FPI Recycle Startup - Service Mode
This is a startup Procedure for FPI Recycle - Service Mode with pump running. This includes inspection and cleaning of valves, rotameter, tanks and pumps.
FPI Recycle Startup - Service Mode
This is a startup Procedure for FPI Recycle - Service Mode with pump running. This includes inspection and cleaning of valves, rotameter, tanks and pumps.
Are feed valves FV#1 and FV#2 are open?
if the answer is "oneOf [No]"
Are there any leaks or damage?
if the answer is "oneOf [Yes]"
Is area clean and free of debris?
if the answer is "oneOf [No]"
Permate Discharge Valve is open
if the answer is "oneOf [No]"
Is the tank level on polytank below red line (less than 1/4 full)?
if the answer is "oneOf [Yes]"
With pump#1 (service mode) on, is the pressure gauge PG#1 between 180-210 psi?
if the answer is "oneOf [No]"
With pump#1 on, is the flow rate on rotameters within 0.13gpm and 0.5gpm?
if the answer is "oneOf [No]"
Is the rotameter RM#3 flowrate within 3gpm and 4gpm?
if the answer is "oneOf [No]"
Source: Precision Metal Products (Community Member)