The Komatsu Bulldozer D155A-6 is a robust and versatile piece of heavy machinery designed for earthmoving and construction tasks. Known for its durability and efficiency, this bulldozer excels in various applications, making it a preferred choice for contractors and operators alike.
Turn manuals into instant answers
with your AI-powered assistantTurn manuals into instant answers
with your AI-powered assistant
Get instant access to all the maintenance information you need. Empower technicians to perform preventive maintenance with asset packages, ready to use right out of the box.
Find all the essential guides in one place.
Tensioning Guide
Belt-diagram
C-120 pulleys
+ 13 more
Pre-built workflows to keep your asset running smoothly.
Daily Electrical System Inspection
Replace Roller and Pulley
Install Engine B-120
+ 29 more
Integrate maintenance plans directly into your work orders.
Motion Industries
Applied Industrial Technologies
Electrical Brothers
+ 5 more
Access the parts list for your equipment in MaintainX.
Drive Motor
B2 Rollers
Tensioning System
+ 40 more

Komatsu Komatsu Bulldozer D155A-6 D155A-6
Create an account to install this asset package.
Integrate maintenance plans directly into your work orders in MaintainX.
250 Hourly Wheel Loader Maintenance
LUBRICATING
1. Lower the work equipment to the ground, then stop the engine.
2. Using a grease pump, pump in grease through the grease fittings shown by arrows.
3. After greasing, wipe off any old grease that was pushed out.
Greasing equalizer bar side pins (2 places)
Left and right sides of machine: 1 places each
1) Remove all soil and mud from the top of track frame and cover (1).
2) Climb on top of the straight frame and remove the cover from (A) between the track frame and track shoe.
3) Carry out the greasing from the top of the track shoe.
When Required Wheel Loader Maintenance
CLEAN INSIDE OF COOLING SYSTEM
WARNING
Immediately after the engine is stopped, the coolant is at a high temperature and the radiator is under high internal pressure.
If the cap is removed to drain the coolant in this condition, there is a hazard of burns. Wait for the temperature to go down, then turn the cap slowly to release the pressure before removing it.
Cleaning is carried out with the engine running. When standing up or leaving the operator's seat, set the work equipment lock lever and the parking lever to the LOCK position.
For details of starting the engine, see "CHECK BEFORE STARTING ENGINE, ADJUST (PAGE 3-95)" and "STARTING ENGINE (PAGE 3-116)" in the OPERATION section.
Never walk in front of the machine when the engine is running.There is danger of touching the fan.
It is extremely dangerous to go under the machine to clean it when the engine is running. There is danger that the machine may suddenly move. Never go under the machine when the engine is running.
Stop the machine on level ground when cleaning or changing the coolant.
2000 Hourly Wheel Loader Maintenance
CHANGE OIL IN HYDRAULIC TANK, REPLACE HYDRAULIC OIL FILTER ELEMENT
Steps to change oil in hydraulic tank
CLEAN ENGINE BREATHER ELEMENT
Steps to clean engine breather element
CHECK ALTERNATOR, STARTING MOTOR
The brushes may be worn or the bearing may have run out of grease, contact your Komatsu distributorfor inspection and repairs.
CHANGE OIL IN DAMPER CASE, CLEAN DAMPER BREATHER
Steps to change oil in damper case, clean damper breather
CHECK PIVOT BEARING OIL LEVEL, ADD OIL
1000 Hourly Wheel Loader Maintenance
WARNING: The oil is at high temperature immediately after operations, so wait for the temperature to go down before starting the operation.
The undercover is heavy. Do not go directly under the cover when opening or closing it.
Oil replacement amount: 146 liters (38.57 US gal)
Remove drain cover (1) on the left side of the power train case underside to take off drain plug (2), and then loosen drain plug (P1) to drain oil.
Tighten drain plug (P1) after draining oil.
Remove inspection cover (3) of the undercover on the bottom rear of the machine.
Remove drain plug (P2) in the strainer cover, and drain the oil (approx. 4 liters (1.06 US gal)) collected inside the piping.
Loosen mounting bolt (6) of the power train strainer, and remove cover (7).
Remove spring (8), then remove strainer (9).
Initial 250 hours Wheel Loader Maintenance
Perform the following maintenance only after the first 250 hours.
Replace power train oil filter element
Change oil in power train case
Wash strainers (power train pump strainer, scavenging pump strainer)
Change oil in final drive case
Change oil in hydraulic tank
Replace hydraulic oil filter element
For details of the method of replacing or maintaining, see EVERY 500 HOURS, EVERY 1000 HOURS and EVERY 2000 HOURS SERVICE.
Sign off on the wheel loader maintenance
Access the parts list for your equipment in MaintainX.
Power Train Filter Element
07063-51100
Fuel Pre-Filter Cartrige
600-319-4500
Blade Sigmadozer (Cemented Carbide End Bit Specification) Cutting Edge (Left)
17A-71-46680
Blade Angledozer Cutting Edge
175-70-21115
Hydraulic Oil Filter Element
207-60-71182
Power Train Filter Element
07063-51100
Fuel Pre-Filter Cartrige
600-319-4500
Blade Sigmadozer (Cemented Carbide End Bit Specification) Cutting Edge (Left)
17A-71-46680
Blade Angledozer Cutting Edge
175-70-21115
Hydraulic Oil Filter Element
207-60-71182
Power Train Filter Element
07063-51100
Fuel Pre-Filter Cartrige
600-319-4500
Blade Sigmadozer (Cemented Carbide End Bit Specification) Cutting Edge (Left)
17A-71-46680
Blade Angledozer Cutting Edge
175-70-21115
Hydraulic Oil Filter Element
207-60-71182
MaintainX CoPilot is your expert colleague, on call 24/7, helping your team find the answers they need to keep equipment running.
Reduce Unplanned Downtime
Ensure your team follows consistent procedures to minimize equipment failures and costly delays.
Maximize Asset Availability
Keep your assets running longer and more reliably, with standardized maintenance workflows from OEM manuals.
Lower Maintenance Costs
Turn any technician into an expert to streamline operations, maintain more assets, and reduce overall costs.
Thousands of companies manage their assets with MaintainX