ONE PRETIUM-ZHONGYA-1500HR-PREVENTATIVE MAINTENANCE

This procedure walks through the 1500-hour preventative maintenance for the ZHONGYA machine to keep it running safely and reliably. It covers pre-shutdown checks, lockout/tagout, lubrication and fluid checks, electrical and mechanical inspections, cleaning, and a full start-up verification once the work is complete.
Pretium - BET
02/17/2026

ONE PRETIUM-ZHONGYA-1500HR-PREVENTATIVE MAINTENANCE

This procedure outlines the steps for performing a 1500-hour preventative maintenance on the ZHONGYA machine, including pre-shutdown inspections, safety checks, lubrication, fluid level checks, electrical and mechanical maintenance, cleaning, and post-maintenance activities. It ensures the machine is properly maintained and operational, with all safety and functional checks completed.

    Pre-Shutdown Inspection

    Record oil temperature

    Measure and record the current oil temperature.

    Meter name
    Unit

    Observe machine for abnormal noises and movements

    Check for any unusual sounds or movements in the machine.

    • Yes
    • No
    • N / A

    Inspect machine for oil leaks

    Record or tag any oil leaks found and repair during PM.

    • Pass
    • Flag
    • Fail

    Inspect all machine hoses for damage or wear

    Tag any damaged or worn hoses for repair or replacement during PM.

    • Pass
    • Flag
    • Fail

    Check inside pneumatic cabinet for air leaks

    Tag any air leaks for repair during PM.

    • Pass
    • Flag
    • Fail

    Safety Checks

    Inspect and test door electrical, hydraulic, and air safety interlocks

    • Pass
    • Flag
    • Fail

    Verify clamp safety pin engagement

    Open each safety door and ensure the clamp safety pin is engaged.

    • Pass
    • Flag
    • Fail

    Check all 'E' stops for proper function and operation

    Replace any non-functioning 'E' stops as needed.

    • Pass
    • Flag
    • Fail

    Lubrication

    Apply EP2 Lithium based grease to main pump motor bearings

    Apply 2 shots of grease to the Zerk fittings on the front side only.

    Grease injection and blow mold leader pins & bushings

    Ensure all necessary parts are greased and excess is wiped off.

    • Pass
    • Flag
    • Fail

    Fluid Level Checks

    Check main hydraulic tank oil level and fill as needed

    • Pass
    • Flag
    • Fail

    Check head rotate gearbox oil levels

    Ensure sight glass is clean and oil levels are adequate.

    • Pass
    • Flag
    • Fail

    Check retro fit grease packs for injection main bearing

    Determine if they are full, empty, or flashing life span.

    • Pass
    • Flag
    • Fail

    Ensure lubrication reservoir on auto greaser system is full and functioning

    • Pass
    • Flag
    • Fail

    Check each grease line for damage and repair as found

    • Pass
    • Flag
    • Fail

    ONE PRETIUM-ENG: LOCKOUT/TAGOUT- ESP: BLOQUEO/ETIQUETADO

    Steps to properly Lock out and Tag out! ¡Pasos para bloquear y etiquetar correctamente!

    ENG: Is this a FULL LOTO or an MSE / ESP: ¿Es esto un LOTO COMPLETO o una MSE?

    ENG: Notify Affected Employee(s) / ESP: Notificar a las empleadas afectadas)

    ENG: Properly Shut Down the Machine/Equipment where needed. / ESP: Apague adecuadamente la máquina/equipo cuando sea necesario.

    ENG: Isolate all energy Sources needed. / ESP: Aislar todas las fuentes de energía necesarias.

    ENG: Apply the Lock, Tag, and Lock Out Devices where needed. / ESP: Aplique los dispositivos de bloqueo, etiqueta y bloqueo donde sea necesario.

    ENG: Attached Lock(s) / ESP:¿Candado adjunto?

    ENG: Please attach a photo of your locks on the Equipment. ESP: Adjunte una foto de sus cerraduras en el equipo.

    if the answer is "oneOf [LOTO]"

    ENG: Please Provide a Photo / ESP: Por favor proporcione una foto

    ENG: Take a Photo of the LOTO device on the Equipment. ESP: Tome una fotografía del dispositivo LOTO en el equipo.

    Add or drag pictures

    ENG: Verify Total of De-Energization of Sources needed to lock out. / ESP: Verificar Total de Desenergización de Fuentes necesarias para bloquear.

    ENG: Employee Lock Number or Company Lock / ESP: Número de bloqueo de empleado o bloqueo de empresa

    ENG: Authorized Employees Working on the Machine / ESP: Empleados autorizados que trabajan en la máquina

    Click here to sign

    ENG: Authorized Employees Working on the Machine / ESP: Empleados autorizados que trabajan en la máquina

    Click here to sign

    ENG: Authorized Employees Working on the Machine / ESP: Empleados autorizados que trabajan en la máquina

    Click here to sign

    Electrical Inspection

    Inspect all wiring inside panel for damage and bare wires

    • Pass
    • Flag
    • Fail

    Check all switches and lights on control panel

    Replace any broken switches or lights.

    • Pass
    • Flag
    • Fail

    Clean drive motor and door air vents using compressed air

    • Pass
    • Flag
    • Fail

    Replace all door filters

    • Pass
    • Flag
    • Fail

    Ensure all electrical connection box covers are in place and no broken conduits

    • Pass
    • Flag
    • Fail

    Inspect all wires and cables for damage and poor repairs

    Replace as required.

    • Pass
    • Flag
    • Fail

    Mechanical Maintenance

    Change hydraulic oil filters (all 3)

    • Pass
    • Flag
    • Fail

    Replace low pressure air filter on the drop to the machine

    • Pass
    • Flag
    • Fail

    Check oil tank desiccant breather cap

    Replace if flashing or over 6 months old.

    • Pass
    • Flag
    • Fail

    Change out Blow Air Exhaust Mufflers

    • Pass
    • Flag
    • Fail

    Check stripper assembly for excessive movement

    Ensure it is tight to move; replace if too much play.

    • Pass
    • Flag
    • Fail

    Check injection clamp tie rods nuts for broken or missing bolts

    • Pass
    • Flag
    • Fail

    Repair or replace any air, oil, water leaks, and damaged hoses found during pre-shutdown inspection

    • Pass
    • Flag
    • Fail

    Cleaning

    Clean around exterior of machine and remove all old oil pads/socks

    • Pass
    • Flag
    • Fail

    Clean up on top of and inside machine

    Remove any old oil soakers and clean up material spillage.

    • Pass
    • Flag
    • Fail

    Clean windows and pick up any old soak mats

    Ensure no new mats are placed as oil leaks should be repaired during PM.

    • Pass
    • Flag
    • Fail

    Machine Release and Start Up

    Ensure all services are turned on and all LOTO removed

    • Pass
    • Flag
    • Fail

    Ensure all guards and doors are in place and closed

    • Pass
    • Flag
    • Fail

    Test cycle machine to ensure proper operation

    • Pass
    • Flag
    • Fail

    Report any items not covered during the PM or if parts are not available to repair

    Post-Maintenance Cleanup

    Clean all oil and grease from equipment after job completion

    • Pass
    • Flag
    • Fail

    Ensure all tools, bolts, nuts, etc. are picked up and properly stored

    • Pass
    • Flag
    • Fail

    Leave area in a clean condition complying with Alpha Food Safety Policy

    • Pass
    • Flag
    • Fail

    Signatures

    Maintenance Technician Signature

    Click here to sign

    Maintenance Manager Signature

    Click here to sign
Source: Pretium - BET (Community Member)

Please note that any procedure, checklist, or other document available in the MaintainX Procedure Hub is provided for general education and information only and does not constitute legal, medical, or financial advice. MaintainX makes the materials available AS IS and AS PROVIDED, without warranties of any kind. By downloading or using any such materials, you assume the risk that they may not be appropriate for your specific situation and agree that you are solely responsible for any such use, including compliance with applicable law and with meeting any conditions of product warranties.