Daikin CENTRIFUGAL CHILLER, SINGLE COMPRESSOR: After First Month of Operation Maintenance

The following Maintenance Procedures should only be maintained by qualified service personnel. This procedure focuses on re-tourquing all power connections, including pre-wired equipment. This also checks the proper operation of fans if these were properly installed.
MaintainX
08/10/2022

Daikin CENTRIFUGAL CHILLER, SINGLE COMPRESSOR: After First Month of Operation Maintenance

The following Maintenance Procedures should only be maintained by qualified service personnel. This procedure focuses on re-tourquing all power connections, including pre-wired equipment. This also checks the proper operation of fans if these were properly installed.

    One Month After Commissioning Maintenance

Source: MaintainX (Community Member)

Please note that any procedure, checklist, or other document available in the MaintainX Global Procedure Library is provided for general education and information only and does not constitute legal, medical, or financial advice. MaintainX makes the materials available AS IS and AS PROVIDED, without warranties of any kind. By downloading or using any such materials, you assume the risk that they may not be appropriate for your specific situation and agree that you are solely responsible for any such use, including compliance with applicable law and with meeting any conditions of product warranties.