Quarterly Line Guarding and Safety Systems PM

A quarterly preventive maintenance check of all line guarding and safety systems to inspect and verify the condition and functionality of guards, interlocks, emergency stops, and safety sensors, ensuring all protective systems remain fully operational and compliant with applicable workplace safety requirements.
Amcor - PRY
02/27/2026

Quarterly Line Guarding and Safety Systems PM

This procedure outlines the requirements for conducting Quarterly Line Guarding and Safety Systems Preventive Maintenance inspections across all line assets and sub-assets. It ensures that guards, interlocks, light curtains, emergency stops, and related safety devices are properly functioning, securely installed, and compliant with safety standards before equipment is returned to operation.

    LOCKOUT/TAGOUT PROCEDURES MUST BE FOLLOWED AT ALL TIMES

    APPROPRIATE PPE MUST BE WORN AT ALL TIMES

    THIS PM IS FOR THE COMPLETE LINE TO INCLUDE ALL ASSETS AND SUBASSETS ON THE LINE AND ALSO ALL GUARD RAILS ON STAIRWAYS, MEZZANINES, PLATFORMS, ETC. ,

    THIS PM HAS AN IMMEDIATE REPAIR DESIGNATION, IF ANYTHING IS FOUND TO BE INOPERABLE, DAMAGED, MISSING, ETC., IT IS TO BE REPAIRED IMMEDIATELY BEFORE RETURNING EQUIPMENT TO OPERATION

    ARE ALL BARRIER GUARDS IN GOOD CONDITION, NO DAMAGE OR MISSING PIECES, ETC

    ARE ALL FIXED GUARDS IN GOOD CONDITION AND SECURELY FASTENED

    ARE ALL LIGHT CURTAINS WORKING CORRECTLY, CORRECTLY ALIGNED , SECURELY MOUNTED AND CURTAINS MOUNTING APPARATUS IN GOOD CONDITION AND SECURELY MOUNTED.

    CHECK INTERLOCKS FOR OPERATION, ARE THEY FUNCTIONING CORRECTLY

    TIME IT TAKES FOR STOP WHEN INTERLOCK IS ACTIVATED

    CHECK ALL E-STOP BUTTONS, E-STOP CABLES AND PULL CORDS ARE IN GOOD CONDITION, CHECK FOR OPERATION

    TIME IT TAKES TO STOP WHEN E-STOP IS ACTIVATED

    CHECK ALL SLITTER OPERATIONS, AS APPLICABLE, ENSURE THAT IF THEY ARE RETRACTABLE, THEY ARE RETRACTED TO A SAFE CONDITION IF AN E-STOP IS ACTIVATED

    • Pass
    • Flag
    • Fail

    CHECK THAT ALL AUTO-CUTOVERS OR MANUAL CUTOVERS ARE IN GOOD OPERABLE CONDITION, NO DAMAGE.

    • Pass
    • Flag
    • Fail

    CHECK ALL BRAKE OPERATION, AS APPLICABLE, ON ASSETS.S AND SUB-ASSETS, ENSURE THAT WHEN BRAKE IS APPLIED ASSOCIATED EQUIPMENT STOP, ADJUST AS REQUIRED.

    • Pass
    • Flag
    • Fail

    CHECK ALL LIMIT SWITCHES AND PROXIMITY SWITCHES FOR DAMAGE, CORRECT ALIGNMENT AND ADJUSTMENTS.

    • Pass
    • Flag
    • Fail

    CHECK ALL WARNING DEVICES IF LINE IS EQUIPPED FOR CORRECT OPERATION

    • Pass
    • Flag
    • Fail

    CHECK THAT ALL WARNING SIGNS ARE INSTALLED AND READABLE,

    • Pass
    • Flag
    • Fail

    COMMENT:

    DATE

    TECHNICIAN SIGNATURE

    Click here to sign
Source: Amcor - PRY (Community Member)

Please note that any procedure, checklist, or other document available in the MaintainX Procedure Hub is provided for general education and information only and does not constitute legal, medical, or financial advice. MaintainX makes the materials available AS IS and AS PROVIDED, without warranties of any kind. By downloading or using any such materials, you assume the risk that they may not be appropriate for your specific situation and agree that you are solely responsible for any such use, including compliance with applicable law and with meeting any conditions of product warranties.