WW PM Monthly EQ Tank T-1 Tec Tank

The Annual PM according to the Steel Tank Institute / Steel Plate Fabricators Association (STI/SPFA) for the EQ tank manufactured by Tec Tank. Monthly PM of an EQ tank ensures optimal performance, extends equipment lifespan, prevents costly breakdowns, and maintains water quality by addressing potential issues proactively.
087
04/30/2025

WW PM Monthly EQ Tank T-1 Tec Tank

The Annual PM according to the Steel Tank Institute / Steel Plate Fabricators Association (STI/SPFA) for the EQ tank manufactured by Tec Tank. Monthly PM of an EQ tank ensures optimal performance, extends equipment lifespan, prevents costly breakdowns, and maintains water quality by addressing potential issues proactively.

    Food Safety Pre-Check

    Inspect the access ladder and fall arrest cable for security, corrosion, and damage. If Flag or Fail, upload photo and explain in notes. Open a corrective work order. DO NOT use the caged access ladder with harness until repairs are complete.

    • Pass
    • Flag
    • Fail
    if the answer is "oneOf [FLAG,FAIL]"

    Fault found. Open a corrective work order. DO NOT use the caged access ladder with harness until repairs are complete.

    Inspect the tank exterior for visible leaks. Including the roof, shell, heads, bottom, connections, fittings, and valves. Including air lines and meter from the blower to the tank inlet. Including water lines from the roof to the tank. Including water lines from the tank to the pumps. If Flag or Fail, upload photo and explain in notes. Open a corrective work order.

    • Pass
    • Flag
    • Fail
    if the answer is "oneOf [FLAG,FAIL]"

    Inspect the concrete and bollards around the tank for visible signs of leakage, dirt, vegetation, or foreign material. If Flag or Fail, upload photo and explain in notes. Open a corrective work order.

    • Pass
    • Flag
    • Fail
    if the answer is "oneOf [FLAG,FAIL]"

    Inspect and test the tank level transmitter for power, communication, and overfill alarm. If Flag or Fail, upload photo and explain in notes. Open a corrective work order.

    • Pass
    • Flag
    • Fail
    if the answer is "oneOf [FLAG,FAIL]"

    Inspect the tank overfill plumbing for visible leaks and cracks in connections and fittings. If Flag or Fail, upload photo and explain in notes. Open a corrective work order.

    • Pass
    • Flag
    • Fail
    if the answer is "oneOf [FLAG,FAIL]"

    Food Safety Post-Check

Source: 087 (Community Member)

Please note that any procedure, checklist, or other document available in the MaintainX Procedure Hub is provided for general education and information only and does not constitute legal, medical, or financial advice. MaintainX makes the materials available AS IS and AS PROVIDED, without warranties of any kind. By downloading or using any such materials, you assume the risk that they may not be appropriate for your specific situation and agree that you are solely responsible for any such use, including compliance with applicable law and with meeting any conditions of product warranties.