This procedure is used to record what is being isolated, the energy sources involved, and the lockout equipment to be applied, so the isolation can be carried out and verified safely under Part 2.
Manaaki Whenua Landcare ResearchI
03/23/2026

Isolation Permit Part 1

This procedure outlines the first part of the isolation (lockout) permit, which identifies the equipment and energy sources to be isolated before work begins. It guides the permit issuer and receiver through the work details, other required permits, WorkSafe notification, personnel, tools and equipment, and the toolbox talk, then the authorization, followed by a description of the equipment to be isolated, the energy sources, and the isolation equipment to be used.

    Permit to Work

    Work Details

    Enter Work Scope

    Enter Work Location

    Select other types of permits required to complete this task

    Notifiable Works

    Is the work WorkSafe Notifiable?

    if the answer is "oneOf [Yes]"

    Enter the name of the person who notified WorkSafe

    if the answer is "oneOf [Yes]"

    Date WorkSafe notified

    Attach evidence of notification if available

    Add or drag pictures

    Personnel Details

    Enter Permit Receiver details

    Person and Company Name and contact number

    Enter Permit Issuer details

    Name and contact number

    Enter Safety Observer details

    Tools and Equipment

    List required tools and equipment

    Do any tools/equipment require certification?

    if the answer is "oneOf [Yes]"

    Are all certifications in date?

    if the answer is "oneOf [No]"

    Do not start work until item is either certified or replacement certified item is sourced

    Toolbox Talk

    Enter names and roles of attendees

    Toolbox Talk Confirmation Signatures

    By signing this document you confirm your attendance at the toolbox talk and that you understand and will accept the Permit requirements

    Click here to sign

    Permit Authorisation

    All isolations have been tested and verified?

    Stakeholders have been notified?

    This Permit is valid from

    To

    Permit Receiver Signature

    Click here to sign

    Permit Issuer Signature

    Click here to sign

    Description of equipment to be isolated

    Source of Energy

    if the answer is "oneOf [Other]"

    If 'Other' list energy source

    Isolation Equipment

    if the answer is "oneOf [Other]"

    If 'Other' list isolation equipment

Source: Manaaki Whenua Landcare ResearchI (Community Member)

Please note that any procedure, checklist, or other document available in the MaintainX Procedure Hub is provided for general education and information only and does not constitute legal, medical, or financial advice. MaintainX makes the materials available AS IS and AS PROVIDED, without warranties of any kind. By downloading or using any such materials, you assume the risk that they may not be appropriate for your specific situation and agree that you are solely responsible for any such use, including compliance with applicable law and with meeting any conditions of product warranties.