MaintainX Asset Hub logo
EnterprisePricing
Flowserve

Flowserve Pump 16-MFV-18

Need answers fast?
Explore the manual using AI.

Flowserve Pump 16-MFV-18
Flowserve Pump 16-MFV-18

Turn manuals into instant answers
with your AI-powered assistant
Turn manuals into instant answers
with your AI-powered assistant

MAINTENANCE RESOURCES

Complete asset maintenance, one click away

Get instant access to all the maintenance information you need. Empower technicians to perform preventive maintenance with asset packages, ready to use right out of the box.

Documents

Documents & Manuals

Find all the essential guides in one place.

  • CheckTensioning Guide

  • CheckBelt-diagram

  • CheckC-120 pulleys

  • + 13 more

Work Orders

Work Order Templates

Pre-built workflows to keep your asset running smoothly.

  • CheckDaily Electrical System Inspection

  • CheckReplace Roller and Pulley

  • CheckInstall Engine B-120

  • + 29 more

Procedures

Procedures

Integrate maintenance plans directly into your work orders.

  • CheckMotion Industries

  • CheckApplied Industrial Technologies

  • CheckElectrical Brothers

  • + 5 more

Parts

Parts

Access the parts list for your equipment in MaintainX.

  • CheckDrive Motor

  • CheckB2 Rollers

  • CheckTensioning System

  • + 40 more

Flowserve Pump 16-MFV-18

Flowserve Pump 16-MFV-18

Create an account to install this asset package.

Maintenance Plans for Flowserve Pump Model 16-MFV-18

Integrate maintenance plans directly into your work orders in MaintainX.

Pump Maintenance

Check mark

6.7 Disassembly

Check mark

Ensure safety and availability of parts

Check mark

6.7.1 Preliminary to dismantling

Check mark

Isolate motor and lock off electrical supply in accordance with local regulations.

Check mark

Isolate suction and discharge valves.

Check mark

Remove coupling guards and disconnect the coupling halves.

Check mark

Drain pump casing and remove any auxiliary piping if applicable.

Check mark

Lay out all parts in the order in which they are removed for convenience at re-assembly.

Check mark

Protect all machined faces against metal-to-metal contact and corrosion.

Run this procedureArrow right

Bearing Maintenance

Check mark

6.7.3 Bearing installation and removal

Check mark

Ensure proper fit is maintained during bearing installation

Check mark

Was a pulling device used to remove bearings from the shaft?

Check mark

Support the bearing cone with a split ring and press out the shaft using an arbor press

Check mark

Select the method used for mounting a bearing on the pump shaft

Check mark

Heat the bearing to a uniform temperature

Check mark

Quickly mount the heated bearing on the shaft

Check mark

Apply force using an arbor press if alternate method is used

Check mark

Ensure the cone is not cocked when forcing a bearing onto a shaft

Run this procedureArrow right

Impeller Clearance Check

Check mark

5.3 Impeller clearance

Check mark

Measure the current impeller clearance

Check mark

Is the impeller clearance within the nominal design range (0.25 to 0.50 mm)?

Check mark

Check for excessive wearing ring clearance

Check mark

Determine if the rings need renewal or overhaul

Check mark

Record any observations or issues found during the check

Run this procedureArrow right

Pump Startup Check

Check mark

5.1 Pre-commissioning procedure

Check mark

Ensure the following pre-commissioning checks are completed

Check mark

Fill pump bearings with recommended lubricant

Check mark

Check all vent connections for complete filling of the pump

Check mark

Verify the direction of rotation of the pump (Coupling spacer dismantled)

Check mark

Ensure pump rotor and shaft seal are in correct axial position

Check mark

Check readiness of all auxiliary systems (seal system, lubrication system) for startup

Check mark

Verify all pipe work is connected correctly and absolutely tight

Check mark

Ensure suction valve is open and discharge valve is closed or partially open as required

Run this procedureArrow right

Initial Pump Bearing Lubrication

Check mark

Pump Lubricants

Check mark

Determine the mode of lubrication of the pump set

Check mark

Are the grease lubricated pumps and electric motors pre-greased?

Check mark

Fill the bearing housing with correct grade of lubricant and to the correct quantity

Check mark

Bearings – Grease Lubricated

Check mark

Check the bearing frame cavities for grease and add grease as necessary before starting the pump

Check mark

Remove the grease fittings or pipe plug closest to the cover after start up to allow excess grease to flow out

Check mark

Monitor the bearing temperatures until they return to normal

Check mark

Is there any marked increase in the temperature of the bearings after return to normal operation?

Run this procedureArrow right

Unlock efficiency
with MaintainX CoPilot

MaintainX CoPilot is your expert colleague, on call 24/7, helping your team find the answers they need to keep equipment running.

Time Lapse Icon

Reduce Unplanned Downtime

Ensure your team follows consistent procedures to minimize equipment failures and costly delays.

Wrench Clock Icon

Maximize Asset Availability

Keep your assets running longer and more reliably, with standardized maintenance workflows from OEM manuals.

Dollar Coin Icon

Lower Maintenance Costs

Turn any technician into an expert to streamline operations, maintain more assets, and reduce overall costs.

Thousands of companies manage their assets with MaintainX

DuracellAB InBevErgonTitan AmericaMeritUnivar SolutionsRivianCadrexMagnaMaasPresriteSoutheast PowerInterrollDuracellAB InBevErgonTitan AmericaMeritUnivar SolutionsRivianCadrexMagnaMaasPresriteSoutheast PowerInterroll

More from Flowserve

Explore Other Assets