Positive Displacement Pumps (PD Pump) Inspection
This procedure is used to inspect and service positive displacement pumps so wear, damage, and buildup are found before they cause a pump failure.
Positive Displacement Pumps (PD Pump) Inspection
This procedure outlines the inspection of positive displacement (PD) pumps to keep them operating reliably. After notifying operations and applying lockout/tagout, it guides the technician through inspecting the couplings, guards, mounting fasteners, shaft play, gearbox oil, shaft seal, pump head internals (bull gear, idler gear, check valve), motor conduit, motor buildup, and cooling fan, followed by cleanup and sign-off.
Some pumps may have only one coupling. Others may have two.
Remove coupling and inspect components of coupling
Falk grid couplings - should have two halves of grid and no wear on grid or hub wear grid rides. Omega Couplings - Any dry rot, cracking, or rubber peeling from metal will require replacement
Ensure hubs are tight to shaft and keyways are not loose.
Is guarding OK?
Check all mounting fasteners on pump, motor, and gearbox if applicable
Inspect Motor, gearbox, and pump for shaft play.
ISO 220 Oil
Seal OK on pump shaft?
TAKE NOTE OF ORIENTATION OF CHECK VALVE PRIOR TO REMOVAL
Inspect bull gear for wear. OK?
Inspect idle gear for wear? OK?
Both the gear side and play on shaft need inspected.
Inspect inside of check valve for build ups and blockage. remove if present
Inspect flex conduit going to motor is it OK?
Inspect motor for build up. Remove any build up
Cooling fan OK?
Sign after completion of work
Click here to sign
Source: Goodland Crush - Scoular (Community Member)