Tensioning Guide
Belt-diagram
C-120 pulleys
+ 13 more
Pre-built workflows to keep your asset running smoothly.
Daily Electrical System Inspection
Replace Roller and Pulley
Install Engine B-120
+ 29 more
Integrate maintenance plans directly into your work orders.
Motion Industries
Applied Industrial Technologies
Electrical Brothers
+ 5 more
Access the parts list for your equipment in MaintainX.
Drive Motor
B2 Rollers
Tensioning System
+ 40 more

Mercer Valve Pressure Relief Valve 91-43G51V61I1
Create an account to install this asset package.
Integrate maintenance plans directly into your work orders in MaintainX.
1 Yearly Pressure Relief Valve Visual Inspection
Warning: Ensure the valve is not pressurized before starting the inspection
Cap and Seal Wire in good condition
Flanged Connections in good condition
Threaded Connections in good condition
Outlet free from corrosion or debris
External Surface free from damage
Valve Tag information corresponds to service conditions
If any of the above checks fail, the valve is deemed dangerous to test and should be replaced or repaired immediately
Sign off on the visual inspection
Pressure Relief Valve Offsite Testing
Warning: This procedure requires trained personnel with PPE!
Valves removed from the units and brought to the shop
Valve tested and inspected in the shop
Volume of pressure during testing
Proper assembly of a test bench
Note: The main disadvantage in offsite testing is time
Approximate capacity below the valve when setting for gas/vapor valves
Observation of other valve characteristics (e.g. blowdown)
Volume required for liquid testing
Pressure Relief Valve In Situ Testing
Warning: This procedure requires trained personnel with PPE!
Is the valve accessible for inspection?
If the valve is not accessible, report the issue to the maintenance team and stop the procedure
Is the outlet pipe detached?
Is the internal part of the valve observable for visual inspection?
Is the leak check possible?
Different methods for leak checking are required if the standard method is not applicable
Are block valves present for set pressure testing?
If block valves are not present, report the issue to the maintenance team and stop the procedure
1 Yearly Pressure Relief Valve Maintenance
For dependable performance, PRVs must be maintained regularly.
Mercer Valve Co., Inc. recommends its PRVs are inspected and tested annually.; After the valve has been in installed and a service history has been established, the testing and inspection frequency may be adjusted.
Some guidelines for testing frequencies are found in NB-23, API 576, and API 598.; Additionally, government jurisdiction should be reviewed.; When maintenance is done, qualified repair personnel should perform it.; Qualified repair personnel conducting the annual inspection and testing may alter the maintenance schedule based on the service conditions.
During the inspection, a visual inspection, a set pressure verification, and a leak check should be completed.; These tests can be performed while the PRV is installed on its system or when it’s on a testing bench.; The PRV can only be tested while on its application if there is a method and procedure to apply a controlled pressure to the PRV’s inlet without exceeding any limits of the system.
A visual inspection is used to identify if the PRV is installed properly, is correct for the application, and doesn’t have apparent problems.
Check the nameplate information to verify that the valve is installed on the proper service. A missing nameplate requires immediate addressing.
If the valve is installed on gas/vapor service, the nameplate’s capacity will indicate an air capacity at standard conditions.
If the valve is on liquid service, the nameplate will indicate a water capacity.
Check the seal wire. A broken seal wire indicates that an unqualified person has adjusted the set pressure this also removes any warranty the valve had.
Pressure Relief Valve Testing With Mobile Test Units
Warning: Only trained personnel should perform this procedure
Valve removed from the application
Thorough inspection of the valve performed
Is the valve transport necessary?
Select the type of mobile test unit used
Note: The limitations of the test stand should be documented and the test stand should only be used for the sizes and pressure that it is designed for
Document the limitations of the test stand
Enter the size of the valve
Enter the pressure the valve is designed for
MaintainX CoPilot is your expert colleague, on call 24/7, helping your team find the answers they need to keep equipment running.
Reduce Unplanned Downtime
Ensure your team follows consistent procedures to minimize equipment failures and costly delays.
Maximize Asset Availability
Keep your assets running longer and more reliably, with standardized maintenance workflows from OEM manuals.
Lower Maintenance Costs
Turn any technician into an expert to streamline operations, maintain more assets, and reduce overall costs.
Thousands of companies manage their assets with MaintainX