MaintainX Asset Hub logo
EnterprisePricing
Goulds Pumps

Goulds Pumps Vertical Turbine Pump VIT-FF 10A

Need answers fast?
Explore the manual using AI.

Goulds Pumps Vertical Turbine Pump VIT-FF 10A
Goulds Pumps Vertical Turbine Pump VIT-FF 10A

Turn manuals into instant answers
with your AI-powered assistant
Turn manuals into instant answers
with your AI-powered assistant

PDF MANUAL

Manual for Goulds Pumps Vertical Turbine Pump VIT-FF 10A

MAINTENANCE RESOURCES

Complete asset maintenance, one click away

Get instant access to all the maintenance information you need. Empower technicians to perform preventive maintenance with asset packages, ready to use right out of the box.

Documents

Documents & Manuals

Find all the essential guides in one place.

  • CheckTensioning Guide

  • CheckBelt-diagram

  • CheckC-120 pulleys

  • + 13 more

Work Orders

Work Order Templates

Pre-built workflows to keep your asset running smoothly.

  • CheckDaily Electrical System Inspection

  • CheckReplace Roller and Pulley

  • CheckInstall Engine B-120

  • + 29 more

Procedures

Procedures

Integrate maintenance plans directly into your work orders.

  • CheckMotion Industries

  • CheckApplied Industrial Technologies

  • CheckElectrical Brothers

  • + 5 more

Parts

Parts

Access the parts list for your equipment in MaintainX.

  • CheckDrive Motor

  • CheckB2 Rollers

  • CheckTensioning System

  • + 40 more

Goulds Pumps Vertical Turbine Pump VIT-FF 10A

Goulds Pumps Vertical Turbine Pump VIT-FF 10A

Create an account to install this asset package.

Maintenance Plans for Goulds Pumps Vertical Turbine Pump Model VIT-FF 10A

Integrate maintenance plans directly into your work orders in MaintainX.

3 Monthly Pump Inspection

Check mark

6.1 Maintenance schedule

Check mark

Check that the foundation and the hold-down bolts are tight

Run this procedureArrow right

Thrust Pot Oil Change

Check mark

Thrust pot lubrication guidelines

Check mark

Flush the oil reservoir to remove all grit particles in the oil reservoir sump.

Check mark

Use the specified type of oil for flushing the reservoir.

Check mark

Refer to the Thrust Pot IOM for oil changing requirements.

Run this procedureArrow right

Pump Maintenance

Check mark

6.4 Disassembly

Check mark

6.4.1 Disassembly precautions

Check mark

Ensure safety precautions are followed

Check mark

6.4.2 Disassemble the head and column

Check mark

Remove necessary components based on drive type

Check mark

Uncouple the driver or gear box from the pump shaft and mounting flanges

Check mark

Remove all hold-down bolts and integral piping

Check mark

Remove the coupling and mechanical seal

Check mark

Continue disassembly down to the bowls

Run this procedureArrow right

Enclosed Lineshaft Lubrication System Maintenance

Check mark

Set up the lubrication system

Check mark

Observe instructions on the submittal document

Check mark

Fill the oil reservoir with oil

Check mark

Check the lubricator feed and ensure the oil reservoir is flowing freely

Check mark

Set the proper drops per minute on the regulator for shaft 0.75 to 1.00 in. (19 to 25 mm)

Check mark

Set the proper drops per minute on the regulator for shaft 1.19 to 1.94 in. (30 to 50 mm)

Check mark

Set the proper drops per minute on the regulator for shaft 2.19 in. and larger (55 mm and larger)

Check mark

Is synthetic turbine oil ISO VG 32 used for general applications?

Check mark

Consult ITT for more specific data if needed

Run this procedureArrow right

Packing Adjustment

Check mark

6.2 Adjust and replace the packing

Check mark

Check conditions for packing adjustment

Check mark

Is the leakage rate less than one drop per second after adjustment?

Check mark

Is the environment Ex-classified?

Check mark

6.2.1 Adjust the packing when leaking is excessive

Check mark

Tighten the gland nuts one-quarter turn with the pump in operation

Check mark

Has the leakage decreased to two drops per second?

Check mark

Shut down the pump if leakage continues to exceed two drops per second

Check mark

Allow the packing to compress until the gland is about to contact the upper face of the stuffing box

Run this procedureArrow right

Unlock efficiency
with MaintainX CoPilot

MaintainX CoPilot is your expert colleague, on call 24/7, helping your team find the answers they need to keep equipment running.

Time Lapse Icon

Reduce Unplanned Downtime

Ensure your team follows consistent procedures to minimize equipment failures and costly delays.

Wrench Clock Icon

Maximize Asset Availability

Keep your assets running longer and more reliably, with standardized maintenance workflows from OEM manuals.

Dollar Coin Icon

Lower Maintenance Costs

Turn any technician into an expert to streamline operations, maintain more assets, and reduce overall costs.

Thousands of companies manage their assets with MaintainX

DuracellAB InBevErgonTitan AmericaMeritUnivar SolutionsRivianCadrexMagnaMaasPresriteSoutheast PowerInterrollDuracellAB InBevErgonTitan AmericaMeritUnivar SolutionsRivianCadrexMagnaMaasPresriteSoutheast PowerInterroll

More from Goulds Pumps

Explore Other Assets