MaintainX Asset Hub logo
EnterprisePricing
Flowserve

Flowserve Pump 12-MFC-18

Need answers fast?
Explore the manual using AI.

Flowserve Pump 12-MFC-18
Flowserve Pump 12-MFC-18

Turn manuals into instant answers
with your AI-powered assistant
Turn manuals into instant answers
with your AI-powered assistant

MAINTENANCE RESOURCES

Complete asset maintenance, one click away

Get instant access to all the maintenance information you need. Empower technicians to perform preventive maintenance with asset packages, ready to use right out of the box.

Documents

Documents & Manuals

Find all the essential guides in one place.

  • CheckTensioning Guide

  • CheckBelt-diagram

  • CheckC-120 pulleys

  • + 13 more

Work Orders

Work Order Templates

Pre-built workflows to keep your asset running smoothly.

  • CheckDaily Electrical System Inspection

  • CheckReplace Roller and Pulley

  • CheckInstall Engine B-120

  • + 29 more

Procedures

Procedures

Integrate maintenance plans directly into your work orders.

  • CheckMotion Industries

  • CheckApplied Industrial Technologies

  • CheckElectrical Brothers

  • + 5 more

Parts

Parts

Access the parts list for your equipment in MaintainX.

  • CheckDrive Motor

  • CheckB2 Rollers

  • CheckTensioning System

  • + 40 more

Flowserve Pump 12-MFC-18

Flowserve Pump 12-MFC-18

Create an account to install this asset package.

Maintenance Plans for Flowserve Pump Model 12-MFC-18

Integrate maintenance plans directly into your work orders in MaintainX.

300 Hourly Pump Bearing Lubrication

Check mark

Recommended Grease Fill Quantities

Check mark

Select the frame for lubrication

Check mark

Enter re-lubrication quantity for Line Bearing (g)

Check mark

Enter re-lubrication quantity for Thrust Bearing (g)

Check mark

Grease Lubrication Procedure

Check mark

Connect grease gun to the nipple

Check mark

Press grease into the bearing housing until the first signs of it appear in the gap between the housing and shaft

Check mark

Record the operating temperature of the bearing housing (°C)

Check mark

Is the temperature rise above ambient within 55 °C (131 °F)?

Run this procedureArrow right

Pump Maintenance

Check mark

6.7 Disassembly

Check mark

Refer to section 1.6, Safety, before dismantling the pump

Check mark

Ensure genuine Flowserve replacement parts are available

Check mark

Refer to sectional drawings purchased for part reference numbers

Check mark

6.7.1 Preliminary to dismantling

Check mark

Isolate motor and lock off electrical supply in accordance with local regulations

Check mark

Isolate suction and discharge valves

Check mark

Remove coupling guards and disconnect the coupling halves

Check mark

Drain pump casing and remove any auxiliary piping if applicable

Run this procedureArrow right

Mechanical Seal Inspection

Check mark

5.8.3 Pumps fitted with mechanical seal

Check mark

Ensure no adjustment is made to the mechanical seal.

Check mark

Is there any initial leakage from the mechanical seal?

Check mark

Run in the pump mechanical seal using clean liquid before pumping dirty liquids, if possible.

Check mark

Is the external flush or quench started before the pump is run?

Check mark

Is the external flush or quench allowed to flow for a period after the pump has stopped?

Check mark

Ensure the mechanical seal is not run dry, even for a short time.

Check mark

6.1.11 Mechanical seals

Check mark

Confirm no adjustment is made to the mechanical seal.

Run this procedureArrow right

Mechanical Seal Maintenance

Check mark

6.1.9 Maintenance of mechanical seal

Check mark

Ensure all parts are in place

Check mark

6.1.9.1 General instructions

Check mark

Read all seal instructions before installing the seal

Check mark

Ensure no scratches or marring on the lapped seal faces

Check mark

6.1.9.2 Preparing the pump

Check mark

Check concentricity between the bore of stuffing box and shaft sleeve

Check mark

Is the concentricity within the Seal Manufacturer's tolerances?

Check mark

Do the sleeve diameter and stuffing box bore dimensions agree with the seal installation drawing?

Run this procedureArrow right

Gland Packing Inspection

Check mark

Initial Inspection

Check mark

Is there visible leakage from the gland?

Check mark

Ensure gland nuts are finger-tight only.

Check mark

Leakage and Temperature Check

Check mark

Is leakage taking place soon after the stuffing box is pressurized?

Check mark

Is the gland adjusted evenly for visible leakage and concentric alignment?

Check mark

Is there any sign of overheating?

Check mark

Overheating Procedure

Check mark

Stop the pump if overheating occurs and allow it to cool.

Run this procedureArrow right

Unlock efficiency
with MaintainX CoPilot

MaintainX CoPilot is your expert colleague, on call 24/7, helping your team find the answers they need to keep equipment running.

Time Lapse Icon

Reduce Unplanned Downtime

Ensure your team follows consistent procedures to minimize equipment failures and costly delays.

Wrench Clock Icon

Maximize Asset Availability

Keep your assets running longer and more reliably, with standardized maintenance workflows from OEM manuals.

Dollar Coin Icon

Lower Maintenance Costs

Turn any technician into an expert to streamline operations, maintain more assets, and reduce overall costs.

Thousands of companies manage their assets with MaintainX

DuracellAB InBevErgonTitan AmericaMeritUnivar SolutionsRivianCadrexMagnaMaasPresriteSoutheast PowerInterrollDuracellAB InBevErgonTitan AmericaMeritUnivar SolutionsRivianCadrexMagnaMaasPresriteSoutheast PowerInterroll

More from Flowserve

Explore Other Assets