PDF MANUAL

Manual for York Single Package Air Conditioner ZR150N10A2AAA50124A

MAINTENANCE RESOURCES

Complete asset maintenance, one click away

Get instant access to all the maintenance information you need. Empower technicians to perform preventive maintenance with asset packages, ready to use right out of the box.

Documents

Documents & Manuals

Find all the essential guides in one place.

  • CheckTensioning Guide

  • CheckBelt-diagram

  • CheckC-120 pulleys

  • + 13 more

Work Orders

Work Order Templates

Pre-built workflows to keep your asset running smoothly.

  • CheckDaily Electrical System Inspection

  • CheckReplace Roller and Pulley

  • CheckInstall Engine B-120

  • + 29 more

Procedures

Procedures

Integrate maintenance plans directly into your work orders.

  • CheckMotion Industries

  • CheckApplied Industrial Technologies

  • CheckElectrical Brothers

  • + 5 more

Parts

Parts

Access the parts list for your equipment in MaintainX.

  • CheckDrive Motor

  • CheckB2 Rollers

  • CheckTensioning System

  • + 40 more

York Single Package Air Conditioner ZR150N10A2AAA50124A

York Single Package Air Conditioner ZR150N10A2AAA50124A

Create an account to install this asset package.

Maintenance Plans for York Single Package Air Conditioner Model ZR150N10A2AAA50124A

Integrate maintenance plans directly into your work orders in MaintainX.

Gas Piping Cleaning

Check mark

WARNING!

Check mark

Pipe Assembly

Check mark

Use special pipe dope for assembly

Check mark

Pipe Cleaning

Check mark

Clean piping of dirt and scale by hammering on the outside of the pipe

Check mark

Blow out loose particles from the pipe

Check mark

Initial Start-up Preparation

Check mark

Ensure all gas lines external to the unit have been purged of air

Run this procedureArrow right

Initial 24 Hours Belt Tension Check

Check mark

Belt Tension Adjustment

Check mark

Loosen six nuts (top and bottom) A

Check mark

Adjust by turning (B)

Check mark

Ensure nuts (C) are not loosened

Check mark

Use belt tension checker to apply a perpendicular force to one belt at the midpoint of the span

Check mark

Enter the deflection distance obtained

Check mark

Enter the deflection force applied

Check mark

Was the belt tension checked at least two times during the first 24 hours of operation?

Check mark

Did any retensioning fall between the min. and max. deflection force values?

Run this procedureArrow right

Supply Air Drive Maintenance

Check mark

Pre-Maintenance Caution

Check mark

Review installation for errors, leaks, or undesirable system effects

Check mark

Ensure only qualified personnel make blower speed changes

Check mark

Blower Speed Adjustment

Check mark

Measure current CFM

Check mark

Enter required CFM

Check mark

Enter existing datum diameter (DD)

Check mark

Calculate new datum diameter (DD) using formula: (Required CFM/Measured CFM)*Existing DD

Check mark

Post-Adjustment Verification

Run this procedureArrow right

Burner Replacement

Check mark

Preparation

Check mark

Close main manual shut-off valve

Check mark

Shut off all power to the unit

Check mark

Disassembly

Check mark

Open the union fitting upstream of the unit gas valve

Check mark

Remove screws holding manifold to supports

Check mark

Disconnect wiring to the gas valve

Check mark

Remove manifold & gas valve assembly

Check mark

Inspection and Replacement

Run this procedureArrow right

Initial Equipment Inspection

Check mark

Visual Inspection

Check mark

Inspect the unit for visible damage during transit

Check mark

Note the extent of any damage on the carrier’s freight bill

Check mark

Carrier Inspection Request

Check mark

Request inspection by the carrier’s agent in writing

Check mark

Gas Supply Safety Measures

Check mark

Is the furnace disconnected from the gas supply piping system?

Check mark

Enter the pressure of the gas supply piping system

Check mark

Is the pressure of the gas supply piping system equal to or less than 1/2 PSIG?

Run this procedureArrow right

Parts for York Single Package Air Conditioner ZR150N10A2AAA50124A

Access the parts list for your equipment in MaintainX.

Part Name
Part Number

LP Gas Accessory Kit

1NP0442

Ducted Systems Accessory Kit

1GP0405

Optional CO2 Space Sensor Kit

2AQ04700324

Optional CO2 Sensor Kit

2AQ04700424

LP Gas Accessory Kit

1NP0442

Ducted Systems Accessory Kit

1GP0405

Optional CO2 Space Sensor Kit

2AQ04700324

Optional CO2 Sensor Kit

2AQ04700424

LP Gas Accessory Kit

1NP0442

Ducted Systems Accessory Kit

1GP0405

Optional CO2 Space Sensor Kit

2AQ04700324

Optional CO2 Sensor Kit

2AQ04700424

Unlock
efficiency with MaintainX Assist

MaintainX Assist is your expert colleague, on call 24/7, helping your team find the answers they need to keep equipment running.

Time Lapse Icon

Reduce Unplanned Downtime

Ensure your team follows consistent procedures to minimize equipment failures and costly delays.

Wrench Clock Icon

Maximize Asset Availability

Keep your assets running longer and more reliably, with standardized maintenance workflows from OEM manuals.

Dollar Coin Icon

Lower Maintenance Costs

Turn any technician into an expert to streamline operations, maintain more assets, and reduce overall costs.