Back

EMTOS Annual Preventative Maintenance Report

This report provides a structured record of the annual preventative maintenance performed on EMTOS equipment. Complete all applicable sections to document inspection findings, servicing activities, and operational check results in accordance with manufacturer recommendations and site procedures. Record any defects and required follow-up actions to support safe, reliable operation and future maintenance planning.
Envent Corporation
10/20/2026

EMTOS Annual Preventative Maintenance Report

The EMTOS Annual Preventative Maintenance Report documents the yearly inspection, servicing, and operational checks performed on EMTOS equipment. It records equipment condition, maintenance completed, identified defects, and recommended corrective actions to support reliable operation, reduce unexpected downtime, and maintain a complete service history.

    EMTOS Annual PM

    Unit #

    Date

    License Plate #

    Inspectors

    The annual preventative maintenance shall be conducted following an Anuual PM to ensure all equipment is fully inspected, cleaned, and functioning correctly. Inspectors should verify critical components, check for wear or damage, lubricate moving parts, and document any findings for follow-up actions.

    Unit Hours Start

    Meter name
    Unit

    Air Compressor Hours Start

    Gas Meter Start

    Is the car seal installed and intact on the main panel, with no signs of tampering or unauthorized entry?

    • Pass
    • Flag
    • Fail
    if the answer is "noneOf [PASS]"

    Check that the SO cord is connected and snug inside of the panel before energizing power to the unit.

    Check for any loose wires or disconnected wires. Reinstall and tighten to spec.

    No Power on Unit-Generator is Disconnected

    Inspect Trailer Kingpin

    Check for visible cracks, deep gouges, or severe condition

    Inspect Trailer Kingpin

    • Pass
    • Flag
    • Fail
    if the answer is "oneOf [FAIL]"

    Inspect upper coupler plate for warping, bowing, or thin spots.

    • Pass
    • Flag
    • Fail
    if the answer is "oneOf [FAIL]"

    Inspect welds connecting kingpin to trailer for signs of weld failure or cracking.

    • Pass
    • Flag
    • Fail
    if the answer is "oneOf [FAIL]"

    Upload photo of kingpin upon completion of passed inspection.

    Add or drag pictures

    Inspect trailer tires and lights

    Check tires for proper inflation and dry rotting or damage.

    • Pass
    • Flag
    • Fail

    Inspect all lights for proper operation (running lights, turn signals, brake lights).

    • Pass
    • Flag
    • Fail

    Pull break away wire and verify the trailer breaks work by driving truck forward.

    • Pass
    • Flag
    • Fail

    Inspect trailer support

    Inspect leg stands and grease all Zerk fittings.

    • Pass
    • Flag
    • Fail

    Check firebox to trailer bolts and holes for integrity.

    • Pass
    • Flag
    • Fail

    Vaporizer

    Mechanical Inspection (No Power or Propane Required)

    Open and clean Y-strainer. Inspect for propane butter, rust, or debris.

    • Pass
    • Flag
    • Fail

    Inspect power cord for damaged insulation and replace if necessary.

    • Pass
    • Flag
    • Fail

    Inspect igniter wiring and tighten electrical connections.

    • Pass
    • Flag
    • Fail

    Remove and clean burner ring and burner tips with compressed air. Replace damaged tips.

    • Pass
    • Flag
    • Fail

    Inspect thermal generator (relighter) for corrosion. Clean or replace as needed.

    • Pass
    • Flag
    • Fail

    Inspect door, hinges, latches, and locks. Repair or replace as needed.

    • Pass
    • Flag
    • Fail

    Inspect safety relief valve for damage, corrosion, or obstruction. Replace at 5-year intervals or sooner if damaged.

    • Pass
    • Flag
    • Fail

    Cycle all ball valves fully open/closed and verify locking handles are present. Replace defective valves.

    • Pass
    • Flag
    • Fail

    Inspect Acme fittings and camlocks for wear, cracks, or damaged seals. Replace as necessary.

    • Pass
    • Flag
    • Fail

    Remove vent cap and inspect insulation around vaporizer tube. Report deterioration.

    • Pass
    • Flag
    • Fail

    Remove top cover and inspect refractory and doughnut gasket condition. Verify proper positioning.

    • Pass
    • Flag
    • Fail

    Clean exterior, tighten clamps, touch up paint, and inspect overall condition.

    • Pass
    • Flag
    • Fail

    Check vaporizer thermocouple and make sure connections are secure (recrimp if necessary)

    • Pass
    • Flag
    • Fail

    Check controller to ensure the knob can be fully turned into all positions.

    • Pass
    • Flag
    • Fail

    RH80 Specific Checks

    Replace the following components if necessary

    Main Electrical Panel

    Tighten every wire termination to 1.2 Nm torque

    • Pass
    • Flag
    • Fail

    Remove BMS and check terminations.

    • Pass
    • Flag
    • Fail

    Check for open holes in each panel.

    • Pass
    • Flag
    • Fail

    Signs of rust or water.

    • Pass
    • Flag
    • Fail

    Inspect panel door gasket & conduit opening integrity.

    • Pass
    • Flag
    • Fail

    Replace or add desiccant pads.

    • Pass
    • Flag
    • Fail

    Inspect wire condition (no wire rubbing against sharp edges)

    • Pass
    • Flag
    • Fail

    Ensure spiral wire wrap is placed correctly to protect wires.

    • Pass
    • Flag
    • Fail

    Ensure wire tiedowns are operational, replace if necessary.

    • Pass
    • Flag
    • Fail

    Ignitor Electrical Panel

    Tighten every wire termination to 1.2 Nm torque

    • Pass
    • Flag
    • Fail

    Check for open holes in each panel.

    • Pass
    • Flag
    • Fail

    Signs of rust or water.

    • Pass
    • Flag
    • Fail

    Inspect panel door gasket & conduit opening integrity.

    • Pass
    • Flag
    • Fail

    Add dessicant packs if missing or replace if saturated.

    • Pass
    • Flag
    • Fail

    Inspect wire condition (no wire rubbing against sharp edges)

    • Pass
    • Flag
    • Fail

    Ensure spiral wire wrap is placed correctly to protect wires.

    • Pass
    • Flag
    • Fail

    Ensure wire tiedowns are operational, replace if necessary.

    • Pass
    • Flag
    • Fail

    Auxiliary Electrical Panel

    Tighten every wire termination to 1.2 Nm torque

    • Pass
    • Flag
    • Fail

    Signs of rust or water.

    • Pass
    • Flag
    • Fail

    Inspect panel door gasket & conduit opening integrity.

    • Pass
    • Flag
    • Fail

    Add desiccant packs if missing or replace if saturated.

    • Pass
    • Flag
    • Fail

    Inspect wire condition (no wire rubbing against sharp edges)

    • Pass
    • Flag
    • Fail

    Ensure spiral wire wrap is placed correctly to protect wires.

    • Pass
    • Flag
    • Fail

    Ensure wire tiedowns are operational, replace if necessary.

    • Pass
    • Flag
    • Fail

    Chart Recorder

    Verify plug connections and wires are tight for power, thermocouple input 1 & 2, alarm outputs, output control and ground terminals. Visually verify all ribbon cables are landed securely. Verify input cards are seated correctly and free of corrosion or damage.

    • Pass
    • Flag
    • Fail

    Replace Chart Recorder battery.

    • Pass
    • Flag
    • Fail

    Rotary Gas Meter

    Drain oil in all three chambers and refill (left, right, and center).

    • Pass
    • Flag
    • Fail

    Inspect and replace screen paper gasket on the inlet side and regular paper gasket on the outlet side.

    • Pass
    • Flag
    • Fail

    California Only: Remove gas meter and send it to be calibrated and certified.

    • Pass
    • Flag
    • Fail

    Flow Tubes

    Remove all DS-300/400 flow elements and blow out with shop air, inspect and reinsert or replace.

    • Pass
    • Flag
    • Fail

    Firebox

    Inspect fire box sight glass windows and clean if dirty (separate from nipple not by opening the union/glass nut)

    • Pass
    • Flag
    • Fail

    Remove manway door and inspect refractory on floor, roof, walls, process inlet, and burner.

    • Pass
    • Flag
    • Fail

    Verify that the stack and fire box inlet sample points are functional.

    • Pass
    • Flag
    • Fail

    Burner

    Verify burner cone integrity. Observe air gap on burner by removing burner. There should be at least ~1cm air gap around burner housing and cone. Burner should be replaced every ten years.

    • Pass
    • Flag
    • Fail

    Pull the burner and take pictures of the cone and the internals.

    Add or drag pictures

    Inspect burner damper and linkage assembly (wiggle linkage).

    • Pass
    • Flag
    • Fail

    Inspect burner refractory discharge sleeve, check for cracks or broken studs.

    • Pass
    • Flag
    • Fail

    Clean burner site glasses.

    • Pass
    • Flag
    • Fail

    Combustion Blower: Visually inspect all blower mounting bolts for rust and tightness.

    • Pass
    • Flag
    • Fail

    Replace burner gasket and reinstall burner.

    • Pass
    • Flag
    • Fail

    Manual Butterfly Valves

    4" Process Valve: Open gear assembly and grease gears.

    • Pass
    • Flag
    • Fail

    Main Process Valve: Open gear assembly and grease gears.

    • Pass
    • Flag
    • Fail

    Dilution Valve: Open gear assembly and grease gears.

    • Pass
    • Flag
    • Fail

    Automatic Process Isolation Valve

    Visually inspect mounting hardware and support brackets for signs of stress or wear.

    • Pass
    • Flag
    • Fail

    Blowers & Compressors Motor terminals

    Remove electrical motor cover, inspect wire terminations. Replace connectors if needed. Connectors should be industrial grade.

    • Pass
    • Flag
    • Fail

    Verify Motor Terminal gasket integrity.

    • Pass
    • Flag
    • Fail

    Igniter/Ignition Transformer

    Clean igniter, verify no corrosion on the connection point to transformers or to the igniter. Mark igniter position before removing. Replace if necessary.

    • Pass
    • Flag
    • Fail

    Maxon or Eclipse Valves (SSOV 1& 2)

    Open side panels, inspect gasket, check for water intrusion.

    • Pass
    • Flag
    • Fail

    Check wire terminations.

    • Pass
    • Flag
    • Fail

    Add oil if applicable.

    • Pass
    • Flag
    • Fail

    High Temp. Thermocouple

    Replace High Tempertaure Thermocouple. Be sure to document Calibration before install.

    • Pass
    • Flag
    • Fail

    Combustion Thermocouple

    Replace Combustion Thermocouple.

    • Pass
    • Flag
    • Fail

    Process Blower

    NYB Blower Alignment Checks

    This procedure outlines the steps for performing quarterly alignment checks on NYB Blowers, ensuring all components are properly aligned and the area is safe and clean post-inspection.

    Pre-Inspection Setup

    Alignment Inspection

    Measure Blower Housing Centering at Pillow Blocks

    Using a tape measure, measure the distance from the outside edge of each pillow block bearing housing to the edge of the blower housing at all four measurement points (top, bottom, left, and right, or as applicable to the equipment configuration). Record each measurement and compare the values to verify the blower rotor and shaft assembly are centered within the housing.

    When taking measurements:

    if the answer is "oneOf [Record all measurements to the nearest 1/16 inch (or applicable site standard).]"

    Record Measurements:

    Is the alignment within the acceptable range?

    • Yes
    • No
    • N / A

    Post-Inspection Tasks

    Reinstall the Shaft cover.

    • Yes
    • No
    • N / A

    Was the area cleaned after inspection?

    • Yes
    • No
    • N / A

    NYB Blower Bearing Lubrication

    This procedure outlines the steps for purging the bearings of an NYB blower, including inspection, cleaning, lubrication, and testing.

    Preparation

    Inspection and Cleaning

    Inspect bearings and bushing

    • Pass
    • Flag
    • Fail

    Lubrication

    Remove the tubing from the grease injection points on each bearing to allow direct access to the grease fittings and to verify that grease can flow freely into the bearing. Inspect the tubing, fittings, and connectors for restrictions, hardened grease, contamination, damage, or blockages that could prevent proper lubrication.

    • Pass
    • Flag
    • Fail
    if the answer is "noneOf [PASS]"

    If any tubing is damaged, kinked, or plugged, replace it before returning the system to service.

    This ensures hardened, contaminated, incompatible, or degraded grease is removed from the lubrication path and that the tubing is completely charged with fresh grease.

    Visually inspect the discharged grease for signs of contamination, moisture, dirt, discoloration, or metal particles that could indicate lubrication or bearing issues.

    • Pass
    • Flag
    • Fail

    Greasing a stationary bearing can rapidly build internal pressure, forcing grease against the seals and potentially causing seal damage or seal blowout. Excessive pressure can also lead to overheating, premature bearing failure, and reduced lubricant effectiveness. If shaft rotation cannot be achieved, stop the lubrication activity and consult maintenance supervision before proceeding

    This also helps prevent contamination from being drawn back into the bearing.

    The appearance of fresh grease confirms that old grease has been displaced and the bearing cavity has been replenished.

    Vapor Seal Lubrication

    The vapor seal lubrication point and the bearing grease fitting are separate components. Do not introduce anti-seize into the bearing grease fittings, grease lines, or bearing housing. Anti-seize contamination will damage the bearing lubricant, accelerate wear, and can lead to premature bearing failure. Bearings shall only be lubricated with Mobilgrease XHP 222 (Blue) grease.

    The vapor seal is located between the bearing housing and the blower casing where the shaft enters the the housing. Its purpose is to prevent process vapors from migrating along the shaft and reaching the bearing assembly. The fitting closest to the fan housing is typically the vapor seal lubrication point. The fitting located on the bearing housing is the bearing grease fitting. Always verify fitting locations before adding any lubricant. Verify the correct lubrication point before applying lubricant.

    Shaft Cover Install

    Prior to reattaching the blower cover, inspect all mating surfaces, gaskets, O-rings, and sealing areas for damage, debris, corrosion, or residual gasket material. Clean the sealing surfaces as necessary to ensure a proper seal and prevent air leakage. Replace any damaged gaskets, O-rings, or sealing components before reassembly. Carefully position the blower cover onto the housing, ensuring it is properly aligned with the locating features and does not contact the rotor, shaft, or internal components during installation. Install all mounting hardware finger-tight initially to ensure the cover seats evenly against the housing. Tighten mounting bolts in a crisscross or star pattern to evenly distribute clamping force and prevent cover distortion. Torque all fasteners to the manufacturer's specification where applicable. Verify that no tools, rags, hardware, or foreign material remain inside the blower housing prior to fully securing the cover.

    After the cover is installed:

    Testing

    Turn on the blower, let it run for 15 minutes, and take temperature of bearings. Bearing Temp should not exceed 200F in Ambient conditions.

    • Pass
    • Flag
    • Fail

    Does the blower make unusual screeching sounds after the first 5 seconds of startup?

    • Yes
    • No
    • N / A
    if the answer is "oneOf [Yes]"

    Check the belt Tension.

    Both Process Blower stickers in place, the lubrication record and the zerk injection lubrication directions.

    • Pass
    • Flag
    • Fail

    Power ON Unit: Connect Generator and Propane

    Inspect ultrasonic/float level switch housing for moisture and tighten all terminations. Verify operation.

    • Pass
    • Flag
    • Fail

    Inspect power cord for damaged insulation and replace if necessary.

    • Pass
    • Flag
    • Fail

    Inspect igniter wiring and tighten electrical connections.

    • Pass
    • Flag
    • Fail

    Remove and clean burner ring and burner tips with compressed air. Replace damaged tips.

    • Pass
    • Flag
    • Fail

    Inspect thermal generator (relighter) for corrosion. Clean or replace as needed.

    • Pass
    • Flag
    • Fail

    Inspect door, hinges, latches, and locks. Repair or replace as needed.

    • Pass
    • Flag
    • Fail

    Inspect safety relief valve for damage, corrosion, or obstruction. Replace at 5-year intervals or sooner if damaged.

    • Pass
    • Flag
    • Fail

    Cycle all ball valves fully open/closed and verify locking handles are present. Replace defective valves.

    • Pass
    • Flag
    • Fail

    Inspect Acme fittings and camlocks for wear, cracks, or damaged seals. Replace as necessary.

    • Pass
    • Flag
    • Fail

    Remove vent cap and inspect insulation around vaporizer tube. Report deterioration.

    • Pass
    • Flag
    • Fail

    Remove top cover and inspect refractory and doughnut gasket condition. Verify proper positioning.

    • Pass
    • Flag
    • Fail

    Clean exterior, tighten clamps, touch up paint, and inspect overall condition.

    • Pass
    • Flag
    • Fail

    Air Compressor

    Ensure a 0-150 PSI Pressure Gauge is installed before the regulator.

    • Pass
    • Flag
    • Fail

    Verify the compressor stops at ~135 PSIG in the main tank.

    • Pass
    • Flag
    • Fail

    Panel Lights

    Activate each button and switch to confirm it lights up when turned on.

    • Pass
    • Flag
    • Fail

    Area Lights

    Inspect all area lights by turning them on, replace bulbs as needed, and check for rust or water damage.

    • Pass
    • Flag
    • Fail

    Vaporizer

    Functional Checks (Power and Propane Required)

    Soap-test all valves, fittings, regulators, Acmes, camlocks, and piping for leaks.

    • Pass
    • Flag
    • Fail

    Verify igniter produces a strong spark.

    • Pass
    • Flag
    • Fail

    Inspect pilot assembly and ignition system. Replace components as necessary.

    • Pass
    • Flag
    • Fail

    Inspect relight module operation and condition. Replace if corroded or non-functional.

    • Pass
    • Flag
    • Fail

    Inspect thermo-probe wiring and gas valve connections. Tighten and repair as required.

    • Pass
    • Flag
    • Fail

    Verify pilot solenoid valve operation and check for leakage.

    • Pass
    • Flag
    • Fail

    Verify burner ring lights evenly around entire circumference.

    • Pass
    • Flag
    • Fail

    Verify thermo-probe shuts burner off at approximately 120°F vapor temperature.

    • Pass
    • Flag
    • Fail

    Verify fuel gas valve transitions correctly through OFF → PILOT → ON positions.

    • Pass
    • Flag
    • Fail

    Chart Recorder

    Verify the display powers up with no error codes or flickering

    • Pass
    • Flag
    • Fail

    Pen & Paper Operation: Correct date and time stamp, legible temperature recordings.

    • Pass
    • Flag
    • Fail

    Temperature Accuracy: Compare temperature reading with High Limit Controller and verify readings are within 50F of each other.

    • Pass
    • Flag
    • Fail

    Output Control: Test output control by placing in manual and driving the mod motor with the arrow keys.

    • Pass
    • Flag
    • Fail

    Alarm Outputs: At 1400F, verify the top green panel light turns on, and the Process Isolation Valve opens.

    • Pass
    • Flag
    • Fail

    Alarm Outputs: At 1550F, verify the top red panel light turns on. If temperature cannot be raised above 1550F, adjust Alarm setpoints A2S1 and A2S2 below current temperature to simulate.

    • Pass
    • Flag
    • Fail

    Process Valve

    Raise unit above 1400°F and verify valve fully opens and closes promptly. If the valve takes more than 30 seconds to close, replace the air dump valve.

    • Pass
    • Flag
    • Fail

    Burner

    Verify that the modulating actuator moves to high during the 90 second high fire purge and moves to low when the BMS says to start.

    • Pass
    • Flag
    • Fail

    Interlocks

    High Limit Temperature: While BMS is going into purge, change the set point below the chart recorder temperature and verify a "stoppage" in BMS activity.

    • Pass
    • Flag
    • Fail

    High Limit Temperature: While unit is running, lower high temperature set point below chart recorder temperature and verify burner shut down.

    • Pass
    • Flag
    • Fail

    UV Scanner: While unit is running, remove UV scanner from unit. Do not expose to direct sunlight. Cover optical lens and ensure that the unit shuts down.

    • Pass
    • Flag
    • Fail

    LEL Analyzer: Calibrate LEL in accordance with the procesures, verify analyzer is not bypassed by valves or jumped wires behind LEL controller.

    • Pass
    • Flag
    • Fail

    LEL Analyzer: Test high LEL shutdown by lowering the setpoint to 0%. (Add a bias if current reading is 0%) Verify the unit shuts down. Remove any added bias.

    • Pass
    • Flag
    • Fail

    Process Blower Pressure Switch: Open cover of pressure switch and verify that sensor is not jumped. Remove tubing from sensor and verify that interlock is tripped on BMS.

    • Pass
    • Flag
    • Fail

    Process Blower Pressure Switch: Verify on the pressure switch box that one wire is on common and one wire is on Normally Open.

    • Pass
    • Flag
    • Fail

    Combustion Blower Pressure Switch: Open cover of pressure switch and verify that sensor is not jumped. Remove tubing from sensor and verify that interlock is tripped on BMS.

    • Pass
    • Flag
    • Fail

    Combustion Blower Pressure Switch: Verify on the pressure switch box that one wire is on common and one wire is on Normally Open.

    • Pass
    • Flag
    • Fail

    FA Temperature Switch: Remove temperature switch. Wrap heating element around probe, set temperature to 410°F. Verify contacts open with ohms meter at 400°F. (Different from Test Fire)

    • Pass
    • Flag
    • Fail

    Firebox and Main Panel

    Scan the entire exterior firebox wall with a temperature gun and record any areas exceeding 200°F.

    • Pass
    • Flag
    • Fail

    Verify Carseal is installed on Main Panel.

    • Pass
    • Flag
    • Fail

    Are the unit aesthetics in good condition? (Flag is in need of paint and signs of rust)

    • Pass
    • Flag
    • Fail
    if the answer is "noneOf [PASS]"

    Attach photos

    Add or drag pictures

    Vaporizer Serial Number and Year:

    Burner Serial Number and Year:

    DA Cell Serial Number and Year Manufactured:

    FA Cell Serial Number and Year Manufactured:

    Technician Closure Signature

    PM Lead

    PM Lead Signature

    Click here to sign

    Supervisor Closure Approval Signature

    Quality Check Name

    Quality Check Signature

    Click here to sign
Source: Envent Corporation (Community Member)

Please note that any procedure, checklist, or other document available in the MaintainX Procedure Hub is provided for general education and information only and does not constitute legal, medical, or financial advice. MaintainX makes the materials available AS IS and AS PROVIDED, without warranties of any kind. By downloading or using any such materials, you assume the risk that they may not be appropriate for your specific situation and agree that you are solely responsible for any such use, including compliance with applicable law and with meeting any conditions of product warranties.