Turn manuals into instant answers
with your AI-powered assistantTurn manuals into instant answers
with your AI-powered assistant
Get instant access to all the maintenance information you need. Empower technicians to perform preventive maintenance with asset packages, ready to use right out of the box.
Find all the essential guides in one place.
Tensioning Guide
Belt-diagram
C-120 pulleys
+ 13 more
Pre-built workflows to keep your asset running smoothly.
Daily Electrical System Inspection
Replace Roller and Pulley
Install Engine B-120
+ 29 more
Integrate maintenance plans directly into your work orders.
Motion Industries
Applied Industrial Technologies
Electrical Brothers
+ 5 more
Access the parts list for your equipment in MaintainX.
Drive Motor
B2 Rollers
Tensioning System
+ 40 more

FRISTAM Pump FPE 3541
Create an account to install this asset package.
Integrate maintenance plans directly into your work orders in MaintainX.
Pump Storage Maintenance
Long-Term Storage
Treat shaft seals before long-term storage
Rotate all movable pump parts every three months
Storage of Elastomers
Ensure storage temperature is between +5°C and +20°C
Is the relative air humidity below 70%?
Is there no direct sunlight exposure?
Is the storage deformation-free?
Recommissioning
Shaft Seal Maintenance
Shaft Seal Replacement
Remove the pump head (see Pump Head Removal)
Replace the mechanical seal, and mount the pump head (see Pump Head Assembly)
Perform the following tasks according to the given shaft seal
Impeller Clearance Calibration
Clearance Too Large
Remove the stationary bushing from the shaft sealing kit
Grind the stationary bushing to the required size
Re-install the stationary bushing
Slide the key and the impeller onto the shaft and tighten them with the impeller nut
Measure the clearance again
Motor Maintenance
Motor Replacement — Special Motor
Turn off the motor and prevent it from being able to be turned on accidentally.
Remove the pump head (see Pump Head Removal).
Replace the special motor.
Replace the mechanical seal if necessary, and mount the pump head (see Pump Head Assembly).
Motor Replacement — IEC Standard Motor for FPE and FP...V
Turn off the motor and prevent it from being able to be turned on accidentally.
Remove the pump head (see Pump Head Removal).
Take the lantern off of the motor.
Pump Head Maintenance
Pump Head Removal — Preparation
Turn off the motor and prevent it from being turned on accidentally.
Close the valve in the discharge line.
Close the valve in the suction line.
Completely empty the pump.
Pump Head Removal — Procedure
Loosen the nuts on the pump cover.
Remove components
Block the impeller with a wooden wedge to prevent injury.
Access the parts list for your equipment in MaintainX.
Pump Casing
101
Stage Casing
108
Cover
160
Back Casing Panel
13-1
Housing Insert
13-2
Pump Casing
101
Stage Casing
108
Cover
160
Back Casing Panel
13-1
Housing Insert
13-2
Pump Casing
101
Stage Casing
108
Cover
160
Back Casing Panel
13-1
Housing Insert
13-2
MaintainX Assist is your expert colleague, on call 24/7, helping your team find the answers they need to keep equipment running.
Reduce Unplanned Downtime
Ensure your team follows consistent procedures to minimize equipment failures and costly delays.
Maximize Asset Availability
Keep your assets running longer and more reliably, with standardized maintenance workflows from OEM manuals.
Lower Maintenance Costs
Turn any technician into an expert to streamline operations, maintain more assets, and reduce overall costs.