more

Parts

Parts

Access the parts list for your equipment in MaintainX.

  • CheckDrive Motor

  • CheckB2 Rollers

  • CheckTensioning System

  • + 40 more

CDR Pompe Pump UCL 125-80-200 50 Hz

CDR Pompe Pump UCL 125-80-200 50 Hz

Create an account to install this asset package.

Maintenance Plans for CDR Pompe Pump Model UCL 125-80-200 50 Hz

Integrate maintenance plans directly into your work orders in MaintainX.

Pump Storage Maintenance

Check mark

3.5 Storage

Check mark

Ensure the pump is stored correctly

Check mark

Verify protection caps and lids of the flanges are on the pump

Check mark

Is the pump stored for a long period or in severe conditions?

Check mark

If stored for a long period or in severe conditions, ensure additional precautions are taken

Run this procedureArrow right

Pump Inspection

Check mark

9.1 Maintenance interval

Check mark

Confirm maintenance interval adherence

Check mark

9.2 Parts to be checked

Check mark

Bearing bracket (Code 330)

Check mark

Impeller (Code 230)

Check mark

Volute casing (Code 102) / Stuffing box housing (Code 451)

Check mark

Check components for replacement

Check mark

9.3 Bearing bracket and bearing life

Check mark

Measure vibrations

Run this procedureArrow right

Pump Startup Check

Check mark

5.1 Pre-start checklist

Check mark

Ensure the following pre-start conditions are met

Check mark

Is the suction pipe filled and foot valve working properly?

Check mark

Verify motor and pump conditions

Check mark

Is the liquid temperature maintained to prevent crystallization or solidification?

Check mark

Check auxiliary connections

Check mark

Is the oil level adequate for pumps with oil lubricated bearing bracket?

Check mark

5.2 Mechanical seal

Check mark

Ensure operating and functional parameters of the mechanical seal are followed as per Data Sheet

Run this procedureArrow right

Pump Maintenance

Check mark

General Information

Check mark

Ensure the following safety measures are taken before maintenance

Check mark

Volute Casing Assembly

Check mark

Choose the method for removing the volute casing

Check mark

If removing the entire pump, perform the following steps

Check mark

If leaving the volute casing connected, perform the following steps

Check mark

Impeller Disassembly

Check mark

Perform the following steps for impeller disassembly

Check mark

Shaft Sleeve Disassembly

Run this procedureArrow right

2100 Hourly Oil Change

Check mark

9.4 Oil change

Check mark

Record the current bearing bracket temperature

Check mark

Is the bearing bracket temperature between 80°C and 90°C?

Check mark

Ensure the lubricant used has a viscosity of 46Cst

Check mark

Verify application limits and room temperature

Check mark

Monitor the bearing temperature for pumps in explosive environments

Check mark

Describe any observed excessive temperature increase

Run this procedureArrow right

Unlock efficiency
with MaintainX CoPilot

MaintainX CoPilot is your expert colleague, on call 24/7, helping your team find the answers they need to keep equipment running.

Time Lapse Icon

Reduce Unplanned Downtime

Ensure your team follows consistent procedures to minimize equipment failures and costly delays.

Wrench Clock Icon

Maximize Asset Availability

Keep your assets running longer and more reliably, with standardized maintenance workflows from OEM manuals.

Dollar Coin Icon

Lower Maintenance Costs

Turn any technician into an expert to streamline operations, maintain more assets, and reduce overall costs.

Thousands of companies manage their assets with MaintainX

DuracellAB InBevErgonTitan AmericaMeritUnivar SolutionsRivianCadrexMagnaMaasPresriteSoutheast PowerInterrollDuracellAB InBevErgonTitan AmericaMeritUnivar SolutionsRivianCadrexMagnaMaasPresriteSoutheast PowerInterroll

More from CDR Pompe

Explore Other Assets