Bioquell Qube Sleeve Change Procedure
This procedure outlines the steps for safely replacing sleeves on Bioquell Qube isolators to maintain contamination control and ensure readiness for production use.
Bioquell Qube Sleeve Change Procedure
This procedure should be followed when changing a sleeve on the Bioquell Qube isolators.
Production to Engineering Handover
Must be completed before carrying out any activity within the production environment
Sleeve change date & time
Name of Manager or Supervisor handing isolator over?
Fitting a new sleeve
Engineering to Production Handover
Must be completed before handing back the isolator to production and leaving the area.
Handover date and time
Name of Manager or Supervisor accepting isolator back into production?
Source: Target Healthcare (Community Member)