Back

EMECS Test Fire Checklist

Completing this checklist during every test fire confirms the EMECS unit is safe, compliant and ready for field service.
Envent Corporation
10/02/2026

EMECS Test Fire Checklist

This procedure guides technicians through a full test fire of an EMECS unit, starting with pre-start checks of the panel seal, fire extinguishers, trailer paperwork, grounding and the generator. It then covers starting the blowers, vaporizer and EMECS unit, running integrity, torque, operational and interlock checks, shutting down safely, and completing a final walkaround with inspector and supervisor sign-off.

    Inspector/s Name:

    Supervisors Name:

    EMECS Unit#

    Date of Test Fire:

    Is the car seal installed and intact on the main panel, with no signs of tampering or unauthorized entry?

    • Pass
    • Flag
    • Fail
    if the answer is "noneOf [PASS]"

    Check that the SO cord is connected and snug inside of the panel before energizing power to the unit.

    Check for any loose wires or disconnected wires. Reinstall and tighten to spec.

    Verify that the two fire extinguishers on the unit are ready to use, not damaged, the seal is intact, the UL tag in place, and they are up to date on their annual inspection. Replace if needed.

    • Pass
    • Flag
    • Fail

    Fire Extinguisher (2/unit) Visual Inspection (Seal, UL, Damage)

    Inspection Date Tag 1:

    Inspection Date Tag 2:

    Conduct the following Trailer Checks and Write the expiration Date. Ensure all paper work is returned to trailer bubble.

    Federal Inspection (Annual)

    • Pass
    • Flag
    • Fail

    Federal Inspection (Annual) Expiration Date

    State Inspection (BIT)

    Registration

    • Pass
    • Flag
    • Fail

    Registration Expiration Date

    Check Grounding and Bonding (10 OHMS or under)

    Unit

    • Pass
    • Flag
    • Fail

    Propane

    • Pass
    • Flag
    • Fail

    Generator

    • Pass
    • Flag
    • Fail

    Generator

    Is the Oil change overdue?

    • Yes
    • No
    • N / A
    if the answer is "oneOf [Yes]"

    Red Tag the Generator. Notify the Shop Manager. Put in a WO Request in MaintainX.

    Generator Hours:

    Meter name
    Unit

    Is the oil level and the coolant level good?

    • Yes
    • No
    • N / A
    if the answer is "oneOf [No]"

    If levels are low fill reservoirs before starting up the generator.

    Check spill containment and drain any liquid.

    • Yes
    • No
    • N / A

    Inspect for any Fuel/Oil/Coolant leaks.

    • Pass
    • Flag
    • Fail
    if the answer is "noneOf [PASS]"

    If leaks are found, red tag the generator, inform the shop manager or supervisor, and put in a WO request in MaintainX to address the leak.

    Generator #

    Check that the SO cord is connected and snug inside of the panel before energizing power to the unit.

    • Pass
    • Flag
    • Fail

    Generator Startup

    Are there any Active Alarms on the Generator?

    • Yes
    • No
    • N / A
    if the answer is "oneOf [Yes]"

    Red Tag the Generator. Notify Shop Manager. Put in a WO Request in MaintainX.

    Capsuhelics and Magnehelics

    Check All and Re-zero or replace if necessary

    • Pass
    • Flag
    • Fail

    VFD's and Power Breaker Switches

    Open Panel (No Power On) Check SO Cord for damage. Verify SO Cord connection is tight to breaker in panel before turning on Generator. Verify Generator is connected correctly. Check for any other issues.

    • Pass
    • Flag
    • Fail

    Process Blower and VFD Panel

    Motor Rotation

    Process Blower

    Observe rotation of Process Blower

    • Pass
    • Flag
    • Fail

    Combustion Blower

    Observe Rotation of Combustion Motor or Blower

    • Pass
    • Flag
    • Fail

    Vaporizer Startup

    Safety: LP gas is extremely flammable. Monitor continuously with a PID/4-gas meter and route relief vents at least 25 ft away from personnel and ignition sources.

    Clear the area and check for leaks – remove all combustibles from the vaporizer area and run a PID/4-gas scan of the cabinet, fuel train, and regulators.

    • Pass
    • Flag
    • Fail

    Both Blowers must be on before the following steps can be performed:

    EMECS Startup

    TOTAL EMECS Unit Hours (Do not put the hours ran during the Test Fire)

    Meter name
    Unit

    Once at Set Point Check all Parameters

    • Pass
    • Flag
    • Fail

    EMECS Integrity Checks

    Above 400F Degrees

    Process Isolation Integrity Test: While Temperature is Below 400F, Open Manual Process valve and Verify No Inlet Vacuum

    • Pass
    • Flag
    • Fail

    Manual Process Valve Integrity Test: While Temp is above 400F, Verify process Valve Opens. Then Verify No Vacuum While in Manual Process Valve is Closed.

    • Pass
    • Flag
    • Fail

    High Temperature Limit Controller: Lower setpoint below operating Temperature and Observe if the Unit Shuts Down.

    • Pass
    • Flag
    • Fail
    if the answer is "oneOf [FAIL,FLAG]"

    Determine Why? Move the Setpoint Back to 2000F and Press Reset Twice.

    DA/FA Torque Check: Check Torque Values on All FA'S and DA'S.

    Verify Torque Values on FA and DA according to the photos below. Record your Torque Pattern and Torque Value's for each pass Below. If you do not Torque properly there is a likely chance of a leak developing. Do NOT bypass this step.

    • ToqueValues.png
    • DAFATorquePattern.png
    • TorquePatternValue.png

    EMECS Operational Checks

    When the Unit is at Set Point Check the Following

    Pressure Gauge Upstream of MAR90 (PSIG)

    Pressure Gauge Downstream MAR90 (PSIG)

    Inlet Flow (Unit Maxed Out)

    Total Flow (Unit Maxed Out)

    Detonation Arrestor Inlet Pressure (with 50' Air Ducting Hose Attached to the DA)

    Detonation Arrestor Outlet Pressure (with 50' Air Ducting Hose Attached to the DA)

    Flame Arrestor Inlet Pressure

    Flame Arrestor Outlet Pressure

    Interlocks (Safety Shut-Downs and Alarms)

    High-High FA Inlet/Outlet & Firebox Inlet Temperature

    • Pass
    • Flag
    • Fail

    FA Backflow-Differential Pressure

    • Pass
    • Flag
    • Fail

    High-High DA Inlet/Outlet Temperature

    • Pass
    • Flag
    • Fail

    Low-Low Fuel Pressure (Pilot & Enrichment Lines)

    • Pass
    • Flag
    • Fail

    High-High Fuel Gas Pressure

    • Pass
    • Flag
    • Fail

    Low-Low Combustion Air Pressure

    • Pass
    • Flag
    • Fail

    Combustion Blower Failure

    • Pass
    • Flag
    • Fail

    High-High Process Air Pressure

    • Pass
    • Flag
    • Fail

    Process Blower Failure

    • Pass
    • Flag
    • Fail

    High High Firebox Temperature

    • Pass
    • Flag
    • Fail

    UV Scanner #1

    • Pass
    • Flag
    • Fail

    UV Scanner #2

    • Pass
    • Flag
    • Fail

    EMECS Shutdown

    Cooling and Shutting Down the Unit

    Unit End Hours

    Meter name
    Unit

    Verify Spare Chart Recorder Battery in Panel.

    • Pass
    • Flag
    • Fail

    Verify Chart Recorder Settings Sticker are on the outside of the Chart Panel.

    • Pass
    • Flag
    • Fail
    if the answer is "noneOf [PASS]"

    Get with the Shop Manager and install the Sticker on the panel.

    Meter name
    Unit

    Inspect Air Bottles

    Does the unit have Air bottles for the process inlet?

    • Yes
    • No
    • N / A
    if the answer is "oneOf [Yes]"

    Checks

    Pressure good and above 500 PSI?

    • Pass
    • Flag
    • Fail
    if the answer is "noneOf [PASS]"

    Have bottles filled. Inform Shop Manager.

    While the bottles are online perform a snoop check for leaks. Once leak check is completed block the bottles back in.

    • Pass
    • Flag
    • Fail

    Notes

    Notes or Record any Changes Made to Equipment

    360 Walkaround Inspection

    No Tools or Debris on Deck, Equipment is Secured, all Boxes are Orderly, and Inspection and Registration are Current

    • Pass
    • Flag
    • Fail
    if the answer is "oneOf [FAIL,FLAG]"

    What issues were found during the 360 Inspection?

    Verify Carseal is installed on Main Panel.

    • Pass
    • Flag
    • Fail

    Completion Sign Off

    Inspector/s Signature:

    Click here to sign

    Supervisor Signature:

    Click here to sign
Source: Envent Corporation (Community Member)

Please note that any procedure, checklist, or other document available in the MaintainX Procedure Hub is provided for general education and information only and does not constitute legal, medical, or financial advice. MaintainX makes the materials available AS IS and AS PROVIDED, without warranties of any kind. By downloading or using any such materials, you assume the risk that they may not be appropriate for your specific situation and agree that you are solely responsible for any such use, including compliance with applicable law and with meeting any conditions of product warranties.