The Baker Hughes Large Mass Flow Energy Management Control Valves 72000 Series are designed for precision flow control in industrial applications. These valves ensure optimal energy management and efficiency, making them essential for modern energy systems. Their robust design and advanced technology provide reliable performance in demanding environments.
Turn manuals into instant answers
with your AI-powered assistantTurn manuals into instant answers
with your AI-powered assistant
Get instant access to all the maintenance information you need. Empower technicians to perform preventive maintenance with asset packages, ready to use right out of the box.
Find all the essential guides in one place.
Tensioning Guide
Belt-diagram
C-120 pulleys
+ 13 more
Pre-built workflows to keep your asset running smoothly.
Daily Electrical System Inspection
Replace Roller and Pulley
Install Engine B-120
+ 29 more
Integrate maintenance plans directly into your work orders.
Motion Industries
Applied Industrial Technologies
Electrical Brothers
+ 5 more
Access the parts list for your equipment in MaintainX.
Drive Motor
B2 Rollers
Tensioning System
+ 40 more

Baker Hughes Large Mass Flow Energy Management Control Valves 72000 Series
Create an account to install this asset package.
Integrate maintenance plans directly into your work orders in MaintainX.
Conical Springs Maintenance
- For Models that use a conical spring design, always inspect the body bore surface adjacent to where the conical spring (14) is seated. If this surface has been deformed or if there is a groove where the seal seats, the surface should be cleaned and honed prior to reassembling the valve.
- If the refinishing procedure is unsuccessful, the factory should be consulted for further instructions.;
Gaskets Maintenance
Gasket seating surfaces must be free of dents, scratches, corrosion, or other types of damage. Clean mating surfaces as required and replace any non-conforming parts. Spiral wound gaskets (Items 25, 26 & 27) must always be replaced after disassembly.;
Guiding Surfaces Maintenance
- Prior to reassembly, examine parts carefully for any scratches, unusual wear, or other damage.; Guiding surfaces of the cage, valve plug, guide bushing, plug stem, and auxiliary pilot plug must be checked. If there are only slight wear indications, then gently use a light abrasive, such as Scotchbrite® or fine grit sandpaper, to smooth out guiding surfaces. Parts with significant damage or wear on the guiding surfaces must be replaced.;
Metal Seal Maintenance
For the two piece bonnet configurations: - Prior to reassembly, the metal seal (6) should be inspected for cracks or signs of wear. The metal seal can be reused if it is free from scratches, erosion, corrosion, or any other type of damage.
- If slight wear exists on the metal seal, a new layer of coating should be re-applied to the original condition by the factory or a Masoneilan Authorized Repair Center (MARC'). For emergency repairs in the field, the metal seal may be coated with a molybdenum disulfide based spray on lubricant such as MolyKote®.
- Prior to reassembly of the valve, inspect the inside of the valve body around the area where the metal seal seats. It is common to find slight ridges or depressions from where the seal was originally seated. During initial assembly these depressions aid in the sealing of the valve, however these areas can become leak paths during reassembly if the surface is not restored to its original finish as described below.
- To prevent this potential leakage, machine the seating angle of the bonnet at 40 degrees by approximately 0.1 inches (2.5 mm) deep, thus causing the metal seal to seat further down inside the valve body (on a new undeformed surface). Refer to Figure 7 for details.;
Packing Box Maintenance
- Tight sealing within the packing box is obtained by compression of the packing (19).; Compression must be achieved by evenly tightening the packing flange nuts (16) on the packing flange (17).; Periodic re-tightening of the packing flange nuts may be required to maintain proper sealing.
- Be careful not to over tighten the packing as this could prevent proper operation of the valve.; If leakage persists after maximum packing compression, then the packing needs to be changed.;
Access the parts list for your equipment in MaintainX.
Auxiliary Pilot Plug
-
Back-Up Ring
-
Body
-
Body Gasket
-
Body Nut
-
Auxiliary Pilot Plug
-
Back-Up Ring
-
Body
-
Body Gasket
-
Body Nut
-
Auxiliary Pilot Plug
-
Back-Up Ring
-
Body
-
Body Gasket
-
Body Nut
-
MaintainX CoPilot is your expert colleague, on call 24/7, helping your team find the answers they need to keep equipment running.
Reduce Unplanned Downtime
Ensure your team follows consistent procedures to minimize equipment failures and costly delays.
Maximize Asset Availability
Keep your assets running longer and more reliably, with standardized maintenance workflows from OEM manuals.
Lower Maintenance Costs
Turn any technician into an expert to streamline operations, maintain more assets, and reduce overall costs.
Thousands of companies manage their assets with MaintainX