Reclaim Line 050 Weekly Preventive Maintenance
This procedure focuses on cleaning, inspecting, and servicing the reclaim system line 050 to maintain optimal performance and efficiency. Tasks typically include checking for leaks, clearing blockages, inspecting hoses and fittings, and verifying sensor and pump operation. Regular weekly PM helps minimize downtime, ensure material flow, and extend equipment lifespan.
Reclaim Line 050 Weekly Preventive Maintenance
This procedure focuses on cleaning, inspecting, and servicing the reclaim system line 050 to maintain optimal performance and efficiency. Tasks typically include checking for leaks, clearing blockages, inspecting hoses and fittings, and verifying sensor and pump operation. Regular weekly PM helps minimize downtime, ensure material flow, and extend equipment lifespan.
LOCKOUT/TAGOUT PROCEDURES MUST BE FOLLOWED AT ALL TIMES
APPROPRIATE PPE MUST BE WORN AT ALL TIMES
CHECK HYDRAULIC OIL LEVEL IN RESERVOIR, FILL AS REQUIRED
VERIFY PROPER OPERATION OF SCREEN CHANGERS - NO LEAKS
CHECK FOR ANY OIL LEAKS AROUND LINE
CHECK ROLL FEED GEARBOX OIL LEVEL, FILL AS REQUIRED
CHECK ROLL FEED BEARINGS AND ROLLERS FOR WEAR, GREASE, REPAIR AS REQUIRED
CHECK EXTRUDER BEARING STACK (PIG) OIL LEVEL, FILL AS REQUIRED
DRAIN AIR-WATER TRAPS. IF APPLICABLE
CHECK WATER SUPPLY FILTERS, IF APPLICABLE, CHANGE AS NEEDED
INSURE WATER LEVEL ON COOLING TROUGH IS CORRECT
CHECK FOR ANY WATER LEAKS AROUND THE LINE, REPAIR AS REQUIRED OR CREATE WORK ORDER FOR REPAIR.
CHECK HEATERS FOR DAMAGE, PROPER TEMPERATURES, REPAIR AS REQUIRED OR CREATE WORK ORDER FOR REPAIR.
VERIFY PELLETIZER IS PRODUCING CORRECT SIZE RESIN PELLETS,, REPAIR AS REQUIRED OR CREATE WORK ORDER FOR REPAIR.
VISUALLY CHECK CUTTER COMPACTOR BELTS FOR TIGHTNESS OR MISSING BELTS, REPLACE AS REQUIRED
VERIFY CAN WATER FLOW, SHAKER TABLE AND SPIN DRYER ARE WORKING PROPERLY, REPAIR AS REQUIRED OR CREATE WORK ORDER FOR REPAIR
CHECK RESIN BLOWER, HOPPER FOR OPERATION, LEAKS, REPAIR AS REQUIRED
ASK OPERATORS IF THEY ARE HAVING ISSUES WITH THE LINE, ENTER A WORK ORDER FOR WORK DONE OR IF MORE WORK IS NECESSARY AND NEEDS TO BE SCHEDULED
COMMENTS
Source: Amcor - PRY (Community Member)