Differential Pressure Flush

Perform quarterly flushing of all differential pressure sensors associated with the chilled-water and condenser-water systems. This task ensures pressure sensing lines remain clear of debris, sediment, or air pockets that could affect accuracy. Work includes isolating affected circuits if required, connecting flush hoses, running clean water until flow is clear, verifying stable ΔP readings, and restoring valves to normal position.
Norfolk Southern - Tucker Data Center
11/05/2025

Differential Pressure Flush

Perform quarterly flushing of all differential pressure sensors associated with the chilled-water and condenser-water systems. This task ensures pressure sensing lines remain clear of debris, sediment, or air pockets that could affect accuracy. Work includes isolating affected circuits if required, connecting flush hoses, running clean water until flow is clear, verifying stable ΔP readings, and restoring valves to normal position.
Procedure Max Score: 0

    Verify Job Plan and Equipment Data Complete and Accurate and Report Errors to Lead or Supervisor

    Apply All CBRE Work Safety Policies and Procedures for Work Performed

    Pre -flush

    Identify and Prepare Sensor

    Flush Sequence

    Post-Work

Source: Norfolk Southern - Tucker Data Center (Community Member)

Please note that any procedure, checklist, or other document available in the MaintainX Procedure Hub is provided for general education and information only and does not constitute legal, medical, or financial advice. MaintainX makes the materials available AS IS and AS PROVIDED, without warranties of any kind. By downloading or using any such materials, you assume the risk that they may not be appropriate for your specific situation and agree that you are solely responsible for any such use, including compliance with applicable law and with meeting any conditions of product warranties.