Back

AHU Quarterly Maintenance Procedure

Please ensure that all steps in the procedure are completed, and include comments in the project management system listing the results.
Mt. Dora - Curaleaf
04/17/2024

AHU Quarterly Maintenance Procedure

Please ensure that all steps in the procedure are completed, and include comments in the project management system listing the results.

    Initial Site Inspection. Time - 5 Min.

    • Pass
    • Flag
    • Fail

    Initial Site/Safety Survey

    Please Complete the Check Boxes on all work

    Site Safety Survey

    Safety Survey

    Review Diagnostics. List active faults. Time - 5 min.

    Visual Electrical Inspection. List any issues found in comments and make repairs. Time - 5 min.

    • Pass
    • Flag
    • Fail

    Visual Inspection for Abnormality, Damage and Missing Hardware. Time - 5 min.

    • Pass
    • Flag
    • Fail

    Verify Operating Voltages. Time - 10 min. Please list voltages below.

    Review Operation. Time - 10 min.

    • Pass
    • Flag
    • Fail
Source: Mt. Dora - Curaleaf (Community Member)

Please note that any procedure, checklist, or other document available in the MaintainX Global Procedure Library is provided for general education and information only and does not constitute legal, medical, or financial advice. MaintainX makes the materials available AS IS and AS PROVIDED, without warranties of any kind. By downloading or using any such materials, you assume the risk that they may not be appropriate for your specific situation and agree that you are solely responsible for any such use, including compliance with applicable law and with meeting any conditions of product warranties.