MaintainX Asset Hub logo
EnterprisePricing
Pentair

Pentair Plunger Pump 2345B-P

Need answers fast?
Explore the manual using AI.

Pentair Plunger Pump 2345B-P
Pentair Plunger Pump 2345B-P

Turn manuals into instant answers
with your AI-powered assistant
Turn manuals into instant answers
with your AI-powered assistant

PDF MANUAL

Manual for Pentair Plunger Pump 2345B-P

MAINTENANCE RESOURCES

Complete asset maintenance, one click away

Get instant access to all the maintenance information you need. Empower technicians to perform preventive maintenance with asset packages, ready to use right out of the box.

Documents

Documents & Manuals

Find all the essential guides in one place.

  • CheckTensioning Guide

  • CheckBelt-diagram

  • CheckC-120 pulleys

  • + 13 more

Work Orders

Work Order Templates

Pre-built workflows to keep your asset running smoothly.

  • CheckDaily Electrical System Inspection

  • CheckReplace Roller and Pulley

  • CheckInstall Engine B-120

  • + 29 more

Procedures

Procedures

Integrate maintenance plans directly into your work orders.

  • CheckMotion Industries

  • CheckApplied Industrial Technologies

  • CheckElectrical Brothers

  • + 5 more

Parts

Parts

Access the parts list for your equipment in MaintainX.

  • CheckDrive Motor

  • CheckB2 Rollers

  • CheckTensioning System

  • + 40 more

Pentair Plunger Pump 2345B-P

Pentair Plunger Pump 2345B-P

Create an account to install this asset package.

Maintenance Plans for Pentair Plunger Pump Model 2345B-P

Integrate maintenance plans directly into your work orders in MaintainX.

Valve Assembly Replacement

Check mark

Disassembly

Check mark

Remove the valve cap (Figure 9, Ref. 1)

Check mark

Remove the valve assembly (Ref. 3) from the head using needle nose pliers

Check mark

Remove the o-ring (Ref. 4) from below the valve assembly

Check mark

Remove the o-ring (Ref. 2) from the valve cap

Check mark

Reassembly

Check mark

Reassemble the parts by reversing the disassembly steps

Check mark

Torque Specifications

Check mark

Select the model for torque specification

Run this procedureArrow right

3 Monthly / 500 Hourly Pump Lubrication

Check mark

Pre-Lubrication Check

Check mark

Check the oil level using the dipstick

Check mark

Is the oil level adequate?

Check mark

Oil Change

Check mark

Use Hypro Oil (P/N 2160-0038) for lubrication

Check mark

Enter the crankcase capacity for PowerLine Plus 2200B-P pumps

Check mark

Change oil after 500 hours of operation

Check mark

Post-Lubrication Check

Check mark

Verify the following are marked on the crankcase of the pump

Run this procedureArrow right

Oil Seal Replacement

Check mark

Oil Seal Replacement for 2200B-P and 2300B-P Series

Check mark

Tools Required

Check mark

Ensure the following tools are available

Check mark

Oil Seal Replacement Procedure

Check mark

Drain the oil from the crankcase using a 9/16" hex wrench.

Check mark

Remove the cylinder head and plunger retaining nuts with a 9/16" hex wrench. Remove the plungers and slinger rings.

Check mark

Inspect the plunger rods for nicks or scratches. Replace if necessary.

Check mark

Lift out the plunger guide using two flat screwdrivers, ensuring no damage to the plunger rods.

Check mark

Replace the plunger guides with oil seals and o-rings, indexing to the vent ports.

Run this procedureArrow right

Plunger Seal Maintenance

Check mark

Tools Required

Check mark

Ensure the following tools are available

Check mark

Replace the plunger seals if there is water leakage from the weephole

Check mark

Cylinder Head Removal

Check mark

Use a 3/16" Allen wrench to remove the cylinder head bolts

Check mark

Remove the head from the crankcase assembly

Check mark

Cup Retainer Removal

Check mark

Rotate the shaft and remove the cup retainers from the plungers

Check mark

Remove the cup retainer and the cup from the cylinder head

Run this procedureArrow right

Initial 40 Hours Pump Lubrication

Check mark

IMPORTANT: Hypro PowerLine Plus pumps are filled with Hypro Oil.

Check mark

Oil Change Frequency

Check mark

Change oil after 40 hours of break-in operation.

Check mark

Change oil every three months or 500 hours, whichever comes first.

Check mark

Lubrication Check

Check mark

Check the oil level using the dipstick.

Check mark

Is the oil level adequate?

Check mark

Oil Specification

Check mark

Use Hypro Oil (P/N 2160-0038).

Run this procedureArrow right

Parts for Pentair Plunger Pump 2345B-P

Access the parts list for your equipment in MaintainX.

Part Name
Part Number

Hypro Oil

2160-0038

External Pliers

3010-0057

Oil Seal Insertion Tool

3010-0248

Key, 1-1/4" long

1610-0021

Seal

2102-0017

Hypro Oil

2160-0038

External Pliers

3010-0057

Oil Seal Insertion Tool

3010-0248

Key, 1-1/4" long

1610-0021

Seal

2102-0017

Hypro Oil

2160-0038

External Pliers

3010-0057

Oil Seal Insertion Tool

3010-0248

Key, 1-1/4" long

1610-0021

Seal

2102-0017

Unlock efficiency
with MaintainX CoPilot

MaintainX CoPilot is your expert colleague, on call 24/7, helping your team find the answers they need to keep equipment running.

Time Lapse Icon

Reduce Unplanned Downtime

Ensure your team follows consistent procedures to minimize equipment failures and costly delays.

Wrench Clock Icon

Maximize Asset Availability

Keep your assets running longer and more reliably, with standardized maintenance workflows from OEM manuals.

Dollar Coin Icon

Lower Maintenance Costs

Turn any technician into an expert to streamline operations, maintain more assets, and reduce overall costs.

Thousands of companies manage their assets with MaintainX

DuracellAB InBevErgonTitan AmericaMeritUnivar SolutionsRivianCadrexMagnaMaasPresriteSoutheast PowerInterrollDuracellAB InBevErgonTitan AmericaMeritUnivar SolutionsRivianCadrexMagnaMaasPresriteSoutheast PowerInterroll

More from Pentair

Explore Other Assets