Back

Mechanical and Lightning Daily Checklist

Use this guideline for the daily inspection and maintenance of your lightning and mechanical room.
QPI
04/18/2023

Mechanical and Lightning Daily Checklist

Use this guideline for the daily inspection and maintenance of your lightning and mechanical room.

    1.1 Lighting – Emergency (EXIT) lighting is functioning.

    • Pass
    • Flag
    • Fail

    2.1 Mechanical Room – Boiler/furnaces functioning properly.

    • Pass
    • Flag
    • Fail

    2.2 Mechanical Room – Bleeder is on, valves open (upright is off).

    • Pass
    • Flag
    • Fail

    2.3 Mechanical Room – Visual check of all units (no leaks).

    • Pass
    • Flag
    • Fail

    2.4 Mechanical Room – Check glycol temperature (should be between 150-170).

    • Pass
    • Flag
    • Fail

    2.5 Mechanical Room – Check PSI temperature (should be between 15-20).

    • Pass
    • Flag
    • Fail

    3.1 Safety – No obstructions to emergency exits.

    • Pass
    • Flag
    • Fail

    3.2 Safety – Exterior stairs are in good condition, clear of ice buildup.

    • Pass
    • Flag
    • Fail

    3.3 Safety – Exterior accessibility ramps are in good condition, clear of debris.

    • Pass
    • Flag
    • Fail

    4.1 Electrical – Panels functioning properly.

    • Pass
    • Flag
    • Fail

    4.2 Electrical – Backup generators functioning.

    • Pass
    • Flag
    • Fail

    5.1 HVAC – Systems functioning properly, no issues.

    • Pass
    • Flag
    • Fail

    5.2 HVAC – AHU is working (30-50 is normal).

    • Pass
    • Flag
    • Fail

    6.1 Plumbing – Systems are functioning properly, no issues.

    • Pass
    • Flag
    • Fail

    6.2 Plumbing – Run water in 1st floor washroom to ensure no backup/frozen drain.

    • Pass
    • Flag
    • Fail

    6.3 Plumbing – No leaks on water booster or circulation pump.

    • Pass
    • Flag
    • Fail

    7.2 Exterior – Driveway and parking lot are clear of debris, garbage, etc.

    • Pass
    • Flag
    • Fail

    8.1 Snow – Parking lot, walkways, driveways have been plowed and/or sanded.

    • Pass
    • Flag
    • Fail

    Igluvut.1 - Turn on lights for the building on the relay panel.

    • Pass
    • Flag
    • Fail

    Igluvut.2 - Honeywell computer, acknowledge alarms, ensure no alarms on auto dialer.

    • Pass
    • Flag
    • Fail

    Igluvut.3 - (FRIDAY ONLY) Run generator, ensure proper functioning.

    • Pass
    • Flag
    • Fail

    Inuksug.1 - (FRIDAY ONLY) Run generator, ensure proper functioning.

    • Pass
    • Flag
    • Fail
Source: QPI (Community Member)

Please note that any procedure, checklist, or other document available in the MaintainX Global Procedure Library is provided for general education and information only and does not constitute legal, medical, or financial advice. MaintainX makes the materials available AS IS and AS PROVIDED, without warranties of any kind. By downloading or using any such materials, you assume the risk that they may not be appropriate for your specific situation and agree that you are solely responsible for any such use, including compliance with applicable law and with meeting any conditions of product warranties.