Turn manuals into instant answers
with your AI-powered assistantTurn manuals into instant answers
with your AI-powered assistant
Get instant access to all the maintenance information you need. Empower technicians to perform preventive maintenance with asset packages, ready to use right out of the box.
Find all the essential guides in one place.
Tensioning Guide
Belt-diagram
C-120 pulleys
+ 13 more
Pre-built workflows to keep your asset running smoothly.
Daily Electrical System Inspection
Replace Roller and Pulley
Install Engine B-120
+ 29 more
Integrate maintenance plans directly into your work orders.
Motion Industries
Applied Industrial Technologies
Electrical Brothers
+ 5 more
Access the parts list for your equipment in MaintainX.
Drive Motor
B2 Rollers
Tensioning System
+ 40 more

Allied Air Enterprises Warm Air Gas Furnace 95G1UH045BE12
Create an account to install this asset package.
Integrate maintenance plans directly into your work orders in MaintainX.
Gas Furnace Gas Piping Inspection
Safety Precautions
Ensure black iron pipe is installed at the gas valve and extends outside the furnace cabinet if a flexible gas connector is required or allowed.
Verify that the flexible connector is properly installed between the black iron pipe and the gas supply line.
Torque Specifications
Measure the torque applied when attaching the gas piping to the gas valve.
Gas Supply Piping Inspection
Measure the pressure drop between the gas meter and the unit.
Is the supply gas pipe size equal to or larger than the unit gas connection?
Threaded Joints Inspection
Burner Assembly Cleaning
Preparation
Turn off electrical and gas power supplies to furnace
Remove upper and lower furnace access panels
Disconnection
Disconnect the wires from the gas valve
Remove the burner box cover (if equipped)
Disconnect the gas supply line from the gas valve
Remove gas valve/manifold assembly
Mark and disconnect sensor wire from the sensor
Gas Furnace Preliminary and Seasonal Inspection
Preliminary and Seasonal Checks
Inspect electrical wiring for loose connections and tighten as required.
Check voltage at disconnect switch.
Is the voltage within the range listed on the nameplate?
Inspect condition of condensate traps and drain assembly.
Disassemble and clean condensate traps and drain assembly seasonally.
Heat Exchanger Cleaning
Preparation
Turn off electrical and gas supplies to the furnace.
Remove the furnace access panels.
Disassembly
Disconnect the 2 wires from the gas valve.
Remove gas supply line connected to gas valve and remove gas valve/manifold assembly.
Remove sensor wire from sensor and disconnect 2-pin plug from the ignitor.
Disconnect wires from flame roll-out switches.
Disconnect combustion air intake pipe.
Gas Supply Pressure Testing
Preparation
Ensure furnace has been operating for at least 5 minutes
Shut off all other gas appliances connected to the meter
Gas Flow Measurement
Record time in seconds for two revolutions of gas through the meter
Divide the recorded time by two to get the average time per revolution
Comparison and Adjustment
Is the average time per revolution matching the time in Table 16?
Does the manifold pressure match Table 18?
Access the parts list for your equipment in MaintainX.
External Filter Rack 1 pack (16 x 25)
1.841018
External Filter Rack 10 pack (16 x 25)
1.841039
Natural to LP Kit 1-Stage - 90
11K50
Natural to LP Kit High Altitude 1-Stage
11K45
Natural to LP Kit 1-Stage - 90 Low Input [030K BTUH]
13X57
External Filter Rack 1 pack (16 x 25)
1.841018
External Filter Rack 10 pack (16 x 25)
1.841039
Natural to LP Kit 1-Stage - 90
11K50
Natural to LP Kit High Altitude 1-Stage
11K45
Natural to LP Kit 1-Stage - 90 Low Input [030K BTUH]
13X57
External Filter Rack 1 pack (16 x 25)
1.841018
External Filter Rack 10 pack (16 x 25)
1.841039
Natural to LP Kit 1-Stage - 90
11K50
Natural to LP Kit High Altitude 1-Stage
11K45
Natural to LP Kit 1-Stage - 90 Low Input [030K BTUH]
13X57
MaintainX CoPilot is your expert colleague, on call 24/7, helping your team find the answers they need to keep equipment running.
Reduce Unplanned Downtime
Ensure your team follows consistent procedures to minimize equipment failures and costly delays.
Maximize Asset Availability
Keep your assets running longer and more reliably, with standardized maintenance workflows from OEM manuals.
Lower Maintenance Costs
Turn any technician into an expert to streamline operations, maintain more assets, and reduce overall costs.
Thousands of companies manage their assets with MaintainX