Back

KOT Build/Service Fleet

This process for assembling, servicing, and maintaining the fleet of KOT (Key Operating Tools) vehicles and equipment. This includes regular inspections, repairs, and upgrades to ensure that the fleet remains operational, safe, and efficient for daily use in fulfilling operational tasks.
ErgoFlex
05/13/2025

KOT Build/Service Fleet

This process for assembling, servicing, and maintaining the fleet of KOT (Key Operating Tools) vehicles and equipment. This includes regular inspections, repairs, and upgrades to ensure that the fleet remains operational, safe, and efficient for daily use in fulfilling operational tasks.

    Choose which type to build

    if the answer is "oneOf [New KOT Build]"

    New Unit Knee On Trac Device Master Records

    PRODUCTION TECHNICIAN SECTION

    • KOTimage.jpg

    FRAME INSPECTION

    Notes

    Ensure all parts are included in traction box with unit; black barrel spacer with hardware, 2 wheels, 1" cushion plate, 2" cushion plate, and actuator spacer

    • Pass
    • Flag
    • Fail

    Ensure hand adjustment knob is installed and operates correctly

    • Pass
    • Flag
    • Fail

    Ensure both trays and frame are straight and evenly spaced

    • Pass
    • Flag
    • Fail

    Ensure both adjustment tray drawers slide in and out smoothly and effortlessly

    • Pass
    • Flag
    • Fail

    Ensure both trays are free of all debris 

    • Pass
    • Flag
    • Fail

    Ensure proper coverage of powder coat throughout the entire frame 

    • Pass
    • Flag
    • Fail

    Ensure no visible scratches, chips, or dents

    • Pass
    • Flag
    • Fail

    Ensure welding is done smooth and strong 

    • Pass
    • Flag
    • Fail

    Ensure mounting holes are big enough and are free from powder-coat and protruding burrs

    • Pass
    • Flag
    • Fail

    Ensure all nuts and bolts are tight/torqued and there is no loose or missing hardware 

    • Pass
    • Flag
    • Fail

    Ensure proper orientation of CPU board and that all 4 plastic stand off pins are installed

    • Pass
    • Flag
    • Fail

    IN-PROCESS TESTING OF ACTUATOR BEFORE INSTALL

    • testingofactuators.jpg

    INSTALL COMPONENTS, CALIBRATE & TEST

    • KOTlatestinstallcalandtest.jpg

    ACCEPTANCE

    • NewKOTacceptance.jpg

    FINAL PARTS AND PRODUCTION CHECKLIST

    • KOTfinalparts.jpg

    Prep KOT Chair for Shipping

    if the answer is "oneOf [KOT chair included]"
    • KOTchair.jpg

    COMPONENT SERIAL NUMBERS

    6" Actuator

    Load Cell

    PCB Board

    MAC Address

    Power Supply

    Tablet

    FINAL SIGN-OFF

    Production Technician Signature

    Click here to sign

    Materials Supervisor

    Built in Inventory

    Click here to sign

    SHIPPING TECHNICIAN SECTION

    • shippingKOTedited.jpg

    PREP FOR SHIPPING

    Certificate of Conformity-Knee On Trac

    Serial Number

    • KneeOnTracCOLOR002anybackground.png

    Certificate of Conformity

    This certificate of conformity acknowledges that the KNEE ON TRAC equipment has passed all inspections and testing as required by ERGO-FLEX Technologies quality control management systems, which includes all parts and components.

    • conformitycontact.jpg
    • conformitysignature.jpg
    • shippingprep.jpg

    ACCOUNT ASSIGNMENT

    Assigned Doctor

    Doctors Email

    Attachments/Notes

    BOL signed copy from BTX

    Add or drag pictures

    Shipping Technician Signature

    Click here to sign
    if the answer is "oneOf [Service Fleet]"

    Service Fleet Knee On Trac Renewed Device Master Records

    PRODUCTION TECHNICIAN SECTION

    • KOTtractiononlyimage.jpg

    Notes

    Previous Owner: Previous Serial Number:

    FRAME INSPECTION

    Ensure all parts are included in traction box with unit; black barrel spacer with hardware, 2 wheels, 1" cushion plate, 2" cushion plate, and actuator spacer

    • Pass
    • Flag
    • Fail

    Ensure hand adjustment knob is installed and operates correctly

    • Pass
    • Flag
    • Fail

    Ensure both trays and frame are straight and evenly spaced

    • Pass
    • Flag
    • Fail

    Ensure both adjustment tray drawers slide in and out smoothly and effortlessly

    • Pass
    • Flag
    • Fail

    Ensure both trays are free of all debris 

    • Pass
    • Flag
    • Fail

    Ensure proper coverage of powder coat throughout the entire frame 

    • Pass
    • Flag
    • Fail

    Ensure no visible scratches, chips, or dents

    • Pass
    • Flag
    • Fail

    Ensure welding is done smooth and strong 

    • Pass
    • Flag
    • Fail

    Ensure mounting holes are big enough and are free from powder-coat and protruding burrs

    • Pass
    • Flag
    • Fail

    Ensure all nuts and bolts are tight/torqued and there is no loose or missing hardware 

    • Pass
    • Flag
    • Fail

    Ensure proper orientation of CPU board and that all 4 plastic stand off pins are installed

    • Pass
    • Flag
    • Fail

    IN-PROCESS TESTING OF ACTUATOR BEFORE INSTALL

    • testingofactuators.jpg

    INSTALL COMPONENTS, CALIBRATE & TEST

    • KOTlatestinstallcalandtest.jpg

    ACCEPTANCE

    • NewKOTacceptance.jpg

    FINAL PARTS AND PRODUCTION CHECKLIST

    • KOTfinalparts.jpg

    NEW COMPONENT SERIAL NUMBERS

    6" Actuator

    Load Cell

    PCB Board

    MAC Address

    Power Supply

    Tablet

    FINAL SIGN-OFF

    Production Technician Signature

    Click here to sign

    Materials Supervisor

    Built in Inventory

    Click here to sign

    SHIPPING TECHNICIAN SECTION

    • shippingKOTservicefleet.jpg

    PREP FOR SHIPPING

    Certificate of Conformity-Knee On Trac

    Serial Number

    • KneeOnTracCOLOR002anybackground.png

    Certificate of Conformity

    This certificate of conformity acknowledges that the KNEE ON TRAC equipment has passed all inspections and testing as required by ERGO-FLEX Technologies quality control management systems, which includes all parts and components.

    • conformitycontact.jpg
    • conformitysignature.jpg
    • Prepservicefleetforshipping.jpg

    ACCOUNT ASSIGNMENT

    Assigned Doctor

    Doctors Email

    Attachments/Notes

    BOL signed copy from BTX

    Add or drag pictures

    Shipping Technician Signature

    Click here to sign
Source: ErgoFlex (Community Member)

Please note that any procedure, checklist, or other document available in the MaintainX Procedure Hub is provided for general education and information only and does not constitute legal, medical, or financial advice. MaintainX makes the materials available AS IS and AS PROVIDED, without warranties of any kind. By downloading or using any such materials, you assume the risk that they may not be appropriate for your specific situation and agree that you are solely responsible for any such use, including compliance with applicable law and with meeting any conditions of product warranties.