Turn manuals into instant answers
with your AI-powered assistantTurn manuals into instant answers
with your AI-powered assistant
Get instant access to all the maintenance information you need. Empower technicians to perform preventive maintenance with asset packages, ready to use right out of the box.
Find all the essential guides in one place.
Tensioning Guide
Belt-diagram
C-120 pulleys
+ 13 more
Pre-built workflows to keep your asset running smoothly.
Daily Electrical System Inspection
Replace Roller and Pulley
Install Engine B-120
+ 29 more
Integrate maintenance plans directly into your work orders.
Motion Industries
Applied Industrial Technologies
Electrical Brothers
+ 5 more
Access the parts list for your equipment in MaintainX.
Drive Motor
B2 Rollers
Tensioning System
+ 40 more

Leybold Vacuum Pump TRIVAC S 40 B 102 96
Create an account to install this asset package.
Integrate maintenance plans directly into your work orders in MaintainX.
Pump Module Maintenance
3.7 Removing and Remounting the Pump Module
Ensure all required tools are available
Ensure all required spare parts are available
3.7.1 Removing the Pump Module
Drain the oil and remove the oil case (see Section 3.4)
Unscrew the hex. nuts (13/1)
Pull the entire pump module (13/2) forward off the tie rods (13/5)
Ensure individual pin-fitted parts are not loosened
Remove the gasket (13/3)
Pump Storage Maintenance
3.9 Storing the Pump
Store the pump in a dry place at room temperature (20 °C)
Properly disconnect the pump from the vacuum system
Purge the pump with dry nitrogen
Change the oil in the pump
Seal the inlets and outlets with shipping seals
Set the gas ballast switch to the '0' position
Seal the pump in a PE bag with desiccant if shelved for a long period
Has the pump been shelved for over one year?
1 Daily Pump Maintenance
3.10 Maintenance Plan
Operate the pump for at least 0.8 hours with gas ballast
Confirm removal of condensed water from the oil
2 Yearly Pump Maintenance
3.10 Maintenance Plan
Ensure all maintenance tasks are completed
Was the maintenance performed by the Leybold service?
6 Monthly Internal Demister Cleaning
3.4 Removing and Fitting the Internal Demister
Ensure all required tools and spare parts are available
Shutdown the pump and drain the oil (see Section 3.2)
Remove the six recessed screws (10/6) on the oil case (10/4)
Pull the oil case forward off the pump
Remove the gasket (10/5)
Remove components
Lift off the frame (10/2) and remove the internal demister (10/3)
Clean all parts and check their condition
Access the parts list for your equipment in MaintainX.
Oil N 62 1l
177 01
Oil N 62 5l
177 02
Oil N 62 20l
177 03
Oil HE-200 1 Qt
98 198 006
Oil HE-200 12 Qt Case
98 198 049
Oil N 62 1l
177 01
Oil N 62 5l
177 02
Oil N 62 20l
177 03
Oil HE-200 1 Qt
98 198 006
Oil HE-200 12 Qt Case
98 198 049
Oil N 62 1l
177 01
Oil N 62 5l
177 02
Oil N 62 20l
177 03
Oil HE-200 1 Qt
98 198 006
Oil HE-200 12 Qt Case
98 198 049
MaintainX CoPilot is your expert colleague, on call 24/7, helping your team find the answers they need to keep equipment running.
Reduce Unplanned Downtime
Ensure your team follows consistent procedures to minimize equipment failures and costly delays.
Maximize Asset Availability
Keep your assets running longer and more reliably, with standardized maintenance workflows from OEM manuals.
Lower Maintenance Costs
Turn any technician into an expert to streamline operations, maintain more assets, and reduce overall costs.
Thousands of companies manage their assets with MaintainX