30,000 Hour Dekker Maintenance Preventive Maintenance
This maintenance schedule outlines the necessary checks and actions to ensure the Mach1 Vacuum Pump operates efficiently. It includes initial checks after the first 8 hours, daily and weekly maintenance tasks, and more extensive checks at 500, 1000, 10,000, and 30,000 hours of operation.
30,000 Hour Dekker Maintenance Preventive Maintenance
This maintenance schedule outlines the necessary checks and actions to ensure the Mach1 Vacuum Pump operates efficiently. It includes initial checks after the first 8 hours, daily and weekly maintenance tasks, and more extensive checks at 500, 1000, 10,000, and 30,000 hours of operation.
Record Hours
Meter name
Unit
First 8 Hours of Operation
Check initial conditions
Daily Maintenance
Perform daily checks
Inspect for leaks
Weekly Maintenance
Perform weekly checks
Inspect for leaks
500 Hours of Operation
Perform 500-hour checks
Under normal operating conditions, repeat the daily steps above and,
1000 Hours of Operation
Check back pressure on separator element (should not exceed 4 psig)
Meter name
Unit
Change separator element if back pressure exceeds 4 psig
Perform 1000-hour checks
10,000 Hours of Operation
Change seal fluid using DEKKER Vmaxol seal fluid
Change separator element if back pressure exceeds 4 psig
Check coupling element for wear and replace if worn
Clean strainer in seal fluid line
30,000 Hours of Operation
Schedule tech (Vantage pump) San Antonio
Replace vacuum pump’s mechanical seals and bearings
This should be done by a DEKKER authorized distributor or properly trained service technician.
Source: 299 New Waverly (Community Member)