AHU Quarterly Maintenance Procedure.
Use this checklist each quarter to complete every step on the AHU and record your findings and any voltage readings in the comments.
AHU Quarterly Maintenance Procedure.
This procedure outlines the quarterly preventive maintenance required to keep the air handling unit (AHU) operating safely, efficiently, and reliably. It guides the technician through safety checks, inspections, cleaning, electrical verification, and operational review, with results documented for each unit.
Initial Site Inspection. Time - 5 Min.
Initial Site/Safety Survey
Please Complete the Check Boxes on all work
Site Safety Survey
Safety Survey
Lockout Tagout Has Been Performed Procedure
LOTO Print to Fill Form
Lockout/Tagout has been performed.
Review Diagnostics. List active faults. Time - 5 min.
Visual Electrical Inspection. List any issues found in comments and make repairs. Time - 5 min.
Visual Inspection for Abnormality, Damage and Missing Hardware. Time - 5 min.
Verify Operating Voltages. Time - 10 min. Please list voltages below.
Review Operation. Time - 10 min.
Source: Mt. Dora - Curaleaf (Community Member)