Back

Pre-Lift Checklist for Suspended Personnel Platforms

Workplace Inspections identify hazardous conditions and apply hazard control measures, onmitor and evaluate the effectiveness of health and safety practices and procedures and improve health and safety practices and procedures.
MaintainX
07/26/2022

Pre-Lift Checklist for Suspended Personnel Platforms

22 steps
Workplace Inspections identify hazardous conditions and apply hazard control measures, onmitor and evaluate the effectiveness of health and safety practices and procedures and improve health and safety practices and procedures.
  • Project Name:

  • Project Location:

  • Crane Operator:

  • Date:

  • Crane Set Up

  • Crane has been leveled and outriggers fully deployed.

    • Pass
    • Flag
    • Fail
  • Total weight of the load does not exceed 50% of rated capacity of the crane.

    • Pass
    • Flag
    • Fail
  • Two means of controlling decent of platform are available to prevent free fall, brakes and another automatic means.

    • Pass
    • Flag
    • Fail
  • Variable angled booms have boom angle indicator.

    • Pass
    • Flag
    • Fail
  • Telescoping boom has boom length clearly indicated

    • Pass
    • Flag
    • Fail
  • Anti-two-blocking device prevents load block and boom tip contact

    • Pass
    • Flag
    • Fail
  • Load line has device that regulates the lowering rate of speed, prevents free fall.

    • Pass
    • Flag
    • Fail
  • When wire rope bridle/rigging is used it connects to a master link, not directly to the personnel platform

    • Pass
    • Flag
    • Fail
  • Hook on overhaul ball is closed and locked.

    • Pass
    • Flag
    • Fail
  • Trial Lift Proof Testing

  • Trial lift with the unoccupied personnel platform loaded to anticipated weight.

    • Pass
    • Flag
    • Fail
  • Platform lifted to each location at which the personnel platform is to be hoisted.

    • Pass
    • Flag
    • Fail
  • Hoist ropes are free of kinks and multiple part line is not twisted around each other.

    • Pass
    • Flag
    • Fail
  • No slack in load rope around drums.

    • Pass
    • Flag
    • Fail
  • Visual inspection of platform and crane after trial lift test looking for defects.

    • Pass
    • Flag
    • Fail
  • At each job site, platform tested to 125% of platform-rated capacity by holding it in a suspended position for five minutes, PRIOR to hoisting employees on the platform.

    • Pass
    • Flag
    • Fail
  • The crane operator, employees to be lifted and any other workers involved, must attend the meeting. It needs to be held prior to the Trial Lift and at each new work location for newly assigned employees or workers.

  • Attendance:

  • Signature:

    Click here to sign
  • Date:

Source: MaintainX (Community Member)

Please note that any procedure, checklist, or other document available in the MaintainX Global Procedure Library is provided for general education and information only and does not constitute legal, medical, or financial advice. MaintainX makes the materials available AS IS and AS PROVIDED, without warranties of any kind. By downloading or using any such materials, you assume the risk that they may not be appropriate for your specific situation and agree that you are solely responsible for any such use, including compliance with applicable law and with meeting any conditions of product warranties.