MaintainX Logo
EnterprisePricing
Daikin

Daikin Split System Air Conditioner FCAG71BVEB

Need answers fast?
Explore the manual using AI.

Daikin Split System Air Conditioner FCAG71BVEB
Daikin Split System Air Conditioner FCAG71BVEB

Turn manuals into instant answers
with your AI-powered assistant
Turn manuals into instant answers
with your AI-powered assistant

PDF MANUAL

Manual for Daikin Split System Air Conditioner FCAG71BVEB

MAINTENANCE RESOURCES

Complete asset maintenance, one click away

Get instant access to all the maintenance information you need. Empower technicians to perform preventive maintenance with asset packages, ready to use right out of the box.

Documents

Documents & Manuals

Find all the essential guides in one place.

  • CheckTensioning Guide

  • CheckBelt-diagram

  • CheckC-120 pulleys

  • + 13 more

Work Orders

Work Order Templates

Pre-built workflows to keep your asset running smoothly.

  • CheckDaily Electrical System Inspection

  • CheckReplace Roller and Pulley

  • CheckInstall Engine B-120

  • + 29 more

Procedures

Procedures

Integrate maintenance plans directly into your work orders.

  • CheckMotion Industries

  • CheckApplied Industrial Technologies

  • CheckElectrical Brothers

  • + 5 more

Parts

Parts

Access the parts list for your equipment in MaintainX.

  • CheckDrive Motor

  • CheckB2 Rollers

  • CheckTensioning System

  • + 40 more

Daikin Split System Air Conditioner FCAG71BVEB

Daikin Split System Air Conditioner FCAG71BVEB

Create an account to install this asset package.

Maintenance Plans for Daikin Split System Air Conditioner Model FCAG71BVEB

Integrate maintenance plans directly into your work orders in MaintainX.

5 Yearly Heat Exchanger Maintenance

Check mark

Be aware that the mentioned maintenance and replacement cycles do not relate to the warranty period of the components.

Check mark

NOTICE: The table indicates main components. Refer to your maintenance and inspection contract for more details.

Check mark

The table indicates recommended intervals of maintenance cycles. However, in order to keep the unit operational as long as possible, maintenance work may be required sooner. Recommended intervals can be used for appropriate maintenance design in terms of budgeting maintenance and inspection fees.

Check mark

Depending on the content of the maintenance and inspection contract, inspection and maintenance cycles may in reality be shorter than listed.

Check mark

Heat exchanger replaced?

Check mark

Notes on the condition of the heat exchanger before replacement

Check mark

Upload a photo of the new heat exchanger installed

Check mark

Sign off on the heat exchanger maintenance

Run this procedureArrow right

Suction Grille Cleaning

Check mark

NOTICE: Do NOT use water of 50°C or higher. Possible consequence: Discoloration and deformation.

Check mark

Open the suction grille

Check mark

Remove the suction grille

Check mark

Remove the air filter

Check mark

Clean the suction grille. Wash with a soft bristle brush, and water or neutral detergent. If the suction grille is very dirty, use a typical kitchen cleaner, leave it on for 10 min, then wash it with water.

Check mark

Reattach the air filter (step 3 in reverse order)

Check mark

Reattach the suction grille and close it (step 2 and 1 in reverse order)

Check mark

Sign off on the suction grille cleaning

Run this procedureArrow right

25000 Hourly PCB Maintenance

Check mark

Be aware that the mentioned maintenance and replacement cycles do not relate to the warranty period of the components.

Check mark

Replace PCB

Check mark

The table assumes the following conditions of use:

Check mark

NOTICE

Check mark

The table indicates main components. Refer to your maintenance and inspection contract for more details.

Check mark

The table indicates recommended intervals of maintenance cycles. However, in order to keep the unit operational as long as possible, maintenance work may be required sooner. Recommended intervals can be used for appropriate maintenance design in terms of budgeting maintenance and inspection fees.

Check mark

Depending on the content of the maintenance and inspection contract, inspection and maintenance cycles may in reality be shorter than listed.

Check mark

PCB replaced?

Check mark

Sign off on the PCB replacement

Run this procedureArrow right

1 Yearly Split System Air Conditioner Inspection

Check mark

Be aware that the mentioned maintenance and replacement cycles do not relate to the warranty period of the components.

Check mark

Inspect Electric motor

Check mark

Inspect PCB

Check mark

Inspect Heat exchanger

Check mark

Inspect Sensor (thermistor, etc.)

Check mark

Inspect User interface and switches

Check mark

Inspect Drain pan

Check mark

Inspect Expansion valve

Check mark

Inspect Solenoid valve

Run this procedureArrow right

20000 Hourly Solenoid Valve Maintenance

Check mark

Warning: The mentioned maintenance and replacement cycles do not relate to the warranty period of the components.

Check mark

The table assumes the following conditions of use:

Check mark

NOTICE

Check mark

The table indicates main components. Refer to your maintenance and inspection contract for more details.

Check mark

The table indicates recommended intervals of maintenance cycles. However, in order to keep the unit operational as long as possible, maintenance work may be required sooner. Recommended intervals can be used for appropriate maintenance design in terms of budgeting maintenance and inspection fees.

Check mark

Depending on the content of the maintenance and inspection contract, inspection and maintenance cycles may in reality be shorter than listed.

Check mark

Solenoid valve replaced

Check mark

Enter the current operational hours of the unit

Check mark

Sign off on the solenoid valve maintenance

Run this procedureArrow right

Unlock efficiency
with MaintainX CoPilot

MaintainX CoPilot is your expert colleague, on call 24/7, helping your team find the answers they need to keep equipment running.

Time Lapse Icon

Reduce Unplanned Downtime

Ensure your team follows consistent procedures to minimize equipment failures and costly delays.

Wrench Clock Icon

Maximize Asset Availability

Keep your assets running longer and more reliably, with standardized maintenance workflows from OEM manuals.

Dollar Coin Icon

Lower Maintenance Costs

Turn any technician into an expert to streamline operations, maintain more assets, and reduce overall costs.

Thousands of companies manage their assets with MaintainX

DuracellAB InBevErgonTitan AmericaMeritUnivar SolutionsRivianCadrexMagnaMaasPresriteSoutheast PowerInterrollDuracellAB InBevErgonTitan AmericaMeritUnivar SolutionsRivianCadrexMagnaMaasPresriteSoutheast PowerInterroll

More from Daikin

Explore Other Assets