Back

Paint Line Audit

This audit evaluates various components of the paint line, including equipment, procedures, material usage, and quality control processes. The goal is to identify areas for improvement, ensure consistency, and optimize the efficiency of the paint line.
Depor Industries
11/12/2024

Paint Line Audit

This audit evaluates various components of the paint line, including equipment, procedures, material usage, and quality control processes. The goal is to identify areas for improvement, ensure consistency, and optimize the efficiency of the paint line.
Procedure Max Score: 20

    Auditor Line Information

    Operator Name

    Shift

    Work order #

    Part number

    Customer

    Paint Specs

    Paint Type

    Viscosity Readings

    Paint Temperature

    Last Viscosity Check Time

    Last Basket Changed Time

    Basket Condition

    • Pass
    • Flag
    • Fail

    Spacer Bar

    • Yes
    • No
    • N / A

    Samples from Each Tub

    • Yes
    • No
    • N / A

    Correct Paint per Work Order

    • Yes
    • No
    • N / A

    Load Size

    Plant Floor Parameters

    Written on Production Log

    Actual Running Parameters

    Dip Time

    Actual Running Parameters

    RPM

    Plant Floor Parameters

    Written on Production Log

    Actual Running Parameters

    Spin Time

    Plant Floor Parameters

    Written on Production Log

    Actual Running Parameters

    Number Of Spins

    Plant Floor Parameters

    Written on Production Log

    Actual Running Parameter

    Programs *Line 4 Only*

    Plant Floor Parameters

    Written on Production Log

    Actual Running Parameters

    Pre Cure Oven Temperature

    Oven Temperature Reference Sheet

    Written on Production Log

    Actual Running Parameters

    Cure Oven Temperature

    Oven Temperature Reference Sheet

    Written on Production Log

    Actual Running Parameters

    Continuation

    Look Alike Parts

    • Yes
    • No
    • N / A

    1st/Last Basket Insp

    • Yes
    • No
    • N / A

    Correct WO/TubTag

    • Yes
    • No
    • N / A

    Head/Thread Fill

    • Yes
    • No
    • N / A

    Foreign Material

    In the next field, you will need to take two photos even if there are no foreign materials.

    • Yes
    • No
    • N / A

    Paint Coverage

    • Yes
    • No
    • N / A

    Tubs Overfilled

    • Yes
    • No
    • N / A

    End Of Lot Check

    • Yes
    • No
    • N / A

    Cleanliness

    Please add a photo for any discrepancies

    Parts Underneath Belt In Oven (if yes take photos)

    • Yes
    • No
    • N / A

    OPERATOR INITIAL SPECIAL INSTRUCTIONS

    • Yes
    • No
    • N / A

    Audit Results

    Did you watch 3 baskets dump?

    • Yes
    • No
    • N / A

    Pass or Failed Audit

    • Pass
    • Flag
    • Fail

    Auditor name

    Signature

    Click here to sign
Source: Depor Industries (Community Member)

Please note that any procedure, checklist, or other document available in the MaintainX Procedure Hub is provided for general education and information only and does not constitute legal, medical, or financial advice. MaintainX makes the materials available AS IS and AS PROVIDED, without warranties of any kind. By downloading or using any such materials, you assume the risk that they may not be appropriate for your specific situation and agree that you are solely responsible for any such use, including compliance with applicable law and with meeting any conditions of product warranties.