The checklist's aim is to ensure the accurate performance and reliability of the capillary system by conducting regular monthly testing and inspection. onsistent monthly testing helps maintain optimal equipment performance, prevent process interruptions, and support safety and quality control standards within the operation.
1M - FL08 - Monthly Capillary test
The checklist's aim is to ensure the accurate performance and reliability of the capillary system by conducting regular monthly testing and inspection. onsistent monthly testing helps maintain optimal equipment performance, prevent process interruptions, and support safety and quality control standards within the operation.
Maintenance Tasks
Inspect and Replace O-rings
Enter the current air pressure of the booster
Meter name
Unit
Is the booster starting at the correct air pressure?
Check Air Pressure
Clean Components
Inspect Valves
Check for Leaks
Safety Checks
Ensure all safety equipment is mounted and in perfect condition
PPM Sign Off
Production sign off procedure for Building 3
Equipment has been checked after PPM work and is safe, clean, and ready for production
if the answer is "oneOf [Yes]"
Equipment accepted back into production
Click here to sign
if the answer is "oneOf [No]"
Please inform maintenance manager that additional work is required before Signoff is completed