Turn manuals into instant answers
with your AI-powered assistantTurn manuals into instant answers
with your AI-powered assistant
Get instant access to all the maintenance information you need. Empower technicians to perform preventive maintenance with asset packages, ready to use right out of the box.
Find all the essential guides in one place.
Tensioning Guide
Belt-diagram
C-120 pulleys
+ 13 more
Pre-built workflows to keep your asset running smoothly.
Daily Electrical System Inspection
Replace Roller and Pulley
Install Engine B-120
+ 29 more
Integrate maintenance plans directly into your work orders.
Motion Industries
Applied Industrial Technologies
Electrical Brothers
+ 5 more
Access the parts list for your equipment in MaintainX.
Drive Motor
B2 Rollers
Tensioning System
+ 40 more
Trane CenTraVac™ Water-Cooled Chiller CVHF - 1070-1300 - 1062 - 142M / 142L
Create an account to install this asset package.
Integrate maintenance plans directly into your work orders in MaintainX.
3 Yearly Tubes Maintenance
- Use a non-destructive tube test to inspect the condenser and evaporator tubes
1. It may be desirable to perform tube tests on these components at more frequent intervals depending upon chiller application
2. This is especially true of critical process equipment
3. Ask your Sales account manager for a copy of engineering bulletin (CTV-PRB024*-EN) for clarification of the role of eddy current testing in chiller maintenance by providing information about eddy current technology and heat exchanger tubing;
1 Yearly Optional Accessories Maintenance
- Shut down the chiller once each year to check the items of Optional Accessories
1. If applicable, lubricate factory-installed gantries
2. After the first month of operation, inspect Heresite® or Belzona® coated waterboxes; thereafter, inspect as needed
3. Inspect anodes
4. Inspect and lubricate hinged waterboxes
5. With water flow sensing option, bleed tubing from waterboxes to transformers;
1 Yearly Chiller Leak Test
- Shut down the chiller once each year to check the items for Leak Test Chiller
1. Check purge times and unit performance logs. If warranted, pressure leak test
2. Review oil analysis. If required, submit refrigerant sample for analysis
3. Inspect unit for any signs of refrigerant or oil leakage
4. Check unit for any loose screws on flange, volutes, or casing
WARNING
Explosion Hazard!
Failure to follow safe leak test procedures below could result in death or serious injury or equipment or property-only-damage
Never use an open flame to detect gas leaks. Use a leak test solution for leak testing
6 Monthly Chiller Lubrication
- Lubricate the vane control linkage bearings, ball joints, and pivot points
- Lubricate vane operator tang O- rings
- Lubricate the oil filter shutoff valve O-rings;
1 Yearly Exterior Parts Maintenance
- Shut down the chiller once each year to check the items of Exterior
1. Inlet guide vane linkage
2. Clean and touch-up painted surfaces as needed
3. Repair deteriorated, torn, or missing insulation;
Access the parts list for your equipment in MaintainX.
Safety Hoist Ring 3/4-10, CTV Unit
RNG01884
Safety Hoist Ring 1/2-13, CTV Unit
RNG01885
Evap Lifting Fixture, CTV Unit
BAR00400
Safety Hoist Ring 3/4-10, CTV Unit
RNG01884
Safety Hoist Ring 1/2-13, CTV Unit
RNG01885
Evap Lifting Fixture, CTV Unit
BAR00400
Safety Hoist Ring 3/4-10, CTV Unit
RNG01884
Safety Hoist Ring 1/2-13, CTV Unit
RNG01885
Evap Lifting Fixture, CTV Unit
BAR00400
MaintainX CoPilot is your expert colleague, on call 24/7, helping your team find the answers they need to keep equipment running.
Reduce Unplanned Downtime
Ensure your team follows consistent procedures to minimize equipment failures and costly delays.
Maximize Asset Availability
Keep your assets running longer and more reliably, with standardized maintenance workflows from OEM manuals.
Lower Maintenance Costs
Turn any technician into an expert to streamline operations, maintain more assets, and reduce overall costs.
Thousands of companies manage their assets with MaintainX