Manual for York Centrifugal Chiller YKKPKPH95CKGS

MAINTENANCE RESOURCES

Complete asset maintenance, one click away

Get instant access to all the maintenance information you need. Empower technicians to perform preventive maintenance with asset packages, ready to use right out of the box.

Documents

Documents & Manuals

Find all the essential guides in one place.

  • CheckTensioning Guide

  • CheckBelt-diagram

  • CheckC-120 pulleys

  • + 13 more

Work Orders

Work Order Templates

Pre-built workflows to keep your asset running smoothly.

  • CheckDaily Electrical System Inspection

  • CheckReplace Roller and Pulley

  • CheckInstall Engine B-120

  • + 29 more

Procedures

Procedures

Integrate maintenance plans directly into your work orders.

  • CheckMotion Industries

  • CheckApplied Industrial Technologies

  • CheckElectrical Brothers

  • + 5 more

Parts

Parts

Access the parts list for your equipment in MaintainX.

  • CheckDrive Motor

  • CheckB2 Rollers

  • CheckTensioning System

  • + 40 more

York Centrifugal Chiller YKKPKPH95CKGS

York Centrifugal Chiller YKKPKPH95CKGS

Create an account to install this asset package.

Maintenance Plans for York Centrifugal Chiller Model YKKPKPH95CKGS

Integrate maintenance plans directly into your work orders in MaintainX.

1 Yearly Chiller Maintenance

Check mark

7.1.6 Annually (more often if necessary)

Check mark

Inspect and service electrical components as necessary

Check mark

7.8 Electrical Controls

Check mark

Inspect all electrical controls for obvious malfunctions

Check mark

Ensure factory settings of controls (operation and safety) are unchanged

Check mark

Perform chemical analysis of system

Run this procedureArrow right

1 Yearly Heat Exchangers Maintenance

Check mark

7.1.6 Annually (more often if necessary)

Check mark

Inspect and clean components

Check mark

7.5 Condenser and Evaporator

Check mark

Check for common water issues

Check mark

Is water treatment necessary?

Check mark

Recommendations for water treatment

Check mark

7.5.1 Chemical Water Treatment

Check mark

Has a chemical analysis of the water been conducted?

Check mark

Water treatment expert consultation notes

Run this procedureArrow right

Initial Chiller Startup Check

Check mark

5.1 Preparation

Check mark

Inspect unit for installation damage

Check mark

Check refrigerant charge and inspect for leaks

Check mark

Check oil system charge and oil level

Check mark

Verify single point of electrical isolation

Check mark

Check control panel for foreign materials and cleanliness

Check mark

Verify correct connection of customer power cables

Check mark

Verify proper earthing of unit and tightness of internal earth connections

Check mark

Verify site voltage supply corresponds to unit requirement

Run this procedureArrow right

Chiller Shutdown Maintenance

Check mark

6.8 Prolonged Shutdown

Check mark

Test all system joints for refrigerant leaks with a leak detector

Check mark

Were any refrigerant leaks found?

Check mark

Repair any detected refrigerant leaks before long-term shutdown

Check mark

Periodically check the tightness of the system during idle periods

Check mark

Drain water from cooling tower, condenser, condenser pump, chilled water system, chilled water pump, and coils if freezing temperatures are expected

Check mark

Open drains on evaporator and condenser liquid heads to ensure complete drainage

Check mark

Drain water from additional systems if applicable

Check mark

Disable the clock on the SETUP Screen to conserve battery

Run this procedureArrow right

Chiller Refrigerant Maintenance

Check mark

7.4.4 Refrigerant Charging

Check mark

Remove refrigerant charge when opening any part of the refrigerant system for repairs.

Check mark

Isolate refrigerant if chiller is equipped with optional valves.

Check mark

Add only refrigerant vapour to the system until pressure is above freezing point of evaporator liquid.

Check mark

Ensure system pressure is above 58.9 kPa for R134a at sea level.

Check mark

Prevent moisture laden air from entering the system during charging.

Check mark

Make up a suitable charging connection from new copper tubing.

Check mark

Ensure charging connection is purged each time a new container of refrigerant is connected.

Check mark

Change containers quickly to minimise refrigerant loss.

Run this procedureArrow right

Parts for York Centrifugal Chiller YKKPKPH95CKGS

Access the parts list for your equipment in MaintainX.

Part Name
Part Number

Heat Conductive Compound

013-00890-000

Oil Charging Pump

070-10654

Heat Conductive Compound

013-00890-000

Oil Charging Pump

070-10654

Heat Conductive Compound

013-00890-000

Oil Charging Pump

070-10654

Unlock efficiency
with MaintainX CoPilot

MaintainX CoPilot is your expert colleague, on call 24/7, helping your team find the answers they need to keep equipment running.

Time Lapse Icon

Reduce Unplanned Downtime

Ensure your team follows consistent procedures to minimize equipment failures and costly delays.

Wrench Clock Icon

Maximize Asset Availability

Keep your assets running longer and more reliably, with standardized maintenance workflows from OEM manuals.

Dollar Coin Icon

Lower Maintenance Costs

Turn any technician into an expert to streamline operations, maintain more assets, and reduce overall costs.

Thousands of companies manage their assets with MaintainX

DuracellAB InBevErgonTitan AmericaMeritUnivar SolutionsRivianCadrexMagnaMaasPresriteSoutheast PowerInterrollDuracellAB InBevErgonTitan AmericaMeritUnivar SolutionsRivianCadrexMagnaMaasPresriteSoutheast PowerInterroll

More from York

Explore Other Assets