Dewatering Screen

-6 Month/Periodic PM Inspection is for when performing a screen change a more thorough inspection for wear, fatigue and rust should be conducted on stringers, beams, rubber linings & side plates
2 MX Main Demo
04/04/2022

Dewatering Screen

9 steps
-6 Month/Periodic PM Inspection is for when performing a screen change a more thorough inspection for wear, fatigue and rust should be conducted on stringers, beams, rubber linings & side plates
  • CCM -COMPETENCE CENTER MATERIALS

  • Unique Identification Number

    ScreenShot2022-03-30at2.04.33PM.png
  • 6 Month Running Inspection --Expected Time (10 minutes)

  • Performance

  • SCHEDULE / PLAN - Investigate and rectify

  • SCHEDULE / PLAN - Preventative Maintenance

  • Periodic inspection -- Expected Time (10 minutes)

  • Screen Media

  • When performing a screen change a more thorough inspection for wear, fatigue and rust should be conducted on stringers, beams, rubber linings & side plates

  • SCHEDULE / PLAN - Preventative Maintenance Depending on severity

  • Overall Comments

  • Tech comments and recommendations / photos as needed

Source: 2 MX Main Demo (Community Member)

Please note that any procedure, checklist, or other document available in the MaintainX Global Procedure Library is provided for general education and information only and does not constitute legal, medical, or financial advice. MaintainX makes the materials available AS IS and AS PROVIDED, without warranties of any kind. By downloading or using any such materials, you assume the risk that they may not be appropriate for your specific situation and agree that you are solely responsible for any such use, including compliance with applicable law and with meeting any conditions of product warranties.