Back

EMTOS Quarterly Preventative Maintenance Report

This report documents the quarterly preventive maintenance performed on EMTOS equipment, including inspections, servicing, and identified issues, to support reliable operation and timely corrective action.
Envent Corporation
09/30/2026

EMTOS Quarterly Preventative Maintenance Report

This quarterly preventative maintenance shall be performed to ensure the equipment operates reliably and safely between annual inspections. Inspectors should check all critical systems, verify proper operation of controls and safety devices, clean accessible components, inspect for wear damage, and document any issues for corrective action.
Procedure Max Score: 187

    EMTOS Quarterly PM

    Unit #

    Date

    License Plate #

    Inspectors

    Unit Hours Start

    Meter name
    Unit

    Air Compressor Hours Start

    Gas Meter Start

    Is the car seal installed and intact on the main panel, with no signs of tampering or unauthorized entry?

    • Pass
    • Flag
    • Fail
    if the answer is "noneOf [PASS]"

    Check that the SO cord is connected and snug inside of the panel before energizing power to the unit.

    if the answer is "noneOf [PASS]"

    Check for any loose wires or disconnected wires. Reinstall and tighten to spec.

    No Power on Unit: Generator disconnected

    Trailer

    Inspect Trailer Kingpin

    Check for visible cracks, deep gouges, or severe condition

    • Pass
    • Flag
    • Fail
    if the answer is "oneOf [FAIL]"

    Inspect upper coupler plate for warping, bowing, or thin spots

    • Pass
    • Flag
    • Fail
    if the answer is "oneOf [FAIL]"

    Inspect welds connecting kingpin to trailer for signs of weld failure or cracking

    • Pass
    • Flag
    • Fail
    if the answer is "oneOf [FAIL]"

    Upload photo of kingpin upon completion of passed inspection.

    Add or drag pictures

    Inspect trailer tires and lights

    Check tires for proper inflation and dry rotting or damage.

    • Pass
    • Flag
    • Fail

    Inspect all lights for proper operation (running lights, turn signals, brake lights).

    • Pass
    • Flag
    • Fail

    Pull break away wire and verify the trailer breaks work by driving truck forward.

    • Pass
    • Flag
    • Fail

    Inspect trailer support

    Inspect leg stands and grease Zerk fittings.

    • Pass
    • Flag
    • Fail

    Check firebox to trailer bolts and holes for integrity.

    • Pass
    • Flag
    • Fail

    Vaporizer

    Check vaporizer thermocouple and make sure connections are secure (recrimp if necessary).

    • Pass
    • Flag
    • Fail

    Check controller to ensure the knob can be fully turned into all positions.

    • Pass
    • Flag
    • Fail

    Check silicone integrity around pilot ignitor transformer.

    • Pass
    • Flag
    • Fail

    Open inlet Y strainer to check for propane butter. Depressurize line before breaking.

    • Pass
    • Flag
    • Fail

    Remove 6-screw top cover to inspect refractory and doughnut gasket. Verify gasket is seated properly and clear of tank spacing.

    • Pass
    • Flag
    • Fail

    Main Electrical Panel

    Tighten every wire termination to 1.2 Nm torque.

    • Pass
    • Flag
    • Fail

    Remove BMS and check terminations.

    • Pass
    • Flag
    • Fail

    Check for open holes.

    • Pass
    • Flag
    • Fail

    Signs of rust or water.

    • Pass
    • Flag
    • Fail

    Inspect panel door gasket & conduit opening integrity.

    • Pass
    • Flag
    • Fail

    Add desiccant packs if missing or replace if saturated.

    • Pass
    • Flag
    • Fail

    Inspect wire condition (no wire rubbing against sharp edges).

    • Pass
    • Flag
    • Fail

    Ensure spiral wire wrap is placed correctly to protect wires.

    • Pass
    • Flag
    • Fail

    Ensure wire tie downs are operational, replace if necessary.

    • Pass
    • Flag
    • Fail

    Ignitor Panel

    Tighten every wire termination to 1.2 Nm torque

    • Pass
    • Flag
    • Fail

    Check for open holes in each panel.

    • Pass
    • Flag
    • Fail

    Signs of rust or water.

    • Pass
    • Flag
    • Fail

    Inspect panel door gasket & conduit opening integrity.

    • Pass
    • Flag
    • Fail

    Add desiccant packs if missing or replace if saturated.

    • Pass
    • Flag
    • Fail

    Inspect wire condition (no wire rubbing against sharp edges)

    • Pass
    • Flag
    • Fail

    Ensure spiral wire wrap is placed correctly to protect wires.

    • Pass
    • Flag
    • Fail

    Ensure wire tiedowns are operational, replace if necessary.

    • Pass
    • Flag
    • Fail

    Electrical Panels (Open all Panels and Perform the following Tasks)

    Tighten every wire termination to 1.2 Nm torque (10.6 lb-in)

    • Pass
    • Flag
    • Fail

    Remove BMS and check terminations.

    • Pass
    • Flag
    • Fail

    Check for open holes in each panel.

    • Pass
    • Flag
    • Fail

    Signs of rust or water.

    • Pass
    • Flag
    • Fail

    Inspect panel door gasket & conduit opening integrity.

    • Pass
    • Flag
    • Fail

    Add desiccant packs if missing or replace if saturated.

    • Pass
    • Flag
    • Fail

    Inspect wire condition (no wire rubbing against sharp edges)

    • Pass
    • Flag
    • Fail

    Ensure spiral wire wrap is placed correctly to protect wires.

    • Pass
    • Flag
    • Fail

    Ensure wire tiedowns are operational, replace if necessary.

    • Pass
    • Flag
    • Fail

    Chart Recorder

    Verify plug connections and wires are tight for power, thermocouples input 1 & 2, alarm outputs, output control and ground terminals.

    • Pass
    • Flag
    • Fail

    Visually verify all ribbon cables are landed securely.

    • Pass
    • Flag
    • Fail

    Verify input cards are seated correctly and free or corrosion or damage.

    • Pass
    • Flag
    • Fail

    Rotary Gas Meter (Totalizer)

    Drain oil in all three chambers and refill (left, right, and center).

    • Pass
    • Flag
    • Fail

    Inspect and replace screen paper gasket on the inlet side and regular paper gasket on the outlet side.

    • Pass
    • Flag
    • Fail

    Flow Tubes

    Remove all DS-300/400 and blow out with shop air, inspect, and reinsert or replace.

    • Pass
    • Flag
    • Fail

    Firebox

    Remove manway door and inspect refractory on floor, roof, walls, process inlet, and burner.

    • Pass
    • Flag
    • Fail

    Burner

    Inspect burner damper and linkage assembly (wiggle linkage).

    • Pass
    • Flag
    • Fail

    Clean burner site glasses.

    • Pass
    • Flag
    • Fail

    Combustion Blower

    Visually inspect all blower mounting bolts for rust and tightness.

    • Pass
    • Flag
    • Fail

    Maxon or Eclipse Valves (SSOV 1&2)

    Inspect all valve covers and gaskets are in place and tight. If gasket integrity is compromised replace gasket.

    • Pass
    • Flag
    • Fail

    Inspect landed wires on the valve terminal block are in good condition.

    • Pass
    • Flag
    • Fail

    Ensure that all connections are tight and wiring is not frayed.

    • Pass
    • Flag
    • Fail

    Open side cover plate and verify that no water, debris, or foreign mater. If there are signs of water intrusion, get with engineering to inspect further and give path forward on repairs.

    • Pass
    • Flag
    • Fail

    Manual Butterfly Valves

    4" Process Valve: Open gear assembly and grease gears.

    • Pass
    • Flag
    • Fail

    Main Process Valve: Open gear assembly and grease gears.

    • Pass
    • Flag
    • Fail

    Dilution Valve: Open gear assembly and grease gears.

    • Pass
    • Flag
    • Fail

    Automatic Process Isolation Valve

    Visually inspect mounting hardware and support brackets for signs of stress or wear.

    • Pass
    • Flag
    • Fail

    Process Blower

    NYB Blower Alignment Checks

    This procedure outlines the steps for performing quarterly alignment checks on NYB Blowers, ensuring all components are properly aligned and the area is safe and clean post-inspection.

    Pre-Inspection Setup

    Alignment Inspection

    Measure Blower Housing Centering at Pillow Blocks

    Using a tape measure, measure the distance from the outside edge of each pillow block bearing housing to the edge of the blower housing at all four measurement points (top, bottom, left, and right, or as applicable to the equipment configuration). Record each measurement and compare the values to verify the blower rotor and shaft assembly are centered within the housing.

    When taking measurements:

    if the answer is "oneOf [Record all measurements to the nearest 1/16 inch (or applicable site standard).]"

    Record Measurements:

    Is the alignment within the acceptable range?

    • Yes
    • No
    • N / A

    Post-Inspection Tasks

    Reinstall the Shaft cover.

    • Yes
    • No
    • N / A

    Was the area cleaned after inspection?

    • Yes
    • No
    • N / A

    NYB Blower Bearing Lubrication

    This procedure outlines the steps for purging the bearings of an NYB blower, including inspection, cleaning, lubrication, and testing.

    Preparation

    Inspection and Cleaning

    Inspect bearings and bushing

    • Pass
    • Flag
    • Fail

    Lubrication

    Remove the tubing from the grease injection points on each bearing to allow direct access to the grease fittings and to verify that grease can flow freely into the bearing. Inspect the tubing, fittings, and connectors for restrictions, hardened grease, contamination, damage, or blockages that could prevent proper lubrication.

    • Pass
    • Flag
    • Fail
    if the answer is "noneOf [PASS]"

    If any tubing is damaged, kinked, or plugged, replace it before returning the system to service.

    This ensures hardened, contaminated, incompatible, or degraded grease is removed from the lubrication path and that the tubing is completely charged with fresh grease.

    Visually inspect the discharged grease for signs of contamination, moisture, dirt, discoloration, or metal particles that could indicate lubrication or bearing issues.

    • Pass
    • Flag
    • Fail

    Greasing a stationary bearing can rapidly build internal pressure, forcing grease against the seals and potentially causing seal damage or seal blowout. Excessive pressure can also lead to overheating, premature bearing failure, and reduced lubricant effectiveness. If shaft rotation cannot be achieved, stop the lubrication activity and consult maintenance supervision before proceeding

    This also helps prevent contamination from being drawn back into the bearing.

    The appearance of fresh grease confirms that old grease has been displaced and the bearing cavity has been replenished.

    Vapor Seal Lubrication

    The vapor seal lubrication point and the bearing grease fitting are separate components. Do not introduce anti-seize into the bearing grease fittings, grease lines, or bearing housing. Anti-seize contamination will damage the bearing lubricant, accelerate wear, and can lead to premature bearing failure. Bearings shall only be lubricated with Mobilgrease XHP 222 (Blue) grease.

    The vapor seal is located between the bearing housing and the blower casing where the shaft enters the the housing. Its purpose is to prevent process vapors from migrating along the shaft and reaching the bearing assembly. The fitting closest to the fan housing is typically the vapor seal lubrication point. The fitting located on the bearing housing is the bearing grease fitting. Always verify fitting locations before adding any lubricant. Verify the correct lubrication point before applying lubricant.

    Shaft Cover Install

    Prior to reattaching the blower cover, inspect all mating surfaces, gaskets, O-rings, and sealing areas for damage, debris, corrosion, or residual gasket material. Clean the sealing surfaces as necessary to ensure a proper seal and prevent air leakage. Replace any damaged gaskets, O-rings, or sealing components before reassembly. Carefully position the blower cover onto the housing, ensuring it is properly aligned with the locating features and does not contact the rotor, shaft, or internal components during installation. Install all mounting hardware finger-tight initially to ensure the cover seats evenly against the housing. Tighten mounting bolts in a crisscross or star pattern to evenly distribute clamping force and prevent cover distortion. Torque all fasteners to the manufacturer's specification where applicable. Verify that no tools, rags, hardware, or foreign material remain inside the blower housing prior to fully securing the cover.

    After the cover is installed:

    Testing

    Turn on the blower, let it run for 15 minutes, and take temperature of bearings. Bearing Temp should not exceed 200F in Ambient conditions.

    • Pass
    • Flag
    • Fail

    Does the blower make unusual screeching sounds after the first 5 seconds of startup?

    • Yes
    • No
    • N / A
    if the answer is "oneOf [Yes]"

    Check the belt Tension.

    Power on Unit: Connect Generator and Propane

    Air Compressor

    Ensure a 0-150 PSI Pressure Guage is installed before the regulator.

    • Pass
    • Flag
    • Fail

    Verify the compressor stops at ~135 PSIG in the main tank.

    • Pass
    • Flag
    • Fail

    Panel Light Check

    Activate each button and switch to confirm it lights up when turned on.

    • Pass
    • Flag
    • Fail

    Area Lights

    Inspect all area lights by turning them on, replace bulbs as needed, and check for rust or water damage.

    • Pass
    • Flag
    • Fail

    Chart Recorder

    Verify the display powers up with no error codes or flickering.

    • Pass
    • Flag
    • Fail

    Pen & Paper Operation: Correct date and time stamp, legible temperature recordings.

    • Pass
    • Flag
    • Fail

    Temperature Accuracy: Compare temperature reading with High Limit Controller and verify readings are within 50F of each other.

    • Pass
    • Flag
    • Fail
    if the answer is "noneOf [PASS]"

    Follow the Maintenance SOP Calibration and Thermocouple Replacement. Add a note if Thermocouple was replaced or Calibrated.

    Output Control: Test output control by placing in manual and driving the mod motor with the arrow keys.

    • Pass
    • Flag
    • Fail

    Alarm Outputs: At 1400F, verify the top green panel light turns on, and the Process Isolation Valve opens.

    • Pass
    • Flag
    • Fail

    Alarm Outputs: At 1550F, verify the top red panel light turns on. If temperature cannot be raised above 1550F, adjust Alarm setpoints A2S1 and A2S2 below current temperature to simulate.

    • Pass
    • Flag
    • Fail

    Process Isolation Valve

    Raise unit above 1400°F and verify valve fully opens and closes promptly. If the valve takes more than 30 seconds to close, replace the air dump valve.

    • Pass
    • Flag
    • Fail

    Rotary Gas Meter

    Check Pressure gauges on rotary meter and read out gauges. Check differential pressure between gauge (In./H20) behind of main gas (pancake) regulator and first gauge on gas meter is less than 10" wc. If greater, change gasket screen on Totalizer.

    • Pass
    • Flag
    • Fail

    Drain moisture in airline to actuator and verify actuator opens valve once temperature is above 1400F

    • Pass
    • Flag
    • Fail

    Process Valve

    Check integrity of 4" process bypass valve and 10" process valve by bringing unit above 1400F with both valves closed and verify no suction at inlet

    • Pass
    • Flag
    • Fail

    Burner

    Verify that the modulating actuator moves to high during the 90 second high fire purge and moves to low when the BMS says to start.

    • Pass
    • Flag
    • Fail

    Firebox

    Scan the entire exterior firebox wall with a temperature gun and record any areas exceeding 200°F.

    • Pass
    • Flag
    • Fail

    Check bearing temperatures on Process Blower. Normal bearing housing temperature (temp-gun reading) should be stable and typically < 180°F (82°C). Investigate if temperature increases from the unit’s normal baseline, if one side is significantly hotter than the other, or if readings exceed ~180°F; treat ~200°F (93°C) as a do-not-run/notify supervision. Plan to replace bearings. Flag this inspection as fail.

    • Pass
    • Flag
    • Fail

    Interlock Testing

    Check all Interlocks on unit

    High Limit Temperature

    While BMS is going into purge, change the set point below the chart recorder temperature and verify a "stoppage" in BMS activity

    • Pass
    • Flag
    • Fail

    While unit is running, lower high temperature set point below chart recorder temperature and verify burner shut down.

    • Pass
    • Flag
    • Fail

    UV Scanner

    While unit is running, remove UV scanner from unit. Do not expose to direct sunlight. Cover optical lens and ensure that the unit shuts down.

    • Pass
    • Flag
    • Fail

    LEL Analyzer

    Calibrate LEL in accordance with the procedures, verify analyzer is not bypassed by valves or by jumped wires behind LEL controller.

    • Pass
    • Flag
    • Fail

    Test high LEL shutdown by lowering the setpoint to 0%. (Add a bias if current reading is 0%) Verify the unit shuts down. Remove any added bias.

    • Pass
    • Flag
    • Fail

    Process Blower Pressure Switch

    Open cover of pressure switch and verify that sensor is not jumped. Remove tubing from sensor and verify that interlock is tripped on BMS.

    • Pass
    • Flag
    • Fail

    Verify on the pressure switch box that one wire is on common and one wire is on Normally Open.

    • Pass
    • Flag
    • Fail

    Combustion Blower Pressure Switch

    Open cover of pressure switch and verify that sensor is not jumped. Remove tubing from sensor and verify that interlock is tripped on BMS.

    • Pass
    • Flag
    • Fail

    Verify on the pressure switch box that one wire is on common and one wire is on Normally Open.

    • Pass
    • Flag
    • Fail

    FA Temperature Switch

    Remove temperature switch. Wrap heating element around probe, set temperature to 410°F. Verify contacts open with ohms meter at 400°F. (Different from Test Fire)

    • Pass
    • Flag
    • Fail

    Rotary Gas Meter

    Drain oil in all three chambers and refill (left, right, and center).

    • Pass
    • Flag
    • Fail

    Inspect and replace screen paper gasket on the inlet side and regular paper gasket on the outlet side.

    • Pass
    • Flag
    • Fail

    Firebox, Main Panel, and Sapre Parts

    Remove manway door and inspect refractory on floor, roof, walls, process inlet, and burner.

    • Pass
    • Flag
    • Fail

    Scan the entire exterior firebox wall with a temperature gun and record any areas exceeding 200°F.

    • Pass
    • Flag
    • Fail

    Verify that the modulating actuator moves to high during the 90 second high fire purge and moves to low when the BMS says to start

    • Pass
    • Flag
    • Fail

    Verify Carseal is installed on Main Panel.

    • Pass
    • Flag
    • Fail

    Take a picture and attach of the following in the comments of the work order.

    PM Lead Closure Signature

    PM Lead Sign Off

    Quality Check Approval Signature (Shop Personnel)

    Quality Check Sign Off (Shop Personnel)

    Click here to sign
Source: Envent Corporation (Community Member)

Please note that any procedure, checklist, or other document available in the MaintainX Procedure Hub is provided for general education and information only and does not constitute legal, medical, or financial advice. MaintainX makes the materials available AS IS and AS PROVIDED, without warranties of any kind. By downloading or using any such materials, you assume the risk that they may not be appropriate for your specific situation and agree that you are solely responsible for any such use, including compliance with applicable law and with meeting any conditions of product warranties.