The Haas Automation CNC Horizontal Machining Center HS-6R is a versatile and robust machine designed for precision machining tasks. Known for its reliability and efficiency, the HS-6R is ideal for various industrial applications, ensuring high productivity and quality in manufacturing processes.
Turn manuals into instant answers
with your AI-powered assistantTurn manuals into instant answers
with your AI-powered assistant
Get instant access to all the maintenance information you need. Empower technicians to perform preventive maintenance with asset packages, ready to use right out of the box.
Find all the essential guides in one place.
Tensioning Guide
Belt-diagram
C-120 pulleys
+ 13 more
Pre-built workflows to keep your asset running smoothly.
Daily Electrical System Inspection
Replace Roller and Pulley
Install Engine B-120
+ 29 more
Integrate maintenance plans directly into your work orders.
Motion Industries
Applied Industrial Technologies
Electrical Brothers
+ 5 more
Access the parts list for your equipment in MaintainX.
Drive Motor
B2 Rollers
Tensioning System
+ 40 more

Haas Automation CNC Horizontal Machining Center HS-6R
Create an account to install this asset package.
Integrate maintenance plans directly into your work orders in MaintainX.
1 Daily CNC Horizontal Machining Center Maintenance
Check coolant level
Check way lube lubrication tank level
Clean chips from way covers and bottom pan
Clean chips from tool changer
Wipe spindle taper with a clean cloth rag and apply light oil
Sign off on the daily maintenance
1 Monthly CNC Horizontal Machining Center Maintenance
Check oil level in gear box
Inspect way covers for proper operation
Lubricate with light oil, if necessary
Place a dab of grease on the outside edge of the guide rails of the tool changer
EC-400 Clean the locating pads on the A-axis and the load station
Sign off on the CNC Horizontal Machining Center Maintenance
1 Weekly CNC Horizontal Machining Center Maintenance
• Check Through the Spindle Coolant (TSC) filters. Clean or replace element if needed.
• Check for proper operation of auto drain on filter regulator.
• On machines with the TSC option, clean the chip basket on the coolant tank.
Remove the tank cover and remove any sediment inside the tank. Disconnect the coolant pump from the cabinet and power off the machine before working on the coolant tank.
Do this MONTHLY for machines without the TSC option.
• Check air gauge/regulator for 85 psi. Check the spindle air pressure regulator for 17 psi. For 15K-spindle machines, check spindle air pressure regulator for 20 psi.
• For machines with the TSC option, place a dab of grease on the V-flange of tools.
Do this MONTHLY for machines without the TSC option.
• Clean exterior surfaces with mild cleaner. DO NOT use solvents.
1 Yearly CNC Horizontal Machining Center Maintenance
• Replace the gearbox oil. Drain the oil from the bottom of the gearbox.
Remove inspection cover beneath spindle head. Add oil slowly from top until oil begins dripping from overflow tube at bottom of sump tank. For 50 taper spindles, add oil from the side of the transmission.
• Check oil filter and clean out residue at bottom of filter.
• Check SMTC oil level in sight glass, (see Side Mount Tool Changer Oil Level in this section).
• Lubricate the Changer Slide Linear Guide with red grease.;
2 Yearly CNC Horizontal Machining Center Maintenance
• Replace air filter on control box every 2 years.
• EC-400 Replace the Rotary A-axis oil
1. Remove the fourteen (14) BHCS on the right Z-axis way cover at the receiver end and slide it toward the column.
2. Remove the left Z-axis way cover: Jog the Z-axis all the way toward the column and rotate the H-frame 45° counter clockwise. Remove the thirteen (13) BHCS that fasten the waycover to the receiver and remove it through the door at the control pendant.
3. Disconnect the reservoir at the rotary indexer end and plug the end of the hose.
4. Remove the drain plug on the opposite side of the rotary indexer. Replug the hole when the oil has drained.
5. Remove the air escape hole plug on the side of the platter.
6. Fill the rotary table until oil begins to escape from the air escape hole and plug it.
7. Replace the reservoir hose and the way covers. Command the receiver 180° to 0° repeatedly for fifteen minutes.
Access the parts list for your equipment in MaintainX.
Access Cover (2)
25-6003
Back Panel Sheet Metal
25-0528
Bearing Crossroller
51-2038
Bearing Retainer Ring
20-6113
Brake Assy
30-7754
Access Cover (2)
25-6003
Back Panel Sheet Metal
25-0528
Bearing Crossroller
51-2038
Bearing Retainer Ring
20-6113
Brake Assy
30-7754
Access Cover (2)
25-6003
Back Panel Sheet Metal
25-0528
Bearing Crossroller
51-2038
Bearing Retainer Ring
20-6113
Brake Assy
30-7754
MaintainX CoPilot is your expert colleague, on call 24/7, helping your team find the answers they need to keep equipment running.
Reduce Unplanned Downtime
Ensure your team follows consistent procedures to minimize equipment failures and costly delays.
Maximize Asset Availability
Keep your assets running longer and more reliably, with standardized maintenance workflows from OEM manuals.
Lower Maintenance Costs
Turn any technician into an expert to streamline operations, maintain more assets, and reduce overall costs.
Thousands of companies manage their assets with MaintainX