The Okuma Vertical Machining Center MC-V4020 is a high-performance CNC machine designed for precision machining tasks. Known for its reliability and advanced features, this model excels in various industrial applications, ensuring optimal productivity and efficiency in manufacturing processes.
Turn manuals into instant answers
with your AI-powered assistantTurn manuals into instant answers
with your AI-powered assistant
Get instant access to all the maintenance information you need. Empower technicians to perform preventive maintenance with asset packages, ready to use right out of the box.
Find all the essential guides in one place.
Tensioning Guide
Belt-diagram
C-120 pulleys
+ 13 more
Pre-built workflows to keep your asset running smoothly.
Daily Electrical System Inspection
Replace Roller and Pulley
Install Engine B-120
+ 29 more
Integrate maintenance plans directly into your work orders.
Motion Industries
Applied Industrial Technologies
Electrical Brothers
+ 5 more
Access the parts list for your equipment in MaintainX.
Drive Motor
B2 Rollers
Tensioning System
+ 40 more

Okuma Vertical Machining Center MC-V4020
Create an account to install this asset package.
Integrate maintenance plans directly into your work orders in MaintainX.
1 Daily Control Enclosure and Operation Box Inspection
Warning: The CNC unit incorporates electronic devices which are susceptible to moisture, oil, dirt, dust, and chips, and also elevated temperatures in the enclosure caused by clogging of filters in the cooling unit. Therefore, daily inspection and maintenance of the CNC unit is important.
Visually check the control enclosure and the operation box for adhesion of water, oil, dust, and chips
Check the cooling unit filter for clogging
If the control enclosure and the operation box are dirty, clean them.
Check the inside of the control enclosure and the operation box.
Sign off on the daily control enclosure and operation box inspection
1 Daily Vertical Machining Center Maintenance
Daily Tasks
Check incoming air pressure, 0.55 MPa [5.5 kgf/cm (78.2 psi)]
Check oil level of the pneumatic lubricator
Clean the tapered bore of the spindle
Remove and discharge chips from machine
Weekly Tasks
Clean the air filter
1 Monthly Vertical Machining Center Maintenance
Check that the machine is level (only after the first month of machine use)
Clean the coolant tank
Apply grease to the ball screws and linear guides (only after the first month of machine use)
2 Monthly Vertical Machining Center Maintenance
Check that the machine is level
Every 6 months:
Check condition of lubrication of X-,Y- and Z-axis drive ball screws
Check condition of lubrication of X-,Y- and Z-axis linear guide
3 Monthly Cooling Unit Cleaning
Warning: The CNC unit incorporates electronic devices which are susceptible to moisture, oil, dirt, dust, and chips, and also elevated temperatures in the enclosure caused by clogging of filters in the cooling unit.
Therefore, daily inspection and maintenance of the CNC unit is important.
Every Three-month Inspection
Does the cooling unit mounted at the control enclosure door operate to blow air hard?
If the filter is clogged, clean it.
Sign off on the cooling unit cleaning
Access the parts list for your equipment in MaintainX.
Floppy head cleaning disk FCD-3.5W
E0241-602-003
Floppy head cleaning disk FCD-3.5W
E0241-602-003
Floppy head cleaning disk FCD-3.5W
E0241-602-003
MaintainX CoPilot is your expert colleague, on call 24/7, helping your team find the answers they need to keep equipment running.
Reduce Unplanned Downtime
Ensure your team follows consistent procedures to minimize equipment failures and costly delays.
Maximize Asset Availability
Keep your assets running longer and more reliably, with standardized maintenance workflows from OEM manuals.
Lower Maintenance Costs
Turn any technician into an expert to streamline operations, maintain more assets, and reduce overall costs.
Thousands of companies manage their assets with MaintainX