MaintainX Asset Hub logo
EnterprisePricing
CAT

CAT Generator SR4

Need answers fast?
Explore the manual using AI.

CAT Generator SR4
CAT Generator SR4

Turn manuals into instant answers
with your AI-powered assistant
Turn manuals into instant answers
with your AI-powered assistant

PDF MANUAL

Manual for CAT Generator SR4

MAINTENANCE RESOURCES

Complete asset maintenance, one click away

Get instant access to all the maintenance information you need. Empower technicians to perform preventive maintenance with asset packages, ready to use right out of the box.

Documents

Documents & Manuals

Find all the essential guides in one place.

  • CheckTensioning Guide

  • CheckBelt-diagram

  • CheckC-120 pulleys

  • + 13 more

Work Orders

Work Order Templates

Pre-built workflows to keep your asset running smoothly.

  • CheckDaily Electrical System Inspection

  • CheckReplace Roller and Pulley

  • CheckInstall Engine B-120

  • + 29 more

Procedures

Procedures

Integrate maintenance plans directly into your work orders.

  • CheckMotion Industries

  • CheckApplied Industrial Technologies

  • CheckElectrical Brothers

  • + 5 more

Parts

Parts

Access the parts list for your equipment in MaintainX.

  • CheckDrive Motor

  • CheckB2 Rollers

  • CheckTensioning System

  • + 40 more

CAT Generator SR4

CAT Generator SR4

Create an account to install this asset package.

Maintenance Plans for CAT Generator Model SR4

Integrate maintenance plans directly into your work orders in MaintainX.

1000 Hourly / 1 Yearly Bearing Lubrication

Check mark

This procedure is for the lubrication of spherical roller bearings and ball bearings.

Check mark

Enter the current machine hour reading

Check mark

Has the machine been operated for 1000 hours since the last spherical roller bearings lubrication?

Check mark

Has the machine been operated for 2000 hours since the last ball bearings lubrication?

Check mark

Has it been a year since the last lubrication?

Check mark

If any of the above checks are 'PASS', proceed with the lubrication process.

Check mark

Lubrication Process:

Check mark

Has it been 3 years since the last grease replacement?

Check mark

If 'PASS', proceed with grease replacement.

Run this procedureArrow right

1 Weekly Generator Check

Check mark

Warning: This maintenance check requires trained personnel with PPE!

Check mark

Bearing Bracket Temperature

Check mark

Main Stator Winding Temperature

Check mark

Visual Inspection

Check mark

Space Heaters

Check mark

Cleaning

Check mark

Looseness

Check mark

Walk around

Check mark

Check operation

Run this procedureArrow right

1 Weekly Resistance Check

Check mark

Warning: This procedure requires trained personnel with PPE!

Check mark

Megohmmeter available for testing?

Check mark

If megohmmeter is not available, report to the maintenance team and stop the procedure

Check mark

Select the situation for testing

Check mark

Enter the megohmmeter test reading

Check mark

Is the test reading above one megohm?

Check mark

Note down any issues found during the test

Check mark

Sign off on the resistance check

Run this procedureArrow right

3 Monthly Insulation Test

Check mark

Warning: This test requires trained personnel with PPE!

Check mark

Insulation test performed?

Check mark

Enter the insulation resistance value (in megohms)

Check mark

Is the insulation resistance value above the minimum threshold (1 megohm + rated V / 1000)?

Check mark

Upload a photo of the Megger reading

Check mark

Sign off on the insulation test

Run this procedureArrow right

Bearing Inspection

Check mark

The following maintenance procedure for generator bearings should be followed at every major engine overhaul:

Check mark

1. Remove bearing bracket. Inspect the bracket bore and bearing outer race and rolling elements. Standby Power units should have the bearing inspected and the grease replaced every three years. The bearing bracket bore should be inspected for out of roundness, excessive wear, and a bracket step less than 0.0762 mm (.003 in).

Check mark

The bearing should be inspected for outer race damage, severe fretting, and smoothness of operation. If possible, the bearing elements should be inspected. Some double shielded ball bearings prevent visual inspection of the ball bearing elements. Other double shielded ball bearings have a retaining ring, that can be removed, to allow access for a visual inspection of the ball bearing elements.

Check mark

NOTE: Bearings being removed for failure analysis should not be cut off with a torch.

Check mark

2. Spherical Roller Bearing should be cleaned and re- '@ packed with 108k3611 Grease Pack the bearing and cavity to one-third to one-half of the cavity volume. (Approximately 3 - 4 oz. in the bearing and 4 - 5 02. in the cavity.) Refer to the chart that follows.

Check mark

3. All ball bearings should be cleaned and the bracket cavity re-packed with 2.5-3230 Grease. The cavity should be filled to one-third to one-half of the cavity volume. Refer to the chart that follows.

Check mark

4. Make sure the grease supply tube to the bearing is filled with grease.

Check mark

5. Remove the bracket drain plug and operate generator for one hour. This allows the grease to expand, forcing the excess grease out of the cavity reliei/ing the internal pressure. The generator should continue to operate until the grease stops purging. Grease may not purge until later grease intervals.

Check mark

6. Stop the engine. Install the bracket drain plug and wipe off excess grease.

Run this procedureArrow right

Parts for CAT Generator SR4

Access the parts list for your equipment in MaintainX.

Part Name
Part Number

Bearing OD 100mm (3.937") ID 45mm (1.772") Shield Type Double

5P-1977

Bearing OD 140mm (5.5118") ID 65mm (2.5591") Shield Type Double

3N-1965

Bearing OD 160mm (6.2992") ID 75mm (2.9527") Shield Type Double

5P-2448

Bearing OD 170mm (6.6929") ID 80mm (3.1496") Shield Type Double

109-7687

Bearing OD 170mm (6.6929") ID 80mm (3.1496") Shield Type Single

4L-6677

Bearing OD 100mm (3.937") ID 45mm (1.772") Shield Type Double

5P-1977

Bearing OD 140mm (5.5118") ID 65mm (2.5591") Shield Type Double

3N-1965

Bearing OD 160mm (6.2992") ID 75mm (2.9527") Shield Type Double

5P-2448

Bearing OD 170mm (6.6929") ID 80mm (3.1496") Shield Type Double

109-7687

Bearing OD 170mm (6.6929") ID 80mm (3.1496") Shield Type Single

4L-6677

Bearing OD 100mm (3.937") ID 45mm (1.772") Shield Type Double

5P-1977

Bearing OD 140mm (5.5118") ID 65mm (2.5591") Shield Type Double

3N-1965

Bearing OD 160mm (6.2992") ID 75mm (2.9527") Shield Type Double

5P-2448

Bearing OD 170mm (6.6929") ID 80mm (3.1496") Shield Type Double

109-7687

Bearing OD 170mm (6.6929") ID 80mm (3.1496") Shield Type Single

4L-6677

Unlock efficiency
with MaintainX CoPilot

MaintainX CoPilot is your expert colleague, on call 24/7, helping your team find the answers they need to keep equipment running.

Time Lapse Icon

Reduce Unplanned Downtime

Ensure your team follows consistent procedures to minimize equipment failures and costly delays.

Wrench Clock Icon

Maximize Asset Availability

Keep your assets running longer and more reliably, with standardized maintenance workflows from OEM manuals.

Dollar Coin Icon

Lower Maintenance Costs

Turn any technician into an expert to streamline operations, maintain more assets, and reduce overall costs.

Thousands of companies manage their assets with MaintainX

DuracellAB InBevErgonTitan AmericaMeritUnivar SolutionsRivianCadrexMagnaMaasPresriteSoutheast PowerInterrollDuracellAB InBevErgonTitan AmericaMeritUnivar SolutionsRivianCadrexMagnaMaasPresriteSoutheast PowerInterroll

More from CAT

Explore Other Assets