Dental School Vacuum System Pump LOTO Procedure: HVAC Auxiliaries

This procedure checklist to protect authorized employees against unexpected or unplanned activation of equipment or energy while servicing equipment.
MaintainX
07/26/2022

Dental School Vacuum System Pump LOTO Procedure: HVAC Auxiliaries

22 steps
This procedure checklist to protect authorized employees against unexpected or unplanned activation of equipment or energy while servicing equipment.
  • 1.png
  • ENERGY SOURCES

  • Energy Source (Magnitude):

  • Energy Isolation Point or Control Step:

  • Application Method and LOTO Device

  • Step #

  • 2.png
  • Energy Source (Magnitude)

  • Energy Isolation Point or Control Step

  • Application Method and LOTO Device

  • Step #

  • 3.png
  • LOCKOUT TAGOUT SEQUENCE

  • Notify Employees

  • Notify affected employees of LOTO activity

  • Equipment Shutdown

  • Shut down cold room by normal stopping procedure.

    4.png
  • Isolate Energy

  • Lockout Energy

  • Dissipate Energy

  • Verify Isolation

  • Perform work

  • RESTORE EQUIPMENT TO SERVICE SEQUENCE

  • Clear Work Area

  • Verify Controls

  • Remove Lockout

  • Notify Employees

Source: MaintainX (Community Member)

Please note that any procedure, checklist, or other document available in the MaintainX Global Procedure Library is provided for general education and information only and does not constitute legal, medical, or financial advice. MaintainX makes the materials available AS IS and AS PROVIDED, without warranties of any kind. By downloading or using any such materials, you assume the risk that they may not be appropriate for your specific situation and agree that you are solely responsible for any such use, including compliance with applicable law and with meeting any conditions of product warranties.