AHU Quarterly Maintenance Procedure.

Use this checklist each quarter to complete every step on the AHU and record your findings and any voltage readings in the comments.
Mt. Dora - Curaleaf
02/24/2026

AHU Quarterly Maintenance Procedure.

This procedure outlines the quarterly preventive maintenance required to keep the air handling unit (AHU) operating safely, efficiently, and reliably. It guides the technician through safety checks, inspections, cleaning, electrical verification, and operational review, with results documented for each unit.

    Initial Site Inspection. Time - 5 Min.

    • Pass
    • Flag
    • Fail

    Initial Site/Safety Survey

    Please Complete the Check Boxes on all work

    Site Safety Survey

    Safety Survey

    Lockout Tagout Has Been Performed Procedure

    LOTO Print to Fill Form

    Lockout/Tagout has been performed.

    • Yes
    • No
    • N / A

    Review Diagnostics. List active faults. Time - 5 min.

    Visual Electrical Inspection. List any issues found in comments and make repairs. Time - 5 min.

    • Pass
    • Flag
    • Fail

    Visual Inspection for Abnormality, Damage and Missing Hardware. Time - 5 min.

    • Pass
    • Flag
    • Fail

    Verify Operating Voltages. Time - 10 min. Please list voltages below.

    Review Operation. Time - 10 min.

    • Pass
    • Flag
    • Fail
Source: Mt. Dora - Curaleaf (Community Member)

Please note that any procedure, checklist, or other document available in the MaintainX Procedure Hub is provided for general education and information only and does not constitute legal, medical, or financial advice. MaintainX makes the materials available AS IS and AS PROVIDED, without warranties of any kind. By downloading or using any such materials, you assume the risk that they may not be appropriate for your specific situation and agree that you are solely responsible for any such use, including compliance with applicable law and with meeting any conditions of product warranties.