MaintainX, an Autodesk company
EnterprisePricing
Frick

Frick Compressor Unit RXF-15

Need answers fast?
Explore the manual using AI.

Frick Compressor Unit RXF-15
Frick Compressor Unit RXF-15

Turn manuals into instant answers
with your AI-powered assistant
Turn manuals into instant answers
with your AI-powered assistant

PDF MANUAL

Manual for Frick Compressor Unit RXF-15

MAINTENANCE RESOURCES

Complete asset maintenance, one click away

Get instant access to all the maintenance information you need. Empower technicians to perform preventive maintenance with asset packages, ready to use right out of the box.

Documents

Documents & Manuals

Find all the essential guides in one place.

  • CheckTensioning Guide

  • CheckBelt-diagram

  • CheckC-120 pulleys

  • + 13 more

Work Orders

Work Order Templates

Pre-built workflows to keep your asset running smoothly.

  • CheckDaily Electrical System Inspection

  • CheckReplace Roller and Pulley

  • CheckInstall Engine B-120

  • + 29 more

Procedures

Procedures

Integrate maintenance plans directly into your work orders.

  • CheckMotion Industries

  • CheckApplied Industrial Technologies

  • CheckElectrical Brothers

  • + 5 more

Parts

Parts

Access the parts list for your equipment in MaintainX.

  • CheckDrive Motor

  • CheckB2 Rollers

  • CheckTensioning System

  • + 40 more

Frick Compressor Unit RXF-15

Frick Compressor Unit RXF-15

Create an account to install this asset package.

Maintenance Plans for Frick Compressor Unit Model RXF-15

Integrate maintenance plans directly into your work orders in MaintainX.

Compressor Unit Oil Change

Check mark

Maintenance Schedule

Check mark

Change Oil as directed by oil analysis

Check mark

Ensure oils of different brands, manufacturers, or types are not mixed

Check mark

Refer to the Changing Oil procedure in the manual for the full step-by-step process

Run this procedureArrow right

Initial 24 Hours Suction Strainer Cleaning

Check mark

Initial Start-Up Procedure

Check mark

Pull and clean suction strainer after 24 hours operation.

Check mark

Is the suction strainer excessively dirty?

Check mark

Repeat cleaning every 24 hours until system is clean if strainer is excessively dirty.

Check mark

Follow the Maintenance Schedule if strainer is not excessively dirty.

Run this procedureArrow right

6 Monthly Vibration Check

Check mark

Maintenance Schedule / Vibration Analysis

Check mark

Ensure continuous vibration measurement for optimal preventative control on bearings

Check mark

Check vibration levels

Check mark

Is the vibration measurement within acceptable limits?

Check mark

If vibration levels are not continuously controlled, ensure checks are done every 6 months or more frequently if levels increase

Run this procedureArrow right

5000 Hourly Compressor Unit Maintenance

Check mark

VFD Units Check

Check mark

Check VFD Units Skip Frequency

Check mark

Check for excess vibration and skip frequencies when operating conditions change

Check mark

Electrical Connections Check

Check mark

Check Electrical Connections

Check mark

Torque all terminals in the processor and starter panel as per specification

Check mark

Sensor Calibration Check

Check mark

Check Sensor Calibration

Check mark

Check calibration of

Run this procedureArrow right

5000 Hourly Suction and Discharge Flange Bolt Check

Check mark

Maintenance Schedule

Check mark

Check Suction & Discharge Flange Bolts at specified hours

Check mark

Verify tightness of bolts on suction and discharge flanges

Check mark

Flange Bolt Torque by RXF model (Motor Flange to Compressor Tunnel)

Check mark

Compressor Flange to Separator Flange Torque

Run this procedureArrow right

Parts for Frick Compressor Unit RXF-15

Access the parts list for your equipment in MaintainX.

Part Name
Part Number

Oil Analysis Kit

333Q0001853

Cable, Belden, For RS-422 Communications

9829

Cable, Belden, For RS-485 Up To 2000 Feet (600 Meters) Total Cable Length

9841

Optical Isolation Kit, Frick, One Kit Is Required Per Comm Port

639C0133G01

Oil Analysis Kit

333Q0001853

Cable, Belden, For RS-422 Communications

9829

Cable, Belden, For RS-485 Up To 2000 Feet (600 Meters) Total Cable Length

9841

Optical Isolation Kit, Frick, One Kit Is Required Per Comm Port

639C0133G01

Oil Analysis Kit

333Q0001853

Cable, Belden, For RS-422 Communications

9829

Cable, Belden, For RS-485 Up To 2000 Feet (600 Meters) Total Cable Length

9841

Optical Isolation Kit, Frick, One Kit Is Required Per Comm Port

639C0133G01

Unlock
efficiency with MaintainX Assist

MaintainX Assist is your expert colleague, on call 24/7, helping your team find the answers they need to keep equipment running.

Time Lapse Icon

Reduce Unplanned Downtime

Ensure your team follows consistent procedures to minimize equipment failures and costly delays.

Wrench Clock Icon

Maximize Asset Availability

Keep your assets running longer and more reliably, with standardized maintenance workflows from OEM manuals.

Dollar Coin Icon

Lower Maintenance Costs

Turn any technician into an expert to streamline operations, maintain more assets, and reduce overall costs.

Thousands of companies manage their assets with MaintainX

DuracellAB InBevErgonTitan AmericaMeritUnivar SolutionsRivianCadrexMagnaMaasPresriteSoutheast PowerInterrollDuracellAB InBevErgonTitan AmericaMeritUnivar SolutionsRivianCadrexMagnaMaasPresriteSoutheast PowerInterroll

More from Frick

Explore Other Assets