The Genie Articulated Boom Lift Z-45/25 DC is a versatile and reliable aerial work platform designed for optimal performance in various industrial applications. With its advanced hydraulic system and robust safety features, this boom lift ensures efficient operation and operator safety, making it an essential asset for construction and maintenance tasks.
Turn manuals into instant answers
with your AI-powered assistantTurn manuals into instant answers
with your AI-powered assistant
Get instant access to all the maintenance information you need. Empower technicians to perform preventive maintenance with asset packages, ready to use right out of the box.
Find all the essential guides in one place.
Tensioning Guide
Belt-diagram
C-120 pulleys
+ 13 more
Pre-built workflows to keep your asset running smoothly.
Daily Electrical System Inspection
Replace Roller and Pulley
Install Engine B-120
+ 29 more
Integrate maintenance plans directly into your work orders.
Motion Industries
Applied Industrial Technologies
Electrical Brothers
+ 5 more
Access the parts list for your equipment in MaintainX.
Drive Motor
B2 Rollers
Tensioning System
+ 40 more

Genie Articulated Boom Lift Z-45/25 DC
Create an account to install this asset package.
Integrate maintenance plans directly into your work orders in MaintainX.
1 Yearly Key Switch Test
- Test the Key Switches - ALC1000 Models
Proper key switch action and response is essential to safe machine operation. Failure of either key switch to function properly could cause a hazardous operating situation
This maintenance procedure applies to the following models: S-100, S-100HD, S-105, S-120, S-120HD, S-125, SX-105 XC, SX-125 XC, SX-135 XC, SX-150, SX-180, Z-80/60, Z-135/70 and Zx-135/70
There are two key switches on the machine - the Main key switch and the Bypass/Recovery key switch
The Main key switch controls machine operation from the ground or platform controls
When the Bypass/Recovery key switch is turned to the bypass position, the primary boom can be elevated with the axles retracted (if equipped with retractable axles). This feature of the machine is especially helpful for storage purposes or when loading the machine for transport
When the Bypass/Recovery key switch is turned and held to the recovery position, the emergency power unit turns on and starts a sequence to lower the platform
This feature of the machine is especially helpful if the operator in the platform cannot lower the boom, if the platform controls become inoperative or for returning the machine to a safe position when the safety switches have been tripped
Note: Perform this procedure on a firm, level surface with the machine in the stowed position
1 Yearly Platform Overload Mechanism Lubrication
- Grease the Platform Overload Mechanism (if equipped)
Perform this procedure more often if dusty conditions exist
Application of lubrication to the platform overload mechanism is essential to safe machine operation. Continued use of an improperly greased platform overload mechanism could result in the system not sensing an overloaded platform condition and will result in component damage
This maintenance procedure does not apply to the following models: S-80 XC, S-85 XC, SX-125 XC, SX-135 XC, Z-45 XC
1. Locate the grease fittings on each pivot pin of the platform overload assembly
2. Thoroughly pump grease into each grease fitting
3. Grease Specification
Chevron Ultra-duty grease, EP NLGI 1 (lithium based) or equivalent;
3 Monthly Fuel Select Test
- Test the Fuel Select Operation - Gasoline/LPG Models
Note: Perform this test after checking the gasoline and LPG fuel levels, and warming the engine to normal operating temperature
1. At the platform controls, move the fuel select switch to gasoline and then move the engine idle control switch to foot switch activated high idle (rabbit and foot switch symbol)
2. Start the engine from the platform controls and allow it to run at low idle
3. Press down the foot switch to allow the engine to run at high idle
Result: The engine should start promptly and operate smoothly in low and high idle
4. Release the foot switch and shut the engine off by pushing in the red Emergency Stop button in to the off position
5. Move the fuel select switch to LPG
6. Restart the engine and allow it to run at low idle
1 Daily Kubota Engine Maintanance
- Check Fuel hoses and clamp bands
- Replace Engine oil , Z482
- Check Fan belt tension and damage
- Check Battery electrolyte level
- Check Spark plug
- Clean Air cleaner element (Replace the element after 6 times cleaning)
- Clean Fuel filter (element type)
- Replace Oil filter cartridge, Z482
- Replace Oil filter cartridge, D1105, WG972
1 Daily GM 3.0L Engine Maintanance
- Clean radiator
- Drain/clean LPG vaporizer
- Clean/replace air cleaner element
- Replace engine oil and filter
- Replace fuel filter
- Replace air filter
- Replace distributor cap
- Replace spark plug wires;
Access the parts list for your equipment in MaintainX.
Digital Protractor
58377
O-ring Field Service Kit
49612
Digital Level Kit
58351
Digital Protractor
58377
O-ring Field Service Kit
49612
Digital Level Kit
58351
Digital Protractor
58377
O-ring Field Service Kit
49612
Digital Level Kit
58351
MaintainX CoPilot is your expert colleague, on call 24/7, helping your team find the answers they need to keep equipment running.
Reduce Unplanned Downtime
Ensure your team follows consistent procedures to minimize equipment failures and costly delays.
Maximize Asset Availability
Keep your assets running longer and more reliably, with standardized maintenance workflows from OEM manuals.
Lower Maintenance Costs
Turn any technician into an expert to streamline operations, maintain more assets, and reduce overall costs.
Thousands of companies manage their assets with MaintainX