4-Week Forklift PM Inspection

A 4-week preventive maintenance inspection of all forklifts to evaluate and service all critical hydraulic, mechanical, battery, and safety components, ensuring each unit remains in safe operating condition and performs reliably across all assigned material handling operations.
Pacific Seafood - Woodland
08/13/2026

4-Week Forklift PM Inspection

This procedure outlines the steps for conducting a monthly preventive maintenance inspection on forklifts, ensuring all safety and mechanical components are checked and fluid levels are assessed.

    Pre-Inspection Requirements

    If there are any deficiencies, has the unit been locked out and management notified?

    • Yes
    • No
    • N / A

    Safety Checks

    Check that all safety components are in place and functional

    Mechanical Checks

    Accelerator

    Brakes - Parking

    Brakes - Service

    Hydraulic Controls

    Steering

    Oil Leaks

    • Pass
    • Flag
    • Fail

    Tires

    • Pass
    • Flag
    • Fail

    Fluid Levels

    Engine Oil Level

    Fuel Level

    Radiator

    • Pass
    • Flag
    • Fail

    Oil Pressure

    • Pass
    • Flag
    • Fail

    Comments

    Additional comments or observations

Source: Pacific Seafood - Woodland (Community Member)

Please note that any procedure, checklist, or other document available in the MaintainX Procedure Hub is provided for general education and information only and does not constitute legal, medical, or financial advice. MaintainX makes the materials available AS IS and AS PROVIDED, without warranties of any kind. By downloading or using any such materials, you assume the risk that they may not be appropriate for your specific situation and agree that you are solely responsible for any such use, including compliance with applicable law and with meeting any conditions of product warranties.