Preparation and Notification
Identify sources of energy and Air pressure in relation to the maintenance task
Notify all machine operators about the lockout
Lock Out Procedure
Wait for electricity to discharge (in minutes)
Wait 5 minutes for electricity to discharge.
Verification
Verify the machine will not start up with an e-stop pressed
Verify the machine HMI will not power on with the power switch in the off position
Returning Machine to Service
Main panel visual inspection
Safety Gate function test
Wrap arm and roller carriage visual
Air valve visual inspection
Roller Carriage Visual inspection
Roller Carriage drive and bearings
Lantech pallet conveyors