Tensioning Guide
Belt-diagram
C-120 pulleys
+ 13 more
Pre-built workflows to keep your asset running smoothly.
Daily Electrical System Inspection
Replace Roller and Pulley
Install Engine B-120
+ 29 more
Integrate maintenance plans directly into your work orders.
Motion Industries
Applied Industrial Technologies
Electrical Brothers
+ 5 more
Access the parts list for your equipment in MaintainX.
Drive Motor
B2 Rollers
Tensioning System
+ 40 more
Trane CenTraVac™ Water-Cooled Chiller CVHF - 1070-1300 - 1062 - 142L / 142L
Create an account to install this asset package.
Integrate maintenance plans directly into your work orders in MaintainX.
1 Yearly Exterior Parts Maintenance
- Shut down the chiller once each year to check the items of Exterior
1. Inlet guide vane linkage
2. Clean and touch-up painted surfaces as needed
3. Repair deteriorated, torn, or missing insulation;
1 Yearly Compressor/Motor Inspection
- Shut down the chiller once each year to check the items
- Compressor/Motor p.103:
1. Motor continuity
2. Motor meg test
3. Check motor terminals
4. Inspect motor terminal board
5. Check inlet guide vanes (IGV) for abnormalities;
1 Yearly Evaporator Inspection
- Shut down the chiller once each year to check the items of Evaporator
1. Inspect for fouling and scaling in tubes
2. Check operation of evaporator water flow sensing device
3. Factory recommendation to eddy current test tubes every three years;
1 Yearly Optional Accessories Maintenance
- Shut down the chiller once each year to check the items of Optional Accessories
1. If applicable, lubricate factory-installed gantries
2. After the first month of operation, inspect Heresite® or Belzona® coated waterboxes; thereafter, inspect as needed
3. Inspect anodes
4. Inspect and lubricate hinged waterboxes
5. With water flow sensing option, bleed tubing from waterboxes to transformers;
1 Yearly Chiller Leak Test
- Shut down the chiller once each year to check the items for Leak Test Chiller
1. Check purge times and unit performance logs. If warranted, pressure leak test
2. Review oil analysis. If required, submit refrigerant sample for analysis
3. Inspect unit for any signs of refrigerant or oil leakage
4. Check unit for any loose screws on flange, volutes, or casing
WARNING
Explosion Hazard!
Failure to follow safe leak test procedures below could result in death or serious injury or equipment or property-only-damage
Never use an open flame to detect gas leaks. Use a leak test solution for leak testing
Access the parts list for your equipment in MaintainX.
Safety Hoist Ring 3/4-10, CTV Unit
RNG01884
Safety Hoist Ring 1/2-13, CTV Unit
RNG01885
Evap Lifting Fixture, CTV Unit
BAR00400
Safety Hoist Ring 3/4-10, CTV Unit
RNG01884
Safety Hoist Ring 1/2-13, CTV Unit
RNG01885
Evap Lifting Fixture, CTV Unit
BAR00400
Safety Hoist Ring 3/4-10, CTV Unit
RNG01884
Safety Hoist Ring 1/2-13, CTV Unit
RNG01885
Evap Lifting Fixture, CTV Unit
BAR00400
MaintainX CoPilot is your expert colleague, on call 24/7, helping your team find the answers they need to keep equipment running.
Reduce Unplanned Downtime
Ensure your team follows consistent procedures to minimize equipment failures and costly delays.
Maximize Asset Availability
Keep your assets running longer and more reliably, with standardized maintenance workflows from OEM manuals.
Lower Maintenance Costs
Turn any technician into an expert to streamline operations, maintain more assets, and reduce overall costs.
Thousands of companies manage their assets with MaintainX