Back

Inspector's Checklist for Paving

Use this inspector's checklist guide to help with on-the-spot recording of findings and comments. This hecklist helps to clarify inspection responsibilities, controls inspection activities and provides a report of inspection activities.
MaintainX
07/22/2022

Inspector's Checklist for Paving

Use this inspector's checklist guide to help with on-the-spot recording of findings and comments. This hecklist helps to clarify inspection responsibilities, controls inspection activities and provides a report of inspection activities.

    Name of Project:

    Permit #:

    Paving Contractor/Asphalt Producer:

    Plant Location:

    Before Paving:

    Ensure that asphalt contractors and producers are all on the approved lists provided annually by our Lab.

    • Pass
    • Flag
    • Fail

    Remind Contractor to implement paving Policy and Procedures received from you in the pre-construction meeting.

    • Pass
    • Flag
    • Fail

    Verify that grade is true to County approved cross section and alignment. Subgrade soil has to be free of ruts, contamination, excess dust, stone larger than 3 inches, mud, frozen materials, and recycled materials.

    • Pass
    • Flag
    • Fail

    Witness and approve of Proof-rolling but not many days before paving, as approvals expire if it rains.

    • Pass
    • Flag
    • Fail

    Before paving, subgrade has to be still firmly compacted, unaffected by weather or construction traffic

    • Pass
    • Flag
    • Fail

    Unless otherwise specified, subbase material must be CR-6 stone mix with 6O typical compacted thickness.

    • Pass
    • Flag
    • Fail

    Before tack-coating, the existing HMA course must be free of puddled water, milling debris, defects, and trash.

    • Pass
    • Flag
    • Fail

    Before applying tack-coat, utilities must be sufficiently raised to allow for the approved HMA thickness.

    • Pass
    • Flag
    • Fail

    Tack must be applied thinly but evenly on existing course and all vertical edges (joints, curbs, utility edges).

    • Pass
    • Flag
    • Fail

    Ensure that a Technician with current Certification and copies of our Policy & Procedures is on site before paving starts.

    • Pass
    • Flag
    • Fail

    During Paving:

    Observe arriving loads for proper mix size, minimal segregation, consistent color, and being tarp-covered

    • Pass
    • Flag
    • Fail

    Collect and check asphalt delivery tickets for correct information (project name, mix ID, tonnage, time, etc.).

    • Pass
    • Flag
    • Fail

    Check HMA temperature while being loaded into the paver, and/or behind the roller, after its first pass.

    • Pass
    • Flag
    • Fail

    Paver to maintain correct line, grade, and cross slope; and to minimize automatic controls adjustment.

    • Pass
    • Flag
    • Fail

    Paver to maintain calculated speed that minimizes its stop/start movements without depleting its hopper.

    • Pass
    • Flag
    • Fail

    Rolling to be as continuous as possible, and at a consistent “walking speed” during all compaction stages.

    • Pass
    • Flag
    • Fail

    Paving equipment and vehicles should be adequate & sufficient for the weather and the job, and leakage free.

    • Pass
    • Flag
    • Fail

    Joints should be tight and FLUSH with adjacent surfaces. Longitudinal joints to be overlapped per MD SHA.

    • Pass
    • Flag
    • Fail

    Mat should have uniform appearance, free of visible marks and defects, except for a line along longitudinal joints.

    • Pass
    • Flag
    • Fail

    Technician must call Inspector prior to core cutting & box sampling so Inspector can witness it, if available.

    • Pass
    • Flag
    • Fail

    Contractor must cut QA cores for the County Inspector on site, and cores for his own mandatory QC testing.

    • Pass
    • Flag
    • Fail

    Contractors must provide 5 cores/mix/day with noted locations unless otherwise instructed by Inspector

    • Pass
    • Flag
    • Fail

    QA cores shall come with Cores Lab-Analysis form, and behind-t-paver box samples with a HMA-1 form.

    • Pass
    • Flag
    • Fail

    Document on CTR & your report: weather conditions, suspicious rollers’ type/size, and other issues.

    COMMENTS:

    This is to certify that suspected asphalt/paving problems were tactfully conveyed to Contractor’s Foreman for his cooperation, then to the District Engineer and Lab Engineer at a.m./ p.m. of the day of paving when Contractor failed/refused to make adjustments that may correct, prevent, or reduce such problems.

    Inspector’s Name:

    Date:

    • Pass
    • Flag
    • Fail
Source: MaintainX (Community Member)

Please note that any procedure, checklist, or other document available in the MaintainX Global Procedure Library is provided for general education and information only and does not constitute legal, medical, or financial advice. MaintainX makes the materials available AS IS and AS PROVIDED, without warranties of any kind. By downloading or using any such materials, you assume the risk that they may not be appropriate for your specific situation and agree that you are solely responsible for any such use, including compliance with applicable law and with meeting any conditions of product warranties.