The Parsons Monthly Preventive Maintenance (PM) procedure outlines a comprehensive checklist to ensure the safe and efficient operation of equipment at the Alphia – Woodland facility. This monthly inspection is designed to identify early signs of wear, contamination, or misalignment in key mechanical and pneumatic systems.
Alphia - Woodland
06/27/2025

PARSONS MONTHLY Preventive Maintenance

The Parsons Monthly Preventive Maintenance (PM) procedure outlines a comprehensive checklist to ensure the safe and efficient operation of equipment at the Alphia – Woodland facility. This monthly inspection is designed to identify early signs of wear, contamination, or misalignment in key mechanical and pneumatic systems.

    LOTO REQUIRED? Ensure Lockout Tagout procedures are followed before starting maintenance.

    Grease zerks with multi-purpose synthetic grease until first sign of grease around the seal.

    • Pass
    • Flag
    • Fail

    Check tension and condition of belts, pulleys, and set screws.

    • Pass
    • Flag
    • Fail

    Check tension and alignment of sprockets, inspect for wear.

    • Pass
    • Flag
    • Fail

    Drain water from air separator and check oil level in air oiler.

    • Pass
    • Flag
    • Fail

    Inspect air filter for dirt and debris, replace if necessary.

    • Pass
    • Flag
    • Fail

    Check for air leaks in valves, hoses, and cylinders.

    • Pass
    • Flag
    • Fail

    Inspect vacuum cups for cracks and wear, clean filters.

    • Pass
    • Flag
    • Fail

    Check vacuum generators for dirt, clean out obstructions.

    • Pass
    • Flag
    • Fail

    Inspect Prox switches, clean dust and debris.

    • Pass
    • Flag
    • Fail

    Clean behind the Buckets.

    • Pass
    • Flag
    • Fail

    Remove and clean top and bottom buckets from designated scale heads.

    • Pass
    • Flag
    • Fail

    Replace top bolts with precut all thread for scale heads maintenance.

    • Pass
    • Flag
    • Fail

    Slide out scale heads on all thread rods and vacuum behind them.

    • Pass
    • Flag
    • Fail

    Reassemble units after cleaning, ensuring correct orientation.

    • Pass
    • Flag
    • Fail

    Check all doors, emergency stops, and interlocks for proper operation.

    • Pass
    • Flag
    • Fail

    Ensure all guards

    • Pass
    • Flag
    • Fail

    Notify supervisor that equipment requires sanitization.

    • Pass
    • Flag
    • Fail

    All tools accounted for and sanitized?

    • Yes
    • No
    • N / A

    Sign here to confirm completion of maintenance procedure.

    Click here to sign
Source: Alphia - Woodland (Community Member)

Please note that any procedure, checklist, or other document available in the MaintainX Procedure Hub is provided for general education and information only and does not constitute legal, medical, or financial advice. MaintainX makes the materials available AS IS and AS PROVIDED, without warranties of any kind. By downloading or using any such materials, you assume the risk that they may not be appropriate for your specific situation and agree that you are solely responsible for any such use, including compliance with applicable law and with meeting any conditions of product warranties.